ItemCOU167
Resolved
(1) that Council agree to spend £7.392M for the 2021-22 financial year, in accordance with previous MetroWest reports, from the already secured project funding sources. This funding will progress technical work feeding into the Full Business Case, including completion of Development Consent Order process (DCO) and to commence the detailed design. (2) that Council notes that reporting of spend against this allocated budget will form part of monthly Capital Programme financial reports to the Executive; and (3) that Council notes that in the MetroWest Phase 1 report to 10th November 2020 full council meeting, it indicated that officers were working on opportunities to mitigate the time delay of 9 months to the project caused by Covid. Should these opportunities involve accelerating works and therefore spend these will be outside of the above allocation but part of the total project costs.