23/00750/FP LAND BETWEEN DURHAM WAY AND YORK WAY, ROYSTON SG8 5GX

Agreed Planning 2 papers

Planning Control Committee agreed this item on Tuesday 11 July 2023. Below is the council's own wording, with the papers it was decided on.

Item93

Resolved

That application 22/00750/FP be GRANTED planning permission subject to the reasons and conditions set out in the report of the Development and Conservation Manager, with an additional requirement for the agent to provide an Environmental Management Statement, to cover the installation of EV chargers and PV panels on site, and a relevant condition added subject to confirmation from the Chair of the Planning Control Committee. Should this not be agreed then the application would be brought back to the Committee for determination. As well as the deletion of Condition 19, the re numbering of Condition 20 to 22 to Conditions 19 to 21 and the following amendments to Informative 1 and conditions 19 and: “Informative 1: Charging points shall be installed by an appropriately certified electrician/electrical contractor in accordance with the following specification. The necessary certification of electrical installation should be submitted as evidence of appropriate installation to meet the requirements of Part P of the most current Building Regulations. Cable and circuitry ratings should be of adequate size to ensure a minimum continuous current demand for the vehicle of 16A and a maximum demand of 32A (which is recommended for Eco developments) · A separate dedicated circuit protected by an RBCO should be provided from the main distribution board, to a suitably enclosed termination point within a garage or an accessible enclosed termination point for future connection to an external charge point. · The electrical circuit shall comply with the Electrical requirements of BS7671: 2008 as well as conform to the IET code of practice on Electric Vehicle Charging Equipment installation 2012 ISBN 978-1-84919-515-7 (PDF). This includes requirements such as ensuring the Charging Equipment integral protective device shall be at least Type A RCD (required to comply with BS EN 61851 Mode 3 charging). · If installed in a garage all conductive surfaces should be protected by supplementary protective equipotential bonding. For vehicle connecting points installed such that the vehicle can only be charged within the building, e.g. in a garage with a (non-extended) tethered lead, the PME earth may be used. For external installations the risk assessment outlined in the IET code of practice must be adopted, and may require additional earth stake or mat for the EV charging circuit. This should be installed as part of the EV ready installation to avoid significant on cost later. · A list of authorised installers (for the Government’s Electric Vehicle Homecharge Scheme) can be found at https://www.gov.uk/government/organisations/office-for-low-emission-vehicles . · UK Government is intending to issue legislation in 2021 to require domestic EV charge points to be smart, thus we recommend that all charge points will be capable of smart charging, as detailed in UK Gov consultation response. Condition 18: · Demolition/development shall take place in accordance with the Written Scheme of Investigation approved under condition (17). · The development shall not be occupied until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under condition (17) and the provision made for ... That application 22/00750/FP be GRANTED planning permission subject to the reasons and conditions set out in the report of the Development and Conservation Manager, with an additional requirement for the agent to provide an Environmental Management Statement, to cover the installation of EV chargers and PV panels on site, and a relevant condition added subject to confirmation from the Chair of the Planning Control Committee. Should ... view the full minutes text for item 93.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Planning Control Committee
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
23-00750-FP planReport 543 KB Copy on its way
PDF
23/00750/FP LAND BETWEEN DURHAM WAY AND YORK WAY, ROYSTON SG8 5GXReport 712 KB Copy on its way

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. 23/00750/FP LAND BETWEEN DURHAM WAY AND YORK WAY, ROYSTON SG8 5GXThis decision
  2. 25/03149/rm land between royston road and, cambridge road, barkway, hertfordshireApproved
  3. 25/02998/fp land between shangri-la and todds corner, stevenage road, todds green, hertfordshire, sg1 2jeAgreed
  4. 25/02234/s73 land between royston road and cambridge road, barkway, hertfordshireAgreed
  5. 24/01444/fp land between huntsridge and ashwell house 5, high street, ashwell, hertfordshireAgreed
  6. 25/00949/fp land between shangri-la and todds corner, stevenage road, todds green, hertfordshire, sg1 2jeDecided

More from North Hertfordshire Planning Control Committee

All decisions
MeetingDecisionOutcome
1 Oct 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
1 Oct 2026 Minutes - 3 september 2026That the Minutes of the meeting of the Committee held on 3 September 2026 be approved as a true record of the proceed... Approved Open
1 Oct 2026 Notification of other businessThere was no notification of other business. Decided Open
1 Oct 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Decided Open
1 Oct 2026 Public participationThe Chair confirmed that the registered speakers were in attendance. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies