Housing Compliance Assurance Report - Quarter 3

Decided Executive 2 papers

AI summaryCabinet noted Q3 housing compliance performance with most areas amber rated and solid fuel and oil servicing red, while interim arrangements are in place for damp and mould ahead of Awaab's Law.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNoted exceptions, damp and mould interim arrangements, and ongoing actions
MoneyNot stated
What happens nextOngoing compliance workIncluding fire risk assessments and Awaab's Law preparation
Who it affectsCouncil housing tenantsTenants of Newark and Sherwood District Council homes

What was decided

Cabinet noted the exceptions to performance of the housing service compliance functions.

Cabinet noted the interim arrangements for monitoring damp and mould ahead of Awaab's Law.

Cabinet noted the ongoing actions to improve and maintain compliance performance.

Why

To provide assurance on the work undertaken to ensure the safety of tenants and compliance with regulatory standards.

The report links to Community Plan Ambition 2 on increasing the supply of housing and decent homes, and Ambition 7 on being a top performing, modern and accessible council.

What happens next

Remaining Fire Risk Assessments for Blocks 3 and 4 and Community Centres are due to be completed between January 2026 and March 2026. Report 2.2, P19, P20, P21

The multi-service programme continues, with the aim that all domestic properties will have a Water Risk Assessment within a full year of service. Report 2.5

The council is preparing for further phases of Awaab's Law expected in 2026 and 2027, with the new Housing Management System being set up for automatic reporting. Report 1.6, P12

Options considered

  • Chosen: No options considered; the report sets out performance data for Quarter 3.

Implications

  • Legal: The council must comply with various legislation including the Landlord and Tenant Act 1985, Gas Safety Regulations 1998, Fire Safety Act 2021, Control of Asbestos Regulations 2012, COSHH and Health and Safety at Work Act, and LOLER 1998. Report 3.3, P36, P37, P38, P39, P40
  • Legal: Failure to comply could lead to prosecution, civil claims, or reporting to the Housing Ombudsman. Report 3.5
  • Financial: There are no direct financial implications arising from this report. Report 3.1, P30
  • Equalities: There are no direct equalities implications, though tenant individual circumstances are considered through housing services to achieve compliance. Report 3.2, P32

Who and where

  • Council housing tenants, including those needing access for safety checks Report 1.2, 2.1, P17

Timeline

  • October 2025: New requirement to issue an EICR to new tenants within 28 days of tenancy start date came into force Report 1.7
  • 1 November 2025: Multi-service programme commenced for Domestic Water Risk Assessments alongside Gas Service Report 2.5
  • End of December 2025 (Q3): Performance reporting period covered by the report Report 1.1
  • January 2026 to March 2026: Remaining Fire Risk Assessments for Blocks 3 and 4 and Community Centres to be completed Report 2.2, P19, P20
  • 2026 and 2027: Two further phases of Awaab's Law expected, expanding its scope Report 1.6, P12

Plain English for the jargon

  • EICR: Electrical Installation Condition Report
  • FRA: Fire Risk Assessment
  • WRA: Water Risk Assessment
  • Awaab's Law: New regulation setting strict timescales for the investigation and rectification of damp and mould in social housing
  • RAG rating: Red, Amber, Green performance rating system
  • LOLER: Lifting Operations and Lifting Equipment Regulations 1998
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item370

Resolved

That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangements for monitoring damp and mould ahead of introduction of Awaab’s Law; and c) the ongoing actions to improve and maintain performance. To provide assurance on the work undertaken to ensure the safety of tenants and compliance with the regulatory standards. This links to two ambitions in our Community Plan: Ambition 2: Increase the supply of housing, in particular decent homes that residents can afford to buy and rent, as well as improving housing standards; and Ambition 7: Be a top performing, modern and accessible Council that get its everyday services right for the residents and businesses that it serves . Options Considered: None, this report sets out performance data for Quarter 3.
Word for word from the decision Newark and Sherwood published for this meeting. Source: democracy.newark-sherwooddc.gov.uk

Follow this further

Built from Newark and Sherwood's papers

What the report saysPro

Report to Cabinet

Background

1.1This report provides Members with the performance of housing compliance services at the end of December 2025, focusing on exceptions performance, which is outside the Council’s target parameters.

The full performance summary is shared with SLT; the Portfolio Holder for Housing and discussed as a standard agenda item for the Tenant Engagement Board meetings ensuring that Health & Safety are at the heart of our conversations and actions. Performance is also discussed at Policy and Performance Committee (PPIC) before being presented quarterly at Cabinet (Performance) to ensure there is oversight at Board level.

1.2This report sets out the Council’s performance against the Council’s legal and regulatory landlord responsibilities for a range of building safety measures including fire protection, gas, asbestos, electrical and water. Further information on the Council’s responsibilities can be found here: Safety and Quality Standard - GOV.UK.

1.3Full details of these performance indicators along with associated commentary are included at Appendix 1 to this report.

1.4The Council’s performance in the report is rated as set out in the table below - as recommended by external auditors and the Regulator of Social Housing:

RAG Rating Old Rating New Rating Colour in 2023/24 2024/25 Appendix Report Green At Target 100% Amber Within 2% 98 – 99.9% Red Below 2% 0 – 97.99%

1.5The report also included information on the number of damp and mould cases and our performance in this area including:

• number of inspections conducted. • number of works order raised and completed. • average time taken to complete works. • percentage completed on time. • average cost of repairs not capitalised (Priority 1 & Priority 2 only)

across three categories (P1-P3) based on the amount and difficulty of the work and in total. The description for each category is listed below and can be found on page 3 of Appendix 1 Key Performance Reporting Scorecard for Housing Compliance.

• P1 - Emergency e.g. excessive mould or major leak. • P2 - Minor repair works and mould wash. • P3 - Major Works undertaken by Asset Team e.g. new Damp Proof Course

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24.03.26: Housing Compliance Q3 2025-26 Performance: Appendix 1Appendix 124 KB Download
PDF
Housing Compliance Assurance Report: Quarter 3Report 214 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
PP
Councillor Paul PeacockChair, present
RC
Councillor Rowan CozensCommittee Member, apologies
SC
Councillor Susan CrosbyCommittee Member, present
LB
Councillor Lee BrazierCommittee Member, apologies
SF
Councillor Simon FordeCommittee Member, present
CP
Councillor Claire PennyCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
JK
Councillor Jack KellasCommittee Member, present
NH
Nigel HillSecretary, expected
MF
Matt FinchOfficer, expected
DK
Deborah K JohnsonOfficer, expected
SK
Sanjiv KohliOfficer, expected

All 19 on the meeting page

On this subject at Newark and Sherwood

Search all
  1. Housing Compliance Assurance Report - Quarter 3This decision
  2. Housing Compliance Assurance Report Quarter 1Decided
  3. Housing Compliance Assurance Report Quarter 4 2025-26Decided
  4. Annual and Q4 Compliance Update - HousingAgreed
  5. Quarter 3 2025-26 - Housing Compliance Assurance ReportAgreed
  6. Housing Compliance Assurance Report - Quarter 2Decided

More from Newark and Sherwood Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 Budget Performance Report Quarter 1That Cabinet: (a) note the General Fund projected unfavourable outturn variance of £0.665m; (b) note the Housing Reve... Noted Open
15 Sep 2026 Community Plan Performance Report Quarter 1That Cabinet: a) review the Community Plan Performance Report attached as Appendix 1; b) review the compliance report... Decided Open
15 Sep 2026 Housing Compliance Assurance Report Quarter 1That Cabinet note: a) the exceptions to performance of the housing service compliance functions; b) interim arrangeme... Decided Open
15 Sep 2026 Annual Review of Exempt ItemsThat Cabinet note the report, with any items being released into the public domain if considered no longer being exempt. Noted Open
15 Sep 2026 Progress Towards Net ZeroThat Cabinet: a) notes the Council's 2025/26 corporate emissions position and progress towards the Net Zero 2035 targ... Decided Open