Written from the decision and the officer reportPDF Pro
OutcomeAgreedAgreed unanimously at Policy and Performance Improvement Committee
MoneyNo direct financial implicationsConfirmed in the report's financial section
What happens nextAwaab's Law phase 1 preparationPhases 2 and 3 expected in 2026 and 2027
Who it affectsCouncil tenants and leaseholdersAcross housing stock including blocks and community centres
What was decided
The Committee unanimously noted the exceptions to performance of housing compliance functions, including gas, fire, asbestos, water, stair lifts, EICRs, solid fuel and oil servicing. Report 2.0, P18, 2.1, 2.3, 2.4, 2.5, 2.6, 2.7
Members noted interim arrangements for monitoring damp and mould ahead of Awaab's Law, using ad hoc reports from the new Housing Management System until full reporting is configured. Report 1.5, P16
The Committee noted ongoing actions to improve and maintain performance, linked to Community Plan Ambitions 2 (decent and affordable housing) and 7 (top performing, modern Council). Report P3, P6
Why
The report provides assurance on work undertaken to ensure tenant safety and compliance with regulatory standards. Report P4, 1.0
Performance is rated against targets set within 2% of 100% as Green, with exceptions reported to give Cabinet oversight of landlord responsibilities. Report P10, 1.1, 1.3
What happens next
Domestic Water Risk Assessments will continue alongside the gas servicing programme, with all domestic properties expected to receive a WRA within a full year of service. Report 2.4
Outstanding Fire Risk Assessments will be completed between January 2026 and March 2026, and an Access Plan is being developed to reduce no-access issues for gas servicing. Report 2.1, P23, P19
Domestic asbestos compliance is being progressed towards 100% by the end of the financial year, and EICR changes from October 2025 require new tenants to receive an EICR within 28 days of tenancy start. Report 2.3, 1.5
Options considered
Chosen: Continue with current compliance programme and note exceptions. Provides assurance on tenant safety and regulatory compliance while ongoing improvement work continues. Report P4, 2.0
Rejected: Wait for Awaab's Law system reporting before monitoring damp and mould formally. An interim ad hoc reporting arrangement has been put in place to maintain visibility of damp and mould performance until the new Housing Management System is configured. Report 1.5
Implications
Financial: No direct financial implications arising from this report. Report P33
Legal: No direct legal implications arising from this report, though changes from October 2025 require Social Landlords to issue new tenants with an EICR within 28 days. Report P34, 1.5
Equalities: No direct equalities implications, though individual tenant circumstances are considered when managing compliance services. Report P34
Risk: Two properties remain without a valid EICR, eight without a current gas safety certificate, and solid fuel servicing sits at 90% compliance rated Red. Report 2.6, P18, 2.7
Who and where
Council tenants receiving gas, fire, asbestos, water, electrical, stair lift, solid fuel and oil safety services Report 1.1, 2.0
Residents of 106 blocks and 31 community centres covered by Fire Risk Assessments Report 2.1
New incoming tenants who must receive an EICR within 28 days of tenancy start from October 2025 Report 1.5
Timeline
June 2025: Council received a Government letter ahead of Awaab's Law phase 1 and electrical safety standard changes Report P16
October 2025: New EICR requirements came into force for Social Landlords Report 1.5
1 November 2025: Multi-service programme commenced to undertake Domestic Water Risk Assessments alongside the Gas Service Report 2.4
31 December 2025: Performance position reported for Quarter 3 2025-26 Report P3, 1.0
January to March 2026: Outstanding Fire Risk Assessments scheduled for completion Report 2.1, P23
2026 and 2027: Further phases of Awaab's Law expected to expand its scope Report P16
End of 2025/26 financial year: Target of 100% domestic asbestos compliance Report 2.3
Plain English for the jargon
Awaab's Law: New social housing regulations setting strict timescales for the investigation and rectification of damp and mould, being introduced in phases from 2025.
EICR: Electrical Installation Condition Report, a certificate confirming the safety of a property's electrical installations.
FRA: Fire Risk Assessment, a review of fire safety arrangements in blocks and community centres.
RAG Rating: Red, Amber, Green performance rating system, with Green at 100%, Amber within 2% of target, and Red below 2%.
WRA: Water Risk Assessment, a check of water systems for safety and Legionella risk.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item203
Resolved
AGREED (unanimously) and noted that: a) the exceptions to performance of the housing service compliance functions; b) interim arrangements for monitoring damp and mould ahead of introduction of Awaab’s Law; and c) the ongoing actions to improve and maintain performance. The recommendations are linked to two ambitions located in the Community Plan: Ambition 2: Increase the supply of housing, in particular decent homes that residents can afford to buy and rent, as well as improving housing standards; and Ambition 7: Be a top performing, modern and accessible Council that get its everyday services right for the residents and businesses that it serves .
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to Policy & Performance Improvement Committee
Report to: Policy & Performance Improvement Committee – 16 March 2026 Director Lead: Suzanne Shead - Director of Housing, Health & Wellbeing Lead Officer: Wayne Fox – Business Manager Building Safety & Asset Investment
Report Summary
Report Title Quarter 3 2025-26 - Housing Compliance Assurance Report To provide the performance position as of 31 December 2025 Purpose of Report (Quarter 3) for Housing related compliance and update on activities in the service area. That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangements for monitoring damp and mould ahead of introduction of Awaab’s Law; and c) the ongoing actions to improve and maintain performance. Recommendations This links to two ambitions in our Community Plan: Ambition 2: Increase the supply of housing, in particular decent homes that residents can afford to buy and rent, as well as improving housing standards and, Ambition 7: Be a top performing, modern and accessible Council that get its everyday services right for the residents and businesses that it serves
Reason for To provide assurance on the work undertaken to ensure the Recommendation safety of tenants and compliance with the regulatory standards.
1.0Background This report provides Members with the performance of housing compliance services at the end of December 2025, focusing on exceptions performance, which is outside the Council’s target parameters.
The full performance summary is shared with SLT; the Portfolio Holder for Housing and discussed as a standard agenda item for the Tenant Engagement Board meetings ensuring that Health & Safety are at the heart of our conversations and actions. Performance is also discussed at Policy and Performance Committee (PPIC) before being presented quarterly at Cabinet (Performance) to ensure there is oversight at Board level.
1.1This report sets out the Council’s performance against the Council’s legal and regulatory landlord responsibilities for a range of building safety measures including fire protection, gas, asbestos, electrical and water. Further information on the Council’s responsibilities can be found here https://www.gov.uk/government/publications/safety-and-quality-standard.
1.2Full details of these performance indicators along with associated commentary are included at Appendix 1 to this report.
1.3The Council’s performance in the report is rated as set out in the table below - as recommended by external auditors and the Regulator of Social Housing:
RAG Rating Old Rating New Rating Colour in 2023/24 2024/25 Appendix Report Green At Target 100% Amber Within 2% 98 – 99.9% Red Below 2% 0 – 97.99%
1.4The report also included information on the number of damp and mould cases and our performance in this area including:
• number of inspections conducted. • number of works order raised and completed. • average time taken to complete works. • percentage completed on time. • average cost of repairs not capitalised (Priority 1 & Priority 2 only)
across three categories (P1-P3) based on the amount and difficulty of the work and in total. The description for each category is listed below and can be found on page 3 of Appendix 1 Key Performance Reporting Scorecard for Housing Compliance.
• P1 - Emergency e.g. excessive mould or major leak. • P2 - Minor repair works and mould wash. • P3 - Major Works undertaken by Asset Team e.g. new Damp Proof Course
1.5Due to the move to the new Housing Management System, an interim reporting arrangement is in place as the new system is set up for Awaab’s Law (Damp & Mould) and the associated reporting arrangements required. This means temporarily, the team will produce an ad hoc report that draws down all repairs with a reference to damp and mould, when Awaab’s Law is in force, the system is set up to report automatically from a specific contractor code that relates only to damp and mould repairs, ensuring our information on performance is as accurate as possible.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy & Performance Improvement Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
Q4 Community Plan Performance ReportAGREED (unanimously) that: a) the Community Plan Performance, the Annual Community Plan Performance and the Complianc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.