AI summaryNorth Herts Cabinet noted Q2 progress on the Council Delivery Plan 2025-26, approved new and changed milestones, and proposed 12 new KPIs to better link performance to the Council Plan.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted Q2 update and approved new and changed milestones
MoneyNo direct financial implicationsStated in section 10.1 of the report
What happens nextNot stated
Who it affectsCouncil projects, KPIs and risks monitoredTwo projects completed, five amber, four red
What was decided
Cabinet noted progress against Council projects and performance indicators in the Council Delivery Plan 2025-26 (Appendix A). Report 2.1
Cabinet approved new milestones and changes to existing milestones within the plan. Report 2.1
Twelve new KPIs were proposed for future monitoring, drawn from Council Plan actions, with no targets set initially. Report P29, P30
Why
Quarterly CDP reports let Cabinet and Overview and Scrutiny Committee monitor project progress, spot risks, and identify opportunities. Report 3.1, 4.1
A 2024-25 Corporate Peer Challenge and Internal Audit report recommended stronger links between KPIs and the Council Plan, which the new KPIs address. Report 5.4
Monitoring helps the Council meet its best value duty under Section 3 of the Local Government Act. Report 9.4
What happens next
A new museum collection facility project will be added to the CDP in time for the next monitoring report, following its first Project Board meeting in September 2025.
Directors and Service Managers will continue to provide updates and raise progress issues with Executive Members. Report 5.1
Cabinet will be asked to approve any future changes to milestones after prior review by Overview and Scrutiny Committee. Report 8.9
Options considered
Chosen: Receive quarterly CDP updates with both Cabinet and Overview and Scrutiny Committee reviewing them. Provides additional oversight and support to Cabinet Report 4.1
Rejected: Retain current KPIs focused mainly on core services and accept their limits. Peer Challenge and Internal Audit recommended better alignment with the Council Plan Report 4.2
Chosen: Add 12 new KPIs that better reflect Council Plan outcomes. Discussed and supported at the Political Liaison Board in August and December 2025 Report 5.4, P30
Implications
Risk: Four projects carry a red risk status: Churchgate, Decarbonisation of Council Buildings Phase 2, Leisure Centre Decarbonisation, and Local Plan review. Report P3, 8.6, P28
Risk: All four over-arching Corporate Risks are rated red. Report P3, 8.6
Staffing: Customer Service Centre performance on answering calls in 45 seconds is red, affected by staffing challenges, seasonal demand, and new waste service rollout. Report P3, 8.4, 8.3, P22
Staffing: Two Careline installation KPIs are red due to workforce constraints, though October 2025 performance reached 90.1 percent, just above target. Report P3, 8.4
Equalities: Officers state no direct equalities implications arise from this report, but the Public Sector Equality Duty continues to apply. Report 12.1, 12.2
Financial: No direct financial implications from this report; project efficiencies or investments are tracked through quarterly finance reports. Report 10.1
Other: No direct social value, human resources, or environmental implications arise from the report itself, though several monitored projects relate to environmental issues. Report 13.1, 14.1, 15.1
Who and where
Council residents and service users in North Hertfordshire, particularly those using the Customer Service Centre, Careline service, and waste collections Report 8.4, 8.5, P26
Overview and Scrutiny Committee, which provides comment before Cabinet decisions on the CDP Report 3.1, 5.3, 9.2
Risk and Performance Management Group (RPMG), which reviewed the Q2 draft in November 2025 Report 5.2
Project teams working on the four red-rated projects and the five amber-rated projects Report P3, 8.2, P20
Timeline
August 2025: Political Liaison Board discussed adding new KPIs aligned to the Council Plan Report 5.4
September 2025: Careline installations reached 89.2 percent within 5 working days, 0.8 percent below target Report 8.4
September 2025: Initial Project Board meeting held for the new museum collection facility project
October 2025: Careline performance improved to 90.1 percent, exceeding the 90 percent target by 0.1 percent Report 8.4
November 2025: RPMG reviewed the draft Q2 update; no specific issues raised Report 5.2
Late November 2025: Report prepared, reflecting latest available progress Report P1, 8.1
21 November 2025: Key decision first notified to the public in the Forward Plan Report 6.1, P15
December 2025: Further Political Liaison Board discussion on new KPIs Report 5.4
Mid-January 2026: Feedback session scheduled for the new Safety Advisory Group platform, contributing to Digital Transformation amber status Report P20
20 January 2026: Cabinet meeting at which this decision was taken
Plain English for the jargon
CDP: Council Delivery Plan, the document that brings together projects, risks and performance indicators for the year
KPI: Key Performance Indicator, a measurable value showing how the Council is delivering against its priorities
RPMG: Risk and Performance Management Group, an internal group that reviewed the Q2 update in November 2025
CSC: Customer Service Centre, the team that handles Council calls, currently missing its 45-second answer target
Careline: A Council service installing equipment for residents, currently measured on installations within 5 and 10 working days
Ideagen: The Council's performance and risk management system, holding the live CDP data
SAG: Safety Advisory Group, whose new platform go-live is part of the Digital Transformation project
TRO: Traffic Regulation Order, relevant to the Pay on Exit Parking project at Hitchin Swimming and Fitness Centre
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
That Cabinet noted progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approved new milestones and changes to milestones. REASON FOR DECISION: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities. That Cabinet noted progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approved new milestones and changes to milestones. REASON FOR DECISION: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
This report presents progress on delivering the Council Delivery Plan for 2025-26. This is a Quarter 2 update but generally reflects progress up to the point that this report was prepared (late November 2025). The report includes:
• For the projects identified by Cabinet, it details milestones and progress against them. • The risks in relation to the delivery of those projects, as well as the corporate risks that could impact the delivery of all our projects and services. • Latest data for the Council’s key performance indicators (KPIs).
Two projects have been completed (King George V Skate Park and Waste and Street Cleansing Contract) and associated risks have been managed to the target level. Five projects have an amber delivery status (Decarbonisation of Council Buildings - Phase 2, Digital Transformation, Oughtonhead Common Weir, Pay on Exit Parking, and Resident/Public EV Charging in our Car Parks). Four projects have a red risk status (Churchgate, Decarbonisation of Council Buildings - Phase 2, Leisure Centre Decarbonisation, and Local Plan review). The four over-arching Corporate Risks also have a red status. There are three KPIs that have a red status (two relating to Careline installations and one relating to CSC calls answered in 45 seconds).
This report also sets out plans for developing KPIs that align better to the objectives within our Council Plan.
Recommendations
It is recommended that Overview and Scrutiny Committee:
2.1That Cabinet notes progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approves new milestones and changes to milestones. 3. REASONS FOR RECOMMENDATIONS
3.1The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.
Alternative options considered
4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee so that they can provide additional oversight and support to Cabinet.
4.2In relation to adding new KPIs to better reflect delivery of the Council Plan, there would be an option to just retain the current KPIs and accept that they are primarily focused on delivery of core services.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Directors and Service Managers have provided updates on progress and will have made Executive Members aware of progress made.
5.2A draft of the Quarter 2 update was provided to the Risk and Performance Management Group (RPMG) in November 2025. The Group has a standing invite to the Executive Member for Resources (has responsibility for performance monitoring), the Chair of Overview and Scrutiny Committee (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S and FAR are also encouraged to attend when they can. RPMG were asked to comment on the Q2 update. There were no specific issues raised by the Group.
5.3The Overview and Scrutiny Committee are asked to provide comments on the current progress of the CDP, including recommendations to Cabinet.
5.4In August 2025, proposals in relation to adding new KPIs to better reflect the Council Plan were discussed at the internal informal Political Liaison Board of the Executive and Leadership Team. The conclusion was that it would be desirable to have additional KPIs that helped describe the actions in the Council Plan. This was followed by a further discussion at the Political Liaison Board in December.
6. FORWARD PLAN
6.1This report contains a recommendation on a key decision that was first notified to the public in the Forward Plan dated 21 November 2025.
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.