Newark and Sherwood District Council
Cabinet, Tuesday 14 October 2025 at 6.00pm

HRA Development Programme - Acquisition of S106 Homes at Rainworth (Key Decision)

Approved Executive 1 paper

AI summaryNewark and Sherwood Cabinet approves buying 20 S106 affordable homes from Arkwood at Rainworth, lifting Phase 6 of its housing programme by £200,000 to £11,150,000, with delegated authority to finalise terms.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBusiness case for 20 S106 homes at Rainworth approved
Money£200,000 increase to £11,150,000Phase 6 capital programme uplift, financed from S106 receipts
What happens nextDirector to finalise terms and contractDelegated to Director of Housing, Health and Wellbeing
Who it affectsRainworth housing register applicantsAdds 20 affordable rent homes to council stock

What was decided

Cabinet approved the business case to acquire 20 S106 properties from Arkwood Developments Ltd at Rainworth, subject to Arkwood completing its own site purchase. Report 2.1, P9

Delegated authority was given to the Director of Housing, Health and Wellbeing, in consultation with the Portfolio Holder for Housing, to finalise terms and enter the contract. Report 2.1

Cabinet approved increasing the Phase 6 new build capital programme by £200,000 to £11,150,000, financed as set out in the table at paragraph 3.3. Report 3.3, P30

Why

There is clear demand: the housing register shows 174 applicants eligible for one bed, 133 for two bed, 67 for three bed, 16 for four bed, and 92 for supported older persons housing; recent Rainworth lettings attracted between 29 and 120 bids per property. Report P14, P15, 2.5

The deal offers value for money: a financial appraisal shows a 26 year payback, within the 30 year business plan, and compares favourably with the council's 2024-25 average build cost of £210,000 per unit. Report 3.4, 2.6, P18

There is strategic justification: reduced Registered Provider interest in S106 means the site is unlikely to come forward without a confirmed partner, and the council has exhausted its HRA land bank of multi-unit sites while Phase 6 still has capacity for 14 further units. Report 2.9, 2.10, 2.11

What happens next

The Director of Housing, Health and Wellbeing will finalise property types, specifications and contract terms with Arkwood, and enter into the purchase contract, subject to Arkwood successfully acquiring the site. Report 2.1, P9

Capital programme for Phase 6 will be revised to reflect the new £11,150,000 total and revised funding mix. Report 3.3, P30

The money

  • £200,000 Additional budget required to acquire the 20 S106 units at Rainworth Report 3.3
  • £11,150,000 Revised total Phase 6 capital programme after uplift Report 3.3, P30
  • £10,950,000 Original Phase 6 budget set in October 2023 Report 1.1, 3.1, 3.3
  • £2,364,430 Affordable Housing S106 receipts available as of September 2025 to support Phase 6 Report 3.2, P30
  • £1,072,532 Increase in S106 receipts since the October 2023 report Report 3.2
  • £210,000 Council's average build cost per unit in 2024-25, including land and abnormals Report 2.6, P18
  • 26 years Payback period from the financial appraisal, within the 30 year business plan Report 3.4
  • £2.364m Revised S106 Contributions share of Phase 6 funding Report P30

Options considered

  • Chosen: Acquire 20 S106 properties from Arkwood Developments Ltd at Rainworth. Meets demonstrated demand, offers value for money, supports a stalled site, and uses up remaining Phase 6 capacity without needing new land Report 2.1, 2.3, 2.5, 2.9, 2.10, 2.11

Implications

  • Equalities: No adverse equality implications; delivery of M4(3) adapted properties will support disabled residents to live independently at home for longer. Report 3.5, P33
  • Legal: Cabinet is the appropriate decision body. Legal Services will need to be instructed on contractual and land matters; the purchase is conditional on Arkwood completing its own acquisition of the site. Report 3.6, P9

Who and where

  • Households on the housing register eligible for general needs homes in Rainworth, including 174 one-bed, 133 two-bed, 67 three-bed and 16 four-bed applicants Report P14, 2.5
  • Older people on the housing register needing supported housing (92 applicants) Report P14, 2.5
  • Disabled residents who will benefit from M4(3) adapted properties Report 3.5, P33
  • Future council tenants in Rainworth Report 2.1, 2.3
  • Arkwood Developments Ltd, the council's arms-length development company Report 1.6, 2.1

Timeline

  • 2016: Original council house development programme launched to deliver 335 homes Report 1.1
  • October 2023: Cabinet approved a 50-unit extension, setting Phase 6 budget at £10,950,000 Report 1.1, 3.1
  • 23 July 2024: Cabinet approved expanding the development programme to include acquisitions as well as council-built homes Report 1.2, P36
  • 2024/2025: Recent Rainworth council lettings received between 29 and 120 bids per property, evidence of strong demand Report P15
  • September 2025: S106 receipts available for Phase 6 stood at £2,364,430 Report 3.2
  • 14 October 2025: Cabinet approves acquisition of 20 S106 homes at Rainworth and uplifts Phase 6 budget by £200,000 to £11,150,000 Report 3.3

Plain English for the jargon

  • S106: Section 106 planning obligation requiring developers to provide affordable housing or contributions as part of a planning consent
  • HRA: Housing Revenue Account, the ring-fenced account landlords use for income and spending on council housing
  • Phase 6: Stage of the council's new build housing development programme, currently budgeted for 50 units
  • Arkwood Developments Ltd: The council's arms-length development company, acting as developer and seller on this scheme
  • M4(3): Building Regulations standard for wheelchair accessible or adaptable dwellings
  • Affordable rent: Rented homes let at no more than 80 percent of local market rent
  • 1-4-1 Receipts: HRA receipts the council can keep to fund new affordable housing, equal to the value of each Right to Buy sale
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item313

Resolved

That Cabinet: a) approve the Business Case for the acquisition of 20, S106 properties at Rainworth from Arkwood Developments Ltd; b) approve that delegated authority be granted to the Director - Housing, Health & Wellbeing, in consultation with the Portfolio Holder for Housing, to finalise terms (including, but not limited to property type and specification) and enter into contract with Arkwood Developments Ltd. f or the purchase of 20 x S106 properties on the terms set out in exempt Appendix 1 ; and c) approve that the Capital programme for Phase 6 of the new build programme is increased by £200,000 to £11,150,000 financed as shown in the table at 3.3.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Background

1.1In October 2023, Cabinet approved a 50-unit extension to the original council house development programme launched in 2016 to deliver 335 homes. Following the approval of the 50-unit extension, the budget for Phase 6 was set at £10.950m.

1.2In July 2024, Cabinet also approved to expand the definition of the development programme to specifically include acquisitions as well as council-built homes.

1.3The purchase of S106 properties, former right to buy properties or properties on the open market can be a viable option to increase the Councils housing stock, particularly where the purchase supports a stalled site or where the properties are in a location where there is limited land available for the Council to purchase and build directly and there remains an unmet demand for council housing.

1.4Historically, the Council has intervened in the housing market where it is appropriate and necessary to ensure the delivery of affordable housing and where a Registered Provider has been unable to do so. This has previously included the purchase of two social rented units at Nottingham Road, Southwell in 2021 (Policy and Finance Committee - 23 September 2021 refers); 16 social rented units at Ash Farm, Farnsfield in 2016, (Agenda Item 4, Policy & Finance - 28 July 2015 refers) and eight units at Station Road, Collingham (Agenda Item 19, 23 July 2024 refers).

1.5It was agreed by Cabinet that where there is a business case for acquisition and where the business case is approved by Cabinet, that strategic acquisition can contribute to the overall development programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HRA Development Programme: Acquisition of S106 Homes at Rainworth (Key Decision)Decisions 649 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, present
SC
Councillor Susan CrosbyCommittee Member, apologies
LB
Councillor Lee BrazierCommittee Member, present
SF
Councillor Simon FordeCommittee Member, present
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected
SK
Sanjiv KohliOfficer, expected

All 21 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. HRA Development Programme - Acquisition of S106 Homes at Rainworth (Key Decision)This decision
  2. Homes England Compliance Audit Report 2021-22 - HRA 5 Year Development ProgrammeAgreed
  3. Homes England Compliance Audit Report 2020-21 - HRA 5 Year Development ProgrammeAgreed
  4. HRA New Build Development UpdateAgreed

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open