Approved: To recommend to Council; That a schedule of savings amounting to £636,000 is approved for the General Fund budget for 2013/14. That proposed new developments amounting to £402,000 be included in the General Fund Budget for 2013/14. The Council’s draft General Fund Budget for 2013/14 of £11,650,700 which incorporates the above level of savings is approved. Parish precepts for 2013/14 amounting to £2,144,513 be approved. That a grant of £223,937 be made to Parish and Town Council’s in 2013/14 to compensate for the reduction in the Council Tax Base following the introduction of the Council Tax Support Scheme. After taking account of Revenue Support Grant, Business Rates and the Collection Fund Surplus the Council’s net budget requirement for 2013/14 is set at £4,726,400. For the purpose of Section 35(1) of the Local Government Finance Act 1992, the expenses of £136,900 incurred by the Council in performing the footway lighting function, which is also performed by Parish/Town Councils in other areas of the District, be confirmed as a special expense. 8. The forecast budgets of £11.6million for 2014/15 and £12.2million for 2015/16 are noted at this stage. 9. Based on the budget requirement, a Council Tax Band D of £140.04 be approved for 2013/14 which is an increase of £4.95 (3.66%) on the 2012/13 Council Tax of £135.09.
Word for word from the decision North Kesteven published for this meeting.Source: democracy.n-kesteven.gov.uk
Committee: Executive Board Meeting Date: 14 February 2012 Report presented by: Deputy Chief Executive Author: Alan Thomas Email: [email protected] Tel: 01526 308301
Report Title: The Council’s Draft General Fund Budget for 2013/14 to 2015/16 1. BACKGROUND
1.1At its meeting on the 10th January 2013 the Board agreed a Target Budget for 2013/14. This has been used to consult with representatives of council taxpayers through three budget consultation meetings. The budget details have also been discussed by the Overview and Scrutiny Panel members.
1.2The purpose of this report is to propose a General Fund budget for 2013/14 and forecast budgets for the following two years to 2015/16 following the consultation meetings.
2. PROJECTED OUTTURN FOR 2012/13
2.1A separate report on this agenda provides the Board with a detailed analysis of income and expenditure up to the 31st December 2012. The report indicates that many variations have taken place, and a potential surplus of £160,000 for the year is projected for the General Fund.
2.2The main reasons for the projected surplus for 2012/13 are as follows:-
Amount of Variation £ Vacancy savings and reduced staffing requirement (138,000) Reduction in capital and leasing costs (223,000) Reduction in income from fees and charges 123,000 Lower income expected from dry recyclables 100,000 Redistribution of surplus from Legal Services (31,000) Lincolnshire Lower contractor costs (26,000) Increased fuel costs 25,000 Other 10,000
Net Variance (160,000)
2.3The working balance on the General Fund is projected to be £1.2million at the 31st March 2013. This is a healthy position and therefore it is recommended that any surplus generated from the budget in 2012/13 is transferred to Reserves.
3. DRAFT BASE BUDGET FOR 2013/14
3.1The Council’s draft base budget for 2013/14 amounts to £11,884,700 which is £479,300 (4.2%) higher than the current year’s original budget. 3.2 The main areas for the increase in the draft base budget next year compared with the original budget for the current year are as follows: -
£ • Staff pay award, vacancy savings and increments 80,000 • Temporary arrangements around refuse rounds review 230,000 • Reduced Dry Recyclables income 100,000
3.3Contributions to the following reserves have been built into the draft base budget - Capital Reserve (£200,000) and ICT Reserve (£132,000). A further £100,000 contribution has been included for the Renewals Reserve to cover maintenance at the North Kesteven Sports Centre. A contribution of £541,000 to the Refuse Vehicle Replacement Reserve is also included in the draft base budget based upon a previous decision made by the Executive Board. £50,000 will be transferred from the Planning Delivery Grant Reserve to support the costs of the Joint Planning Unit next year.
3.4The base budget has been compiled using the following assumptions:-
• A provision for pay awards of 1% is included for 2013/14 and 2% for the following 2 years; • Staff turnover will generate a 1% saving on the total salary costs; • Refuse vehicles are financed by outright purchase with a separate maintenance contract; • The redevelopment of Sleaford swimming pool will be partly financed through borrowing as previously agreed; • External funding from Partners will be at the same level as the current year; • Funding for the Council Tax Support scheme will be on the basis of recovering the full funding gap.
Proposed New Developments
3.5A number of new developments have been put forward for inclusion within the draft budget over the next 3 years. A schedule of the proposed new developments is attached at Appendix 2 and amounts to £402,000 in 2013/14, £659,000 in 2014/15 and £666,000 in 2015/16. The Board will need to decide if any or all of these new developments should be included within the budget.
Proposed Budget Savings
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.