AI summaryCabinet noted Quarter 4 2025-26 housing compliance performance for Newark and Sherwood, covering exceptions in gas, fire, asbestos, water and electrical checks, and interim damp and mould reporting ahead of Awaab's Law.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted exceptions, damp and mould interim plans, and improvement actions
MoneyNo direct financial implications arising from the report
What happens nextPrepare for Awaab's Law phasesPhase 1 due from Autumn, two further phases expected in 2026 and 2027
Who it affectsCouncil housing tenantsTenants in domestic properties, blocks and community centres
What was decided
Cabinet noted exceptions to housing compliance performance at the end of March 2026, including gas servicing at 99.94%, fire safety checks amber, asbestos at 98.41%, and solid fuel and oil servicing rated red. Report P6, 1.1, 2.1, 2.2, 2.4, 2.8
Cabinet noted interim reporting arrangements for damp and mould using an ad hoc report, ahead of the new Housing Management System being set up for Awaab's Law. Report P6, 1.8
Cabinet noted ongoing actions to improve and maintain compliance performance and provide assurance on tenant safety and regulatory standards. Report P6, P7, 1.1, 1.2
Why
To give assurance on work to keep tenants safe and meet the Council's legal and regulatory landlord responsibilities for fire protection, gas, asbestos, electrical and water safety. Report P7, 1.1, 1.3
The report links to Community Plan Ambition 2 on increasing decent housing supply and standards, and Ambition 7 on being a top performing modern council. Report P7
Performance is also reviewed by SLT, the Housing Portfolio Holder, the Tenant Engagement Board and the Policy and Performance Committee before coming to Cabinet each quarter. Report 1.2
What happens next
Continue rolling out a multi-service programme so that all domestic properties receive a Water Risk Assessment alongside their gas service within a full year of service. Report 2.5
Develop an Access Plan and review tenant messaging, with the option to cap supply, to reduce no-access cases for gas servicing. Report P22, P23, 2.1
Set up the new Housing Management System to report automatically on damp and mould repairs once Awaab's Law is in force, replacing the current ad hoc interim report.
Options considered
Chosen: Note the report on exceptions, damp and mould interim arrangements, and ongoing actions. Alternative Options Considered: None. The report is presented to give assurance on tenant safety and regulatory compliance. Report P7, 2.0
Implications
Financial: No direct financial implications arise from this report. Report 3.1, P34
Equalities: No direct equalities implications arise from this report, though tenant circumstances are considered through housing services to achieve compliance. Report 3.2, P36
Legal: The report covers the Council's legal and regulatory landlord responsibilities for building safety, with new EICR requirements in force from October 2025. Report 1.3, 1.9
Risk: Solid fuel compliance at 90% and oil servicing at 95.74% are rated red and remain under review to improve asset data. Report 2.8
Who and where
Council housing tenants in domestic properties, blocks and community centres Report 1.3, 2.2, 2.5
New incoming social housing tenants, who must receive an EICR within 28 days of tenancy start Report 1.9
Tenants in properties without valid EICR, gas, water, asbestos, stairlift or hoist certificates, where access is being sought Report 2.1, 2.4, 2.5, 2.6, 2.7
Timeline
June 2025: Council received a Government letter ahead of phase 1 of Awaab's Law and changes to electrical safety standards Report 1.8
From October 2025: New duty for social landlords to issue incoming tenants with a copy of the EICR within 28 days of tenancy start Report 1.9
1 November 2025: Multi-service programme commenced to undertake domestic Water Risk Assessments alongside the gas service Report 2.5
From Autumn, with two further phases expected in 2026 and 2027: Phase 1 of Awaab's Law introduces strict timescales for the investigation and rectification of damp and mould Report 1.8
31 March 2026: End of Quarter 4 reporting period for housing compliance performance Report P5, 1.1
Plain English for the jargon
Awaab's Law: New regulation setting strict timescales for social landlords to investigate and rectify damp and mould hazards
EICR: Electrical Installation Condition Report, required to be issued to new tenants within 28 days from October 2025
FRA: Fire Risk Assessment, completed for blocks and community centres and then placed on a scheduled inspection frequency
WRA: Water Risk Assessment, undertaken in domestic properties alongside the gas service through a multi-service programme
RAG rating: Red, Amber, Green performance rating: Green 100%, Amber 98 to 99.99%, Red below 98%
P1, P2, P3: Priority categories for damp and mould works, from P1 emergency to P3 major works by the Asset Team
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item406
Resolved
That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangements for monitoring damp and mould ahead of introduction of Awaab’s Law; and c) the ongoing actions to improve and maintain performance. To provide assurance on the work undertaken to ensure the safety of tenants and compliance with the regulatory standards. Options Considered: None
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to: Cabinet Meeting: 21 July 2026 Portfolio Holder: Councillor Lee Brazier, Housing Director Lead: Suzanne Shead, Director - Housing Lead Officer: Norman Emery, Compliance Manager, Housing Maintenance & Asset Management Business Unit
Report Summary
Type of Report Open Report / Non-Key Decision
Report Title Housing Compliance Assurance Report Quarter 4 2025-26
To provide the performance position as of 31 March 2026 Purpose of Report (Quarter 4) for Housing related compliance and update on activities in the service area.
That Cabinet note: a) the exceptions to performance of the housing service compliance functions; Recommendations b) interim arrangements for monitoring damp and mould ahead of introduction of Awaab’s Law; and c) the ongoing actions to improve and maintain performance.
Alternative Options None. Considered To provide assurance on the work undertaken to ensure the safety of tenants and compliance with the regulatory standards. This links to two ambitions in our Community Plan: Reason for Ambition 2: Increase the supply of housing, in particular Recommendations decent homes that residents can afford to buy and rent, as well as improving housing standards and, Ambition 7: Be a top performing, modern and accessible Council that get its everyday services right for the residents and businesses that it serves 1.0 Background
1.1This report provides Members with the performance of housing compliance services at the end of March 2026, focusing on exceptions performance, which is outside the Council’s target parameters.
1.2The full performance summary is shared with SLT; the Portfolio Holder for Housing and discussed as a standard agenda item for the Tenant Engagement Board meetings ensuring that Health & Safety are at the heart of our conversations and actions. Performance is also discussed at Policy and Performance Committee (PPIC) before being presented quarterly at Cabinet (Performance) to ensure there is oversight at Board level.
1.3This report sets out the Council’s performance against the Council’s legal and regulatory landlord responsibilities for a range of building safety measures including fire protection, gas, asbestos, electrical and water. Further information on the Council’s responsibilities can be found here https://www.gov.uk/government/publications/safety-and-quality-standard.
1.4Full details of these performance indicators along with associated commentary are included at Appendix 1 to this report.
1.5The Council’s performance in the report is rated as set out in the table below - as recommended by external auditors and the Regulator of Social Housing:
RAG Rating Old Rating New Rating Colour in 2023/24 2024/25 Appendix Report Green At Target 100% Amber Within 2% 98 – 99.9% Red Below 2% 0 – 97.99%
1.6The report also included information on the number of damp and mould cases and our performance in this area including:
• number of inspections conducted. • number of works order raised and completed. • average time taken to complete works. • percentage completed on time. • average cost of repairs not capitalised (Priority 1 & Priority 2 only)
across three categories (P1-P3) based on the amount and difficulty of the work and in total. The description for each category is listed below and can be found on page 3 of Appendix 1 Key Performance Reporting Scorecard for Housing Compliance.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.