CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
North Kesteven District Council
Executive Board, Thursday 14 February 2013 at 2.00pm

Infrastructure Planning in Central Lincolnshire

Approved Executive 2 papers

Executive Board approved this item on Thursday 14 February 2013. Below is the council's own wording, with the papers it was decided on.

Item134

Resolved

Approved: 1. That progress on the development of an Infrastructure Delivery Plan and that the plan for its future development be noted. 2. That Officers continue to prepare the Infrastructure Delivery Plan and Community Infrastructure Levy charging schedule, based on the general approach, reporting and timetable set out in the report.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board

Committee: Executive Board Meeting Date: 14 February 2013 Report presented by: Corporate Director Author: Stephen Priestley and Brendan Gallagher (LCC) Email: [email protected] Contact No: 01522 554845 Report Title: Infrastructure Planning in Central Lincolnshire Key Decision Yes No x Recommendation to Council Yes No x Council Meeting Date: Is this report exempt or confidential Yes No

Purpose of Report Members will be aware of the infrastructure planning work on-going in Central Lincolnshire. The purpose of this report is to provide an update on this work, particularly around development viability and infrastructure priorities.

1.0Introduction Sustainable growth requires the delivery of appropriate levels of supporting infrastructure. This infrastructure can only be provided at a cost. Some of this cost can be met from applying planning obligations against developments but additional funding will also be required, from other sources as well. Therefore a key area of work in demonstrating a deliverable sustainable growth agenda is to: -

• Set out the infrastructure that is required to support growth • Set out the estimated cost assumptions for the infrastructure needed • Identify the potential sources of funding to meet the infrastructure costs – including establishing the viable levels of Community Infrastructure Levy and other planning obligations • Prioritising the infrastructure for delivery

The report outlines progress on the infrastructure priorities and viability work areas undertaken by a working group of officers from the JPU and partner authorities. The work has implications for the Central Lincolnshire growth objectives. Information in and appended to this report will provide an introduction and context for future key decisions required by this Executive Board in respect of the Council’s duties and responsibilities as Charging and Collecting Authority in the setting of a District Community Infrastructure Levy as set out in the Community Infrastructure Levy Regulations 2010 (amended by the Community Infrastructure Levy (Amendment) Regulations 2011).

3.0Infrastructure Delivery Plan Infrastructure planning is a useful tool to help decision making on, and the alignment of, local authority resources and spending. It is also needed to demonstrate deliverability in plan-making (as required by the National Planning Policy Framework and advised by Planning Inspectorate guidance).

The Central Lincolnshire authorities have, therefore, developed an Infrastructure Delivery Plan (IDP). It is important to note that support from different areas of the four authorities will be needed if this is to be successful and in order to provide a coherent message at Examination in Public.

The IDP has been presented to councillors of all four authorities, as well as the Central Lincolnshire Joint Strategic Planning Committee (CLJSPC) meetings and briefings. The CLJSPC is responsible for the development and approval of the IDP for submission alongside the Core Strategy (as part of its evidence base). The draft IDP was approved at the 5th December 2011 Committee for consultation. It included information on infrastructure needs and costs, funding bodies and delivery partners, and links to specific proposed developments. It also set out a proposed approach to infrastructure priorities (which is now under review, within the context of the approach set out below).

In assessing infrastructure need in the draft IDP, the type, scale and distribution of infrastructure items have been informed by assumptions about the level, location and phasing of development, including the Sustainable Urban Extensions, in the Core Strategy. The IDP (and the work behind it) will continue to be updated alongside the Core Strategy production. Types of infrastructure needs covered include transport, health, education, utilities and green infrastructure

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
130214IDP appendix 1 onlyAppendix 98 KB Download
PDF
Infrastructure Planning in Central LincolnshireReport 144 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Infrastructure Planning in Central LincolnshireThis decision
  2. Integrated Planning and Delivery: Economy, Housing and InfrastructureAgreed

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies