CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Hertfordshire District Council
Cabinet, Tuesday 20 January 2026 at 7.30pm

LOCAL PLAN NEXT STEPS

Approved Executive 2 papers

AI summaryNorth Hertfordshire Cabinet approved the direction of travel for the Local Plan Review and delegated authority to publish the formal notice and revised timetable once the new national plan-making system takes effect, expected March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDirection of travel approved; authority delegated to Director: Place
Money£691k current Local Plan budgetAllocated from existing budgets and earmarked reserves
What happens nextPublish notice and revised timetable when system enacted. Expected enactment in March 2026
Who it affectsResidents, developers, landowners in North HertfordshirePlan review to be submitted before April 2028 reorganisation

What was decided

Cabinet approved the broad direction of travel for the Local Plan Review, pending the formal laying and enactment of the relevant legislation and regulations. Report 2.1

Cabinet delegated authority to the Director: Place, in consultation with the Executive Member for Place, to publish the formal notice of intention to undertake a review and to approve and publish a revised Local Plan timetable.

Why

The council wants to be well-positioned to progress the Local Plan as quickly as possible once the new plan-making system comes into effect, after previous work was held back by delays in publishing regulations and guidance. Report P2

Further delay would risk missing the pre-election period deadline of March 2028 and potential dissolution of the council under proposed Local Government Reorganisation. Report 4.2, P3

What happens next

Following enactment of the new system, publish the formal notice of intention to undertake a review of the Local Plan. Report 8.37

Approve and publish the revised Local Plan timetable, attached as Appendix A, subject to alignment with the new statutory framework. Report 8.37

Aim to submit the Local Plan for examination in early 2028, ahead of the anticipated Local Government Reorganisation in North Hertfordshire in April 2028. Report 8.35, 8.36

The money

  • £691k Current budget allocated for the Local Plan Report P64

Options considered

  • Chosen: Approve broad direction of travel and delegate authority to publish notice and revised timetable once the new system is enacted. Allows early progress, supports submission before March 2028 pre-election period and April 2028 reorganisation Report 2.1, 4.2
  • Rejected: Wait for new regulations to be published, including stakeholder feedback to MHCLG, before revising the timetable. Additional delay poses a significant risk to submitting a draft plan before the start of the pre-election period in March 2028 Report 4.2, P3

Implications

  • Financial: The £691k budget may not be sufficient; cost-recovery options from landowners of potential site allocations are being explored, and underspends may be carried forward. Report 10.3, P64
  • Legal: Plan preparation is governed by Section 15 of the Planning and Compulsory Purchase Act 2004, as amended by the Levelling Up and Regeneration Act 2023; new regulations are anticipated in January 2026 and the duty to maintain a Local Development Scheme will be replaced by a duty to maintain a local plan timetable. Report P63
  • Risk: Key risks include inadequate guidance, failure to retain or recruit experienced officers, funding shortfalls, lack of political or government approval at gateways, and government intervention if progress is inadequate. Report P67
  • Staffing: The Strategic Planning Team is currently understaffed and recruitment has not been fully successful; this may impact the delivery timeline and meeting of key milestones. Report P71
  • Equalities: There are no direct equalities implications; an Equalities Impact Assessment will be carried out for the Local Plan Update in accordance with the Equality Act 2010. Report P68
  • Climate: The Local Plan Review will allow the council to put climate change mitigation and adaptation at the heart of the Development Plan and will be subject to statutory environmental assessment requirements. Report P70

Who and where

  • Residents of North Hertfordshire Report 8.1
  • Local planning stakeholders, developers and site promoters Report P21
  • Landowners of potential development sites, who may face charging or cost-recovery arrangements Report 8.13, 10.3, P33
  • The strategic authority preparing any Spatial Development Strategy Report P39
  • A future Unitary authority taking on plan-making after Local Government Reorganisation Report 8.33, P55

Timeline

  • January 2024: Cabinet first resolved in principle that a review of the Local Plan should take place Report P2, P7
  • January 2025: Revised Local Development Scheme published, setting out milestones through to adoption by end of 2027 Report P7, P8
  • 19 September 2025: Recommendation first notified to the public in the Forward Plan Report P6
  • 27 November 2025: Government released new guidance on how councils should prepare Local Plans Report 7.5
  • December 2025: Strategic Planning Project Board endorsed the proposed programme Report P5
  • January 2026: Secondary legislation to enact the new system anticipated to be laid before Parliament Report 7.6
  • March 2026: New plan-making system expected to come into effect, around six weeks after legislation Report 7.6, 8.2, 8.34
  • 15 March 2026: MHCLG deadline for feedback on the new system Report 8.36
  • Early 2028: Target date for submission of the Local Plan for examination Report 8.35, 8.36
  • March 2028: Start of the pre-election period Report 4.2, P3
  • April 2028: Anticipated Local Government Reorganisation in North Hertfordshire Report 8.33, 8.35

Plain English for the jargon

  • LDS (Local Development Scheme): The current statutory timetable for preparing a local plan, replaced under the new system by a local plan timetable.
  • PCPA 2004: Planning and Compulsory Purchase Act 2004, the main legislation governing local plan preparation.
  • LURA 2023: Levelling Up and Regeneration Act 2023, which paves the way for reforms to the plan-making process.
  • MHCLG: Ministry of Housing, Communities and Local Government, the government department overseeing the new system.
  • Gateway 1, 2 and 3: Mandatory self-assessment and progress-check stages within the new plan-making system, the last of which is required before examination.
  • SEA (Strategic Environmental Assessment): The statutory environmental assessment that must accompany the Local Plan, including an environmental report.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That Cabinet: (1) Approved the broad ‘direction of travel’ for the Local Plan Review pending formal laying and enactment of the relevant legislation and regulations. (2) Delegated authority to the Director: Place, in consultation with the Executive Member for Place to, following the creation of a new planning system: a. Publish the formal notice of intention to undertake a review of the Local Plan; and b. Approve and publish a revised Local Plan timetable, attached as Appendix A, subject to any alterations necessary to ensure alignment of timings with the new statutory framework. REASON FOR DECISIONS: To ensure the Council is well-positioned to progress preparation of the Local Plan as quickly as possible once the new plan-making system comes into effect. Cabinet previously first resolved, in principle, that a review of the Local Plan should take place in January 2024. However, the Council did not progress on the review which was held back due to the delays in the publication of the regulations and guidance on the new local plan system. That Cabinet: (1) Approved the broad ‘direction of travel’ for the Local Plan Review pending formal laying and enactment of the relevant legislation and regulations. (2) Delegated authority to the Director: Place, in consultation with the Executive Member for Place to, following the creation of a new planning system: a. Publish the formal notice of intention to undertake a review of the Local Plan; and b. Approve and publish a revised Local Plan timetable, attached as Appendix A, subject to any alterations necessary to ensure alignment of timings with the ... view the full minutes text for item 8.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 15 pages

Recommendations

2.1That Cabinet approve the broad ‘direction of travel’ for the Local Plan Review pending formal laying and enactment of the relevant legislation and regulations 2.2. That Cabinet delegate authority to the Director: Place, in consultation with the Executive Member for Place to, following the creation of a new planning system a. Publish the formal notice of intention to undertake a review of the Local Plan; and b. Approve and publish a revised Local Plan timetable, attached as Appendix A, subject to any alterations necessary to ensure alignment of timings with the new statutory framework

3. REASONS FOR RECOMMENDATIONS 3.1 To ensure the Council is well-positioned to progress preparation of the Local Plan as quickly as possible once the new plan-making system comes into effect. Cabinet previously first resolved, in principle, that a review of the Local Plan should take place in January 2024. However the Council did not progress on the review which was held back due to the delays in the publication of the regulations and guidance on the new local plan system.

4. ALTERNATIVE OPTIONS CONSIDERED 4.1 An alternative option would be to wait for the new regulations to be published, including any amendments arising from stakeholder feedback to MHCLG, before revising the Local Plan timetable. This could minimise the need for further changes and ensure full alignment with the finalised system.

4.2This option is not recommended, as any additional delay poses a significant risk to North Herts Council’s ability to submit a draft Local Plan to the Secretary of State before of the start of the pre-election period in March 2028 and the potential dissolution of this authority under proposed Local Government Re-organisation. Early progress would allow the Council to leave a legacy of having prepared a final Local Plan under the current organisational structure and to meet key milestones set in the new system in a manner that is compatible with the civic cycle.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS 5.1. Strategic Planning Project Board were consulted on, and endorsed, the proposed programme in December 2025. They were also advised of the key issues discussed in this report. 5.2. The Executive Member has been kept up to date with the development of the Local Plan programme.

6. FORWARD PLAN 6.1 This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 19 September 2025.

7. BACKGROUND 7.1 At the January 2024 Cabinet meeting, it was agreed to initiate a review of the Local Plan. Subsequently, a revised Local Development Scheme (LDS) was published in January 2025, setting out the proposed timetable for preparing the Local Plan through to adoption. The key milestones identified were:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1LocalPlanTimetableAppendix 1LocalPlanTimetable 1 pages Download
PDF
LOCAL PLAN NEXT STEPSAppendix 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. LOCAL PLAN NEXT STEPSThis decision
  2. Local plan - content and evidence base consultationNoted
  3. Local plan reviewNoted
  4. Local code of corporate governance 2024 and annual governance statement action plan update 2023/24Approved
  5. Local plan reviewNoted
  6. Local plan reviewNoted

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies