North Somerset Council
Council, Tuesday 12 July 2022 at 6.00pm

MetroWest Phase 1 Update

Noted Committee 1 paper

Council noted this item on Tuesday 12 July 2022. Below is the council's own wording, with the papers it was decided on.

ItemCOU38

Resolved

that the Council 1. Noted the project update and that the project was currently paused, and will remain paused, while formal confirmations were awaited from the Department for Transport and the West of England Combined Authority regarding additional funding required to take the project forward, as set out in recommendations 2 and 3 of the report; 2. Agreed that, subject to: a. approval of the final business case (anticipated autumn 2023), b. confirmation from the West of England Combined Authority of increased capital funding of £10m c. confirmation of increased contribution to capital funding by Department for Transport of £15.58m, and d. confirmation by the Department for Transport that it will take the delivery risk for all the railway works, that the North Somerset Council capital funding contribution to MetroWest be increased by £10m, to be funded from borrowing, and 3. That the capital budget be amended to increase the budget by £35.58m to £152.01m to be funded by the additional £10m as per recommendation 2, a further £15.58m by the Department for Transport and a further ... view the full minutes text for item COU38
Word for word from the decision North Somerset published for this meeting. Source: n-somerset.moderngov.co.uk

Follow this further

Built from North Somerset's papers

What the report saysPro

Report to Council
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
MetroWest Phase 1 UpdateReport 286 KB Copy on its way

More from North Somerset Council

All decisions
MeetingDecisionOutcome
1 Apr 2025 Minutesthat the minutes from 18 February be approved as a correct record. Approved Open
1 Apr 2025 Forward Plan dated 3 March 2025Resolved : that Council noted the Forward Plan. Noted Open
1 Apr 2025 Banwell Bypass - Notice to proceed with constructionthat Council: approved the notice to proceed to stage 2 of the build contract for the build of Banwell bypass with Ga... Approved Open
1 Apr 2025 Adult Social Services and Housing Commissioning Intentions 2025-26that Council: agreed the Adult Social Care and Housing commissioning intentions for the next 18months. approved the c... Agreed Open
1 Apr 2025 Climate Emergency Strategy and Action Plan update and progress reportthat Council: 1. approved that from 2026/27 the Council ceases payments into the Green Energy Premium Tariff. 2. agre... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies