AI summaryCabinet noted Q1 progress on North Herts' 2026-27 Council Delivery Plan, approved new projects and milestone changes, with 2 of 11 projects rated amber.
Written from the decision and the officer reportPDF Pro
OutcomeNotedNew projects, milestones and changes approved
MoneyNo direct financial implicationsProject budgets tracked separately
What happens nextQuarterly monitoring continuesNext key Cabinet paper due 19 January 2027
Who it affectsResidents and council servicesNNDR payers, garden waste subscribers, Careline users
What was decided
Cabinet noted progress against the Council Delivery Plan 2026-27 key projects and performance indicators, and approved new projects, milestones and changes to milestones. Report 2.1
A new project for the Royston Learner Pool was added to the plan, with completion anticipated in April 2028. Report 8.3, P2
Why
Quarterly monitoring gives Cabinet oversight of progress, new issues, risks and opportunities, with Overview and Scrutiny Committee able to scrutinise via the Members Information Bulletin. Report 3.1, 4.1
No alternative options were considered, as the report follows the agreed cycle of quarterly updates to Cabinet. Report 4.2
What happens next
For the Decarbonisation of Council Buildings Phase 2 project, the project team is procuring a contractor through a two-stage design and build approach, with detailed design and costings to inform a paper for the Cabinet meeting on 19 January 2027. Report 8.4
The Risk and Performance Management Group and Overview and Scrutiny Committee will continue to receive future quarterly updates through the Members Information Bulletin. Report 3.1, 5.2
Options considered
Chosen: Note progress and approve new projects, milestones and changes. Standard quarterly monitoring process agreed by Cabinet Report 2.1, 4.1
Rejected: Consider alternative options for the report. No alternative options were considered, as the report follows the agreed cycle of quarterly updates Report 4.2
Implications
Risk: Of 11 project risk entries plus 4 corporate risks, 3 are rated low (green), 5 medium (amber) and 7 high (red).
Legal: No specific legal implications arise from the Council Delivery Plan itself, but individual projects will follow standard legal and procurement requirements; the plan supports the Council's 'best value' duty under Section 3 of the Local Government Act. Report 9.3, 9.4
Equalities: No direct equalities implications arise from this report, though the Public Sector Equality Duty continues to apply to the Council's functions. Report 12.1, 12.2
Financial: No direct financial implications; project efficiencies and investments are tracked through quarterly finance reports. Report 10.1
Staffing: Short-term sickness absence has risen slightly to 4.54 days per FTE against a 4-day target, with a risk of further increases linked to Local Government Reorganisation workload. Report 8.7, P25
Climate: Two projects in the plan relate to environmental work: Decarbonisation of Council Buildings Phase 2 (amber) and Resident/Public EV charging in car parks (amber). Report 8.4, P2
Other: No specific social value or environmental implications arise from the report itself; individual projects may trigger procurement or environmental assessment requirements. Report 13.1, 14.1
Who and where
Business ratepayers (NNDR), affected by delays in billing caused by technical issues with new reliefs and multipliers introduced for 2026/27 Report 8.6, P21
Household garden waste subscribers, experiencing higher reported missed collections linked to a 10-working-day activation period for new subscriptions Report 8.6, P22
Careline customers, with one installation in April 2026 completed outside the 10-working-day target Report 8.7, P24
Residents contacting Customer Services by phone, with 62% of calls answered within 45 seconds against an 80% target, though staffing is stable Report 8.7, P26
Council staff, with short-term sickness absence at 4.54 days per FTE against a 4-day target Report 8.7, P25
Members of Overview and Scrutiny Committee, who may request more detailed updates on items in the plan Report 3.1
Timeline
15 July 2026: Planning permission, with conditions, granted at North Herts Leisure Centre for decarbonisation works Report 8.4
1 September 2026: Tender process for decarbonisation contractor anticipated to complete Report 8.4
Late Autumn 2026: Planning permission for Hitchin Town Hall decarbonisation predicted to be granted Report 8.4
19 January 2027: Cabinet meeting expected to receive paper on detailed designs and costings for decarbonisation works Report 8.4
April 2028: Anticipated completion of new Royston Learner Pool project Report 8.3
Plain English for the jargon
CDP: Council Delivery Plan, the document bringing together projects, risks and performance indicators
KPI: Key Performance Indicator, a measure of council performance against agreed targets
NNDR: National Non-Domestic Rates, the business rates collected by the council
RPMG: Risk and Performance Management Group, an internal group that reviewed the draft Q1 update
MIB: Members Information Bulletin, used to share monitoring reports with Overview and Scrutiny Committee
EV: Electric Vehicle, in the context of public charging points in council car parks
CSC: Customer Service Centre, the council's main phone and online contact point
LGR: Local Government Reorganisation, the process of restructuring local authorities
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item37
Resolved
That Cabinet noted progress against the Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A) and approves new projects, milestones and changes to milestones. REASON FOR DECISION: The Council Delivery Plan (CDP) monitoring reports provide Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities. Overview and Scrutiny Committee have the opportunity to review the monitoring reports sent via the Members Information Bulletin (MIB) and request more detailed updates to be presented. That Cabinet noted progress against the Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A) and approves new projects, milestones and changes to milestones. REASON FOR DECISION: The Council Delivery Plan (CDP) monitoring reports provide Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities. Overview and Scrutiny Committee have the opportunity to review the monitoring reports sent via the Members Information Bulletin (MIB) and request more detailed updates to be presented.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
This report presents progress on delivering the Council Delivery Plan for 2026-27. This is a Quarter 1 update, but generally reflects progress up to the point that the report was prepared (early August 2026). The report includes: • For the projects identified by Cabinet, it details milestones and progress against them. • The risks in relation to the delivery of those projects, as well as the corporate risks that could impact the delivery of all our projects and services. • Latest data for the Council’s key performance indicators (KPIs).
Points to note: • A new item relating to the Royston Learner Pool has been added to the Council Delivery Plan. • 2 Projects have an amber delivery status – Decarbonisation of Council Buildings, Phase 2 and Resident/Public EV charging in our car parks. • 6 Projects have proposed changes to milestones - highlighted in yellow on the report. • 3 Projects have proposed new milestones – highlighted in blue on the report.
Recommendations
2.1That Cabinet notes progress against the Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A) and approves new projects, milestones and changes to milestones.
Reasons for recommendations
3.1The Council Delivery Plan (CDP) monitoring reports provide Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities. Overview and Scrutiny Committee have the opportunity to review the monitoring reports sent via the Members Information Bulletin (MIB) and request more detailed updates to be presented.
Alternative options considered
4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee via the Members Information Bulletin (MIB), to enable them to provide additional oversight and support to Cabinet.
4.2Therefore, no alternative options were considered for this report.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Directors and Service Managers have provided updates on progress and will have made Executive Members aware of progress made.
5.2A draft of the Quarter 1 update was provided to the Risk and Performance Management Group (RPMG) in August 2026. The Group has a standing invite to the Executive Member for Resources (who has responsibility for performance monitoring), the Chair of Overview and Scrutiny Committee (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S, FAR, and Cabinet are also invited to attend if they can. RPMG were asked to comment on the Q1 update. There were no specific issues raised by the Group.
6. FORWARD PLAN
6.1This report contains a recommendation on a key Executive decision that was first notified to the public in the Forward Plan on the 19th June 2026.
Background
7.1The CDP brings together projects, risks and performance indicators in one document. The projects and performance indicators to be included are agreed by Cabinet in June each year, although can be added to during the year.
8. RELEVANT CONSIDERATIONS
8.1Appendix A provides an update on the progress made in delivering the Council Delivery Plan 2026-27. Whilst it is labelled as a Quarter 1 update, it generally reflects the latest position at the time that the report was written (early August). Milestones are set as far ahead as possible but are not included where there is too much uncertainty over the scope or timing of the milestone. In some cases, the expected actions are included, but without a target date.
8.2The focus of the report is on providing a description of the progress made. Projects are rated on overall progress i.e., shown as completed, on track, some delays, significant delays. Where there are delays, Cabinet will be asked to consider revisions to milestones.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.