Newport City Council
Cabinet, Monday 6 June 2016 at 10.00am

Capital Programme Outturn

Approved Executive 1 paper

Cabinet approved this item on Monday 6 June 2016. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

The Head of Finance reported that 2015/16 was the second year of the current four-year capital programme. The 2015/16 budget as per the Budget & MTFP report approved by Cabinet in February 2016 was £26,146,000. Cabinet was informed that since that report there had been a number of additions to the capital programme, resulting in a final 2015/16 budget of £29,292,000. The changes were explained by service area in the report to Cabinet Cabinet Members discussed the reported need to revise the cost estimates in relation to the 21 st Century Schools Programme, mainly owing to the fact that the original estimates were provided some six years ago. It was noted that Newport Norse was currently working on revising cost estimates for all current and planned Education projects and once the outcome of this exercise was known a report would be presented to Cabinet. Cabinet Members were concerned that the report was submitted at the earliest possible opportunity The final outturn for 2015/16 was summarised, along with carry forward requests for slippage. It was noted that since the budget re-profiling exercise that was carried out for the January 2016 Monitoring & Additions Report, some schemes had incurred expenditure quicker than anticipated, so it was requested that budgets were brought back into 2015/16 to re-align budgets with this expenditure. The updated capital programme for 2016/17 including the requested slippage was set out in the report Members were provided with the summary two year programme as it now stands following confirmation of the 2015/16 actual slippage figure. The position as to capital receipts was reported. The Corporate Director (Place) mentioned that more capital receipts were to come in relation to the receipts held for Newport Unlimited. This funding must be used for regeneration in the city centre. It was reported that Civil Servants were working with the Vibrant and Viable Places Board to achieve this investment in the city center To note the outturn position for the 2015/16 capital programme and to approve budget carry forwards requested to cover slippage into 2016/17. To note the balance of Useable Capital Receipts as detailed in the report. Directors, Heads of Service, Monitoring Officer, Head of Finance, and Head of People & Business Change Implemented By: Head of Finance Implementation Timetable: Immediate and ongoing To note the outturn position for the 2015/16 capital programme and to approve budget carry forwards requested to cover slippage into 2016/17. To note the balance of Useable Capital Receipts as detailed in the report.
Word for word from the decision Newport published for this meeting. Source: democracy.newport.gov.uk

Follow this further

Built from Newport's papers

What the report saysPro

Report to Cabinet

Report Cabinet Part 1

Date: 6th June 2016

Item No:

Subject Capital Programme Outturn 2015/16 Purpose The report reviews the outturn of capital expenditure for the 2015/16 financial year, and requests approval of budget carry forwards to fund slippage of expenditure into the new financial year.

Author Senior Finance Business Partner (Capital)

Ward All Wards

Summary The report updates Cabinet on the final outturn position for capital programme schemes in 2015/16 and requests carry forwards required as a result of slippage.

The report lists capital receipts achieved in 2015/16 and highlights the balance of unutilised receipts available for future use.

Proposal To note the outturn position for the 2015/16 capital programme and to approve budget carry forwards requested to cover slippage into 2016/17.

To note the balance of Useable Capital Receipts as detailed in the report.

Action by Head of Finance

Timetable Immediate This report was prepared after consultation with:

 Heads of Service  Accountancy teams for relevant service areas  Relevant Service Area Project Managers  NORSE Property Services

Signed Background  2015/16 was the second year of the current four-year capital programme. The 2015/16 budget as per the Budget & MTFP report approved by Cabinet in February 2016 was £26,146k. Since that report there have been a number of additions to the capital programme; the table below shows these changes, which gives a final 2015/16 budget of £29,292k. The changes are explained by service area following the table.

Table 1: 2015/16 Capital Budget including new additions

Report / Scheme Change Reason Service Area Budget Change (£000’s) 2015/16 budget as per 2016/17 26,146 Budget & MTFP Report New ASD Facility S106 Funding Education 7 21CS Reorganisation Lodge Hill S106 Funding Education 91 21CS Replacement Demountables S106 Funding Education 681 Primary Place Challenge S106 Funding Education 130 St Andrews Primary 3FE Works S106 Funding Education 492 Energy Efficiency Grant Increase Regen, Investment & Housing 35 Vibrant & Viable Places Grant Increase Regen, Investment & Housing 1,155 Brynglas House Annex Refurb Revenue cont Adult & Community Services 100 Substance Misuse Action Fund Grant Increase Adult & Community Services 108 Flood Risk Regulation Grant Increase Streetscene & City Services 45 PDA Equipment Invest to Save Streetscene & City Services 82 Refuse Bin Bulk Replacement Grant Funding Streetscene & City Services 220 Final Budget 2015/16 29,292

 Education – S106 monies totalling £1,401k have been received by the Authority and are now assigned to increase existing budgets for a variety of major projects, particularly within the 21st Century Schools Programme. Recent tenders for schemes ready to commence have made it clear that the original budgets assigned to them up to six years ago are now insufficient. The main reason for this is the inflation in the construction industry in recent years. Newport Norse are currently working on revising cost estimates for all current and planned Education projects and once the outcome of this exercise is known a report will be presented to Cabinet, in which the revised capital budget requirement and current available resources (and therefore projected funding gap) will be analysed.

 Regeneration, Investment & Housing – officers were successful in utilising a residual grant provided by Welsh Government in order to fully fund the expenditure incurred on the Energy Efficiency scheme. Welsh Government also increased the 2015/16 grant award for Vibrant & Viable Places shortly before the end of the financial year.

 Adult & Community Services – refurbishment works completed recently at the Brynglas House Annex are part funded by Revenue contribution. An increase in grant award for the Substance Misuse Action Fund was notified by Welsh Government late in the year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme OutturnReport 620 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
DW
Councillor Debbie WilcoxChair, present
PC
Councillor Paul CockeramCommittee Member, present
GG
Councillor Gail GilesCommittee Member, present
DH
Councillor Debbie HarveyCommittee Member, present
RJ
Councillor Roger JeavonsCommittee Member, apologies
RP
Councillor Robert PooleCommittee Member, present
JR
Councillor John RichardsCommittee Member, present
RT
Councillor Ray TrumanCommittee Member, present
MW
Councillor Mark WhitcuttCommittee Member, present

On this subject at Newport

Search all
  1. Capital Programme OutturnThis decision
  2. Capital Programme Monitoring and Additions Report - 2025/26 OutturnApproved
  3. Capital Programme Monitoring and Additions Report - October 2025Approved
  4. Capital Programme Monitoring and Additions - JulyApproved
  5. Capital Programme Monitoring and Additions OutturnApproved
  6. Capital Programme Monitoring and Additions Report - November 2024Approved

More from Newport Cabinet

All decisions
MeetingDecisionOutcome
8 Jul 2026 Annual Welsh Language Monitoring Report 2025-26Cabinet approved and recommended the monitoring report to Full Council. Approved Open
8 Jul 2026 Safer Newport Community Safety Partnership Annual Report 2025-26Cabinet approved the Safer Newport Community Safety Partnership Annual Report 2025-2026 for publication in line with ... Approved Open
8 Jul 2026 Newport Library Strategy 2026-29Cabinet adopted the and proceeded to publication. Approved Open
8 Jul 2026 Work ProgrammeCabinet agreed the . The Leader gave the following announcement in relation to a package of targeted one-off investme... Agreed Open
17 Jun 2026 Revenue Budget Outturn - 2025/26Cabinet - 1. Noted the outturn position, which was subject to audit; and the major variances for the year (Sections 1... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies