ItemCOU61
Resolved
that 1) The Council noted that since the report to Council of 12th July 2022 that a) the additional £35.58m project capital funding had been confirmed by the project funding partners and the project had therefore resumed. b) the Department for Transport (DfT) confirmed that it will take the project delivery risk going forward via its delivery agent Network Rail c) that the DfT would provide up to £13.80m funding for all project costs up to the submission of the Full Business ... view the full minutes text for item COU61
Word for word from the decision North Somerset published for this meeting.