North Kesteven District Council
Executive Board, Thursday 14 February 2013 at 2.00pm

The Council's Housing and Non-Housing Capital Programme 2013/14 - 2015/16

Approved Executive 6 papers

Executive Board approved this item on Thursday 14 February 2013. Below is the council's own wording, with the papers it was decided on.

Item120

Resolved

Approved: To recommend to Council that the revised Capital Programme for 2012/13 and proposed Capital Programmes for 2013/14 to 2015/16 to be approved.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board

Summary

• The Executive Board at its meeting on 4 December 2013 approved a draft Capital Programme for both the Council’s housing and non-housing capital programmes.

• A detailed review has been completed to confirm all the current funding for the current approved programme for 2012/13. This has highlighted that a number of schemes are likely to slip into 2013/14. These schemes are detailed in appendix 1 and total £288,300 for the housing programme and £210,200 for the non-housing programme. Explanations from officers as to why schemes are likely to slip are also included.

• Furthermore, the land acquisitions at Mareham Lane and Grantham Road Sleaford remain shown for 2012/13. There are risks around these being completed for 2012/13 and, therefore, these may slip as well.

• The Council’s capital programme for 2013/14 to 2015/16 has been compiled and summarised in appendix 2 including for the slipped schemes. The most significant part of the programme relates to the Council’s housing capital programme which now totals £10,712,500, £13,472,900 and £7,643,100 for 2013/14, 2014/15 and 2015/16 respectively and is a result of the Council moving into Self Financing for its housing landlord function and the abolition of the previous housing finance regime of Housing Subsidy.

• The housing capital programme contains the continuation of the Council’s new build programme with £3.8million, £6.8million and £0.5million for 2013/14, 2014/15 and 2015/16 respectively. In 2015/16 there is also a further £4.8million identified for the first phase of redeveloping Newfield Road.

• Under Self Financing the Council has a “cap” of £80.070 million on the total amount of borrowing it can hold against its housing stock. Following the introduction of Self Financing, the Council had to buy out of the old subsidy regime by taking on a loan of £56.867million giving it a total housing debt of £70.406 million. During 2012/13, the council opted to take out the available headroom up to the cap in order to fund the housing capital programme and the continuation of the new build to 2015/16. Each year, the Council is making principal repayments of this debt in excess of £2 million. However, the capital programme assumes that this will be reinvested back into the new build programme with the Council remaining at its borrowing cap over the period 2013/14 to 2015/16.

• The non-housing capital programme now totals £3,317,300, £698,000 and £398,600 for 2013/14, 2014/15 and 2015/16 respectively with the main item in the programme being the refurbishment of the Sleaford Pool.

• The latest intelligence on heating systems sees a greater requirement for more traditional boilers. Therefore, £272,000 has been vired from the Energy Conservation budget to the Boilers budget for 2012/13 in order to allow the achievement of this during the year.

• The engineering budget for 2012/13 has been increased by £40,000 due to additional income being received from Lincolnshire County council to fund additional specific works.

• As with previous years, the funding of disabled facilities grants of £364,000 per annum includes for a Council contribution of £100,000 which it will finance from borrowing. For 2013/14, £55,200 has slipped from 2012/13 which means that £419,200 is now budgeted to be spent during the year on disable facilities grants.

• Two schemes were originally moved from 2012/13 to 2013/14 as part of the draft Capital Programme approved by the Executive Board on 4 December 2012:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme: APPENDIX 1 (V2): Carry Forward Requests into 2013-201Appendix 13 KB Download
PDF
Capital Programme: Appendix 2: SummaryAppendix 23 KB Download
PDF
Capital Programme: Appendix 3: Detailed SchemesAppendix 26 KB Download
PDF
Capital Programme: Appendix 4: Funding SummaryAppendix 31 KB Download
PDF
Capital Programme: Appendix 5: New Build Proposals: 7 Jan 13Appendix 24 KB Download
PDF
The Council's Housing and Non-Housing Capital Programme 2013/14: 2015/16Report 111 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. The Council's Housing and Non-Housing Capital Programme 2013/14 - 2015/16This decision
  2. The Council's Housing and Non-Housing Capital Programme 2015/16, 2016/17 and 2017/18Approved
  3. The Council's Housing and Non-Housing Capital Programme 2015/16, 2016/17 and 2017/18Approved
  4. The Council's Housing and Non-Housing Capital Programme 2014/15 to 2016/17Approved
  5. The Council's Housing and Non-Housing Capital Programme 2013/14 to 2015/16Approved
  6. The Council's Housing and Non-housing Capital Programme 2013/14 - 2015/16Approved

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies