MetroWest Phase 1 Update - governance and funding agreements

Noted Committee 5 papers

Council noted this item on Tuesday 8 November 2022. Below is the council's own wording, with the papers it was decided on.

ItemCOU61

Resolved

that 1) The Council noted that since the report to Council of 12th July 2022 that a) the additional £35.58m project capital funding had been confirmed by the project funding partners and the project had therefore resumed. b) the Department for Transport (DfT) confirmed that it will take the project delivery risk going forward via its delivery agent Network Rail c) that the DfT would provide up to £13.80m funding for all project costs up to the submission of the Full Business ... view the full minutes text for item COU61
Word for word from the decision North Somerset published for this meeting. Source: n-somerset.moderngov.co.uk

Follow this further

Built from North Somerset's papers

What the report saysPro

Report to Council
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
7.1 Appendix 1: Letter from Dft to NSC & WECA 19th July 22Appendix 565 KB Copy on its way
PDF
7.2 Appendix 2: Funding from NR to NSC Ag FFNRA Short v1 050922Appendix 259 KB Copy on its way
PDF
7.3 Appendix 3: Governance ChartAppendix 206 KB Copy on its way
PDF
7.4 Appendix 4: MWP1 Procurement Plan for NSC Full Council Nov 22: FinalAppendix 326 KB Copy on its way
PDF
MetroWest Phase 1 Update: governance and funding agreementsReport 335 KB Copy on its way

More from North Somerset Council

All decisions
MeetingDecisionOutcome
1 Apr 2025 Minutesthat the minutes from 18 February be approved as a correct record. Approved Open
1 Apr 2025 Forward Plan dated 3 March 2025Resolved : that Council noted the Forward Plan. Noted Open
1 Apr 2025 Banwell Bypass - Notice to proceed with constructionthat Council: approved the notice to proceed to stage 2 of the build contract for the build of Banwell bypass with Ga... Approved Open
1 Apr 2025 Adult Social Services and Housing Commissioning Intentions 2025-26that Council: agreed the Adult Social Care and Housing commissioning intentions for the next 18months. approved the c... Agreed Open
1 Apr 2025 Climate Emergency Strategy and Action Plan update and progress reportthat Council: 1. approved that from 2026/27 the Council ceases payments into the Green Energy Premium Tariff. 2. agre... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies