Resolved

Approved: 1. The Draft Residents’ Parking Scheme Policy for consultation. 2. To commence engagement with residents and businesses in Sleaford, Sleaford Town Council, local Members, Lincolnshire County Council Highways and other interested parties regarding proposals to introduce Residents’ Parking Schemes in Sleaford in accordance with the Sleaford Car Parking Strategy.
Word for word from the decision North Kesteven published for this meeting. Source: democracy.n-kesteven.gov.uk

Follow this further

Built from North Kesteven's papers

What the report saysPro

Report to Executive Board

Purpose of report

To consider options around the introduction of Residents’ Parking Schemes.

Background

Civil Parking Enforcement (CPE) was introduced in Lincolnshire in December 2012. This transferred the powers for the enforcement of on-street parking from the Police to Lincolnshire County Council.

For a number of years prior to the introduction of CPE the Police had undertaken relatively little car parking enforcement activity. This led to widespread illegal parking, particularly in Sleaford, as there was relatively little risk of penalties being applied.

For a number of years there has been some interest from residents of Sleaford in the introduction of Residents’ Parking Schemes (RPSs), due to the parking of non-residents (visitors and employees) on residential streets with unrestricted parking, leading to residents finding it difficult to park near their homes. The introduction of CPE, and the increased enforcement of parking restrictions, has made this problem worse.

However the commencement of CPE also offers the opportunity to consider the introduction of RPSs – previously, as there was no effective enforcement, the schemes would have been unable to operate effectively. To date residents who enquired about such schemes have been advised that RPSs were not feasible until CPE was in place.

In 2010 work was undertaken to produce a Sleaford Car Parking Strategy. The preferred option to address issues of parking and traffic included a proposal for 5 RPSs in and around the town centre.

There have been no demands/requests for residents parking in other areas of the District.

Financial information

The general principle that should be employed for RPSs is that the residents who benefit from their introduction should meet the costs of establishing and running the schemes.

Research has indicated that set-up costs may typically be £4,000 – £5,500 per scheme, depending on their size: there is also a cost for the annual issuing of permits. Set up costs can be recovered over time from the annual charges levied. Set up includes:- 1. Initial consultation with residents, collation of results, design of scheme, formal consultation on proposed Traffic Regulation Order (TRO), production of reports.

2. Advertising/making TRO;

3. Site works (lines and signs).

(Steps 2 and 3 would be undertaken by the County Council which would recharge this Council. Step 1 contains elements that could be undertaken using existing resources and other elements that would need to be bought in.)

Data regarding annual permit costs from neighbouring authorities which have established/are considering RPSs are as follows:-

City of Lincoln – £26 Newark and Sherwood - £25 South Kesteven – Est. £50-£100 (scheme not yet in place)

In setting up a scheme it is a pre-requisite that a majority of residents vote to approve the introduction of a scheme. In light of the strategic need for such RPSs as identified in the Sleaford Car Parking Strategy it would be necessary to ensure that the suggested fees would be acceptable to residents.

There would be an anticipated increase in car parking income as a result of on-street parking being made more difficult but the financial impact of this is difficult to estimate and will depend on the extent and number of schemes introduced.

Timescales

Once the consultation and scheme design etc has been undertaken (Step 1 above) the process of introducing the necessary TROs etc. for the implementation of the schemes is estimated to take at least 6 – 7 months.

Suggested next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Residents Parking Scheme Policy: Appendix 1Appendix 35 KB Download
PDF
Residents' Parking SchemesReport 90 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at North Kesteven

Search all
  1. Residents' Parking SchemesThis decision
  2. Residents' Parking Schemes in SleafordApproved
  3. Residents Parking SchemeDecided
  4. Residents Parking SchemesApproved

More from North Kesteven Executive Board

All decisions
MeetingDecisionOutcome
3 Nov 2026 Proposed Private Hire and Hackney Carriage Fees and ChargesRecommended to Council: That approval be given to undertake a consultation process on the proposed draft licensing fe... Approved Open
3 Nov 2026 Review of The Private Sector Housing Enforcement PolicyThat the contents of the report and policy was noted. 2. That Executive Board approved the adoption of the new Privat... Noted Open
3 Nov 2026 NK Plan Quarter 2 Performance Report 2026/27That the key performance indicator progress in the NK Plan was approved. 2. That the Housing Regulatory Performance r... Approved Open
3 Nov 2026 Grantham Road Car ParkThat the appropriation of the part of the Grantham Road site shown on the plan at Appendix 1 from the Housing Revenue... Approved Open
3 Nov 2026 Medium Term Financial Strategy for 2027/28That the Medium Term Financial Strategy for 2027/28 to 2031/32 was approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies