North Somerset Council
Council, Monday 19 July 2021 at 3.00pm

MetroWest Phase 1 - Delivery Update (includes exempt appendix) (Agenda Item 23)

Agreed Committee 2 papers

Council agreed this item on Monday 19 July 2021. Below is the council's own wording, with the papers it was decided on.

ItemCOU48

Resolved

(1) (a) that authority be delegated to the Director of Place, in consultation with the Executive Member for Assets and Capital Delivery, the Assistant Director Legal & Governance & the Director of Corporate Services, to enter into (jointly with the West of England Combined Authority(WECA)) an Implementation Agreement with Network Rail, Part 1 – Detail Design GRIP5 and subsequent addendums to the agreement as outlined in section 5 of the report, as per the values in confidential appendix 2 of the report, leading up to Full Business Case approval, subject to: (b) North Somerset Council (NSC) and WECA firstly entering into a Side Agreement to extend the 50:50 cost sharing to include all project costs (except revenue costs associated with the operation of the train service), through to the completion of the project, including risks and liabilities arising from NSC entering into Protective Obligations and Protective Provision Agreements with statutory undertakers, as set out in section 4 of the report; (2) that Council notes that following completion of Detailed Design GRIP5 and the approval of the Full Business Case, a separate report will be brought to Council in summer 2022 seeking authorisation to proceed with Part 2 of the Implementation Agreement and award construction contracts including GRIP 6-8, via Network Rail and authorisation for all other contract awards required to implement the project and re-open the branch line for scheduled passenger train services; (3) that Council authorise the Client Owned Scope Procurement Plan, attached at appendix 1 of the report and outlined in section 6 of the report, entailing the procurement of the (NSC & WECA) scope of works via the route to market identified for each package at an estimated cost of between £0.800M and £1.100M leading up to Full Business Case approval; (4) that the Director of Place be authorised to agree terms for the acquisition of land by agreement ... view the full minutes text for item COU48
Word for word from the decision North Somerset published for this meeting. Source: n-somerset.moderngov.co.uk

Follow this further

Built from North Somerset's papers

What the report saysPro

Report to Council
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
23.1 Appendix Draft Procurement PlanAppendix 343 KB Copy on its way
PDF
MetroWest Phase 1: Delivery Update (includes exempt appendix) (Agenda Item 23)Appendix 326 KB Copy on its way

At this meeting

Whole meeting
COU28Public Participation, petitions, and deputations (Standing Orders 2(vi) and 17) (Agenda Item 1)On the agenda COU31Minutes - 20 April 2021 (Agenda Item 5)Approved COU33Motions by Members (Standing Order No. 14)On the agenda COU37Forward Plan dated 2 July 2021 (Agenda Item 11)Noted COU38Corporate Parenting (Agenda Item 13)Noted COU39Question Time (Standing Order No. 18) (Agenda Item 14)On the agenda COU40Reports and matters referred from the Policy/Overview and Scrutiny Panels other than those dealt with elsewhere on this agendaNoted COU41Heritage and Regeneration Champion Report (Agenda Item 18)Noted COU42Reports on joint arrangements and external organisations and questions relating thereto: Avon Fire Authority (Agenda Item 19 (1))Noted COU43Reports on joint arrangements and external organisations and questions relating thereto: Avon and Somerset Policy and Crime Panel (Agenda Item 19 (2))Noted COU44Reports on joint arrangements and external organisations and questions relating thereto: West of England Joint Scrutiny Committee (Agenda Item 19 (3))Noted COU45Development Programme: Business Case and Commissioning Plan for Development of Council-owned Land to the south of The Uplands, Nailsea (Agenda Item 20)Approved COU46Submission of Bid to the Levelling Up Fund (Agenda Item 21)Approved COU47Adoption of the North Somerset Active Travel Strategy (ATS) (Agenda Item 22)Approved
COU48MetroWest Phase 1 - Delivery Update (includes exempt appendix) (Agenda Item 23)This decision

On this subject at North Somerset

Search all
  1. MetroWest Phase 1 - Delivery Update (includes exempt appendix) (Agenda Item 23)This decision
  2. MetroWest Phase 1 Update - governance and funding agreementsNoted
  3. MetroWest Phase 1 UpdateNoted
  4. MetroWest Phase 1 - 2021/22 Budget (Agenda Item 21)Agreed

More from North Somerset Council

All decisions
MeetingDecisionOutcome
1 Apr 2025 Minutesthat the minutes from 18 February be approved as a correct record. Approved Open
1 Apr 2025 Forward Plan dated 3 March 2025Resolved : that Council noted the Forward Plan. Noted Open
1 Apr 2025 Banwell Bypass - Notice to proceed with constructionthat Council: approved the notice to proceed to stage 2 of the build contract for the build of Banwell bypass with Ga... Approved Open
1 Apr 2025 Adult Social Services and Housing Commissioning Intentions 2025-26that Council: agreed the Adult Social Care and Housing commissioning intentions for the next 18months. approved the c... Agreed Open
1 Apr 2025 Climate Emergency Strategy and Action Plan update and progress reportthat Council: 1. approved that from 2026/27 the Council ceases payments into the Green Energy Premium Tariff. 2. agre... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies