CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Hertfordshire District Council
Hitchin Committee, Tuesday 13 November 2018 at 7.30pm

REGENERATION OF CHURCHGATE SHOPPING CENTRE

Decided Committee 4 papers

Hitchin Committee decided this item on Tuesday 13 November 2018. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

Audio recording – Start of Item - 38 minutes 28 seconds Councillor Judi Billing declared a declarable Interest in that she was a Community Director of Hitchin Initiative. RECOMMENDED TO CABINET: (1) That the Chairman of Hitchin Committee should be a member of the Churchgate Project Board; (2) That the Hitchin Committee: (i) Welcomes the ideas and concepts put forward by the community groups, as presented by John and Vicky Wyer ; (ii) Notes that, whilst some of the proposals may not be viable at this time, nevertheless many of the concepts and ideas make a positive contribution to the development of the project; (iii) Asks the Council to engage with representatives of the community groups in the design and development of the project, should it go ahead. REASON FOR DECISION: As the Churchgate Shopping Centre is located in Hitchin, this meeting provides a “forum for discussion on matters of local interest”.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Hitchin Committee

Executive summary

1.1The purpose of the report is to give Hitchin Committee an opportunity to comment on the report that will be presented to Cabinet on 20th November 2018 and Full Council on 22nd November 2018. Full details of the proposal for the regeneration of the Churchgate Shopping Centre will be contained within the Council report that will be published on Friday 9th November.

Recommendations

2.1That the Committee considers the report, and where relevant provides the local input to Cabinet on the proposed regeneration of the Churchgate Shopping Centre.

Reasons for recommendations

3.1The Council has been seeking to regenerate the Churchgate Centre for a number of years and a number of different proposals have been considered during that time, with none of those proposals progressing to a successful conclusion. The Council report details a proposed regeneration scheme that has a good chance of being achievable and could provide a financial return that exceeds the current income. As the Churchgate Shopping Centre is located in Hitchin, this meeting provides a “forum for discussion on matters of local interest”.

Alternative options considered

4.1Full Council has received a number of reports on the subject of Churchgate historically and those reports explored a number of different alternative options for the site. At the current time the alternative options can best be summarised as any combination of the following:-

i) do nothing; and/or ii) await Local Plan adoption and subsequent town centre strategy work; and/or iii) allow Shearer Property Group (‘SPG’) option to purchase to expire and seek to acquire on the open market; and/or iv) extend/ re-let the contract for the management of Hitchin Market in the short term, pending further consideration of the operation of the market. 5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1The Leader of the Council and Executive Member for Finance and IT have been kept informed of the discussions with SPG and consulted as appropriate.

6. FORWARD PLAN

6.1The report to Cabinet contains a recommendation on a key decision and therefore was added to the Forward Plan on 22 October 2018.

Background

7.1The full background will be provided as part of the Council report. On 8 February 2018 Council resolved that:

(1) That the principle of a joint venture regeneration of the Churchgate Centre, with the Council as funder of the regeneration, be supported;

(2) That the Deputy Chief Executive, in consultation with the Chief Finance Officer, the Leader of the Council and Executive Member for Finance and IT, be authorised to progress negotiations with Shearer Property Group on the terms of a potential joint venture regeneration of the Churchgate Centre, subject to Full Council’s final approval of the terms of any proposal; and

(3) That the proposal to allow the contract for the management of Hitchin Market to expire and for the market to be managed in-house, subject to Cabinet’s approval, be noted.

7.2On 27 March 2018, Cabinet resolved that:

(1) That a decision on whether to manage Hitchin market in-house be deferred, until there is greater clarity on the deliverability of the proposals for the Churchgate Centre and Hitchin Market and further consideration has been given to the model for operating the market in-house; and

(2) That the Deputy Chief Executive, in consultation with the Head of Leisure and Environmental Services, the Executive Member for Finance and IT and the Executive Member for Leisure, be authorised to agree with Hitchin Markets Ltd the terms of an extension of their existing management contract in the short term.

8. RELEVANT CONSIDERATIONS

8.1The proposals for Churchgate are substantially the same as was detailed to in the Council report in February 2018.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Indicative Site Plan: First FloorAppendix A 4.1 MB Download
PDF
Indicative Site Plan: Ground FloorAppendix A 4.3 MB Download
PDF
REGENERATION OF CHURCHGATE SHOPPING CENTREReport 304 KB DownloadRead as text
PDF
Report due to be submitted to Council on 22 November 2018Report 451 KB Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. REGENERATION OF CHURCHGATE SHOPPING CENTREThis decision
  2. Churchgate regeneration project update & next steps - part 1Approved
  3. Churchgate regeneration project update & next steps - part 1Approved
  4. Churchgate regeneration project update & next steps - part 1Noted
  5. 7b - ITEM REFERRED FROM CABINET: 20 NOVEMBER 2018 - REGENERATION OF CHURCHGATE SHOPPING CENTREDecided
  6. Regeneration of churchgate shopping centreAgreed

More from North Hertfordshire Hitchin Committee

All decisions
MeetingDecisionOutcome
28 Mar 2023 Apologies for absenceApologies for absence were received from Councillor Raj Bhakar. Decided Open
28 Mar 2023 Minutes - 8 december 2022That the Minutes of the Meeting of the Committee held on 8 December 2022 be approved as a true record of the proceedi... Approved Open
28 Mar 2023 Notification of other businessThere was no other business notified. Decided Open
28 Mar 2023 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be audio recorded. Decided Open
28 Mar 2023 Hitchin bid - updateA verbal presentation was received from Tom Hardy of Hitchin BID. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies