RESOLVED THAT: 1) The establishment of internal project governance be noted. 2) The progress of specialist advisors to deliver the feasibility stage of phase 1 of Coalville Project be noted. 3) The procurement of specialist advisors to conduct an options appraisal for the leisure and culture offer of the District be noted. 4) The creation of a Coalville Project reserve and re-assignment of underspent reserves be approved. Reason for decision: To seek Cabinet approval to re-assign underspent reserves into a Coalville Project reserve.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
1.1Following the May 2015 election, the Leader set out the regeneration of Coalville as one of the Council’s priorities, and gave responsibility for delivery to the Chief Executive. The Authority already had a number of Coalville-based projects underway including: collaboration with EMH to develop the former Pick and Shovel site on Memorial Square, now known as Royal Oak Court, providing 14 new affordable homes; the Coalville shop front improvement scheme, for businesses on High Street and Hotel Street; improvements to Coalville Market and the car park area which backs onto the Belvoir Centre.
1.2On 22 September 2015 Cabinet agreed to progress with the Building Confidence in Coalville project as outlined in that report (the “Coalville Project”) and to access the Scape Major Works framework in order to procure specialist advisors to commence the feasibility stage of potential works on Stenson Square (referred to as Phase 1 of the Coalville Project). 1.3 Cabinet agreed to receive quarterly update reports seeking approval to progress to the next stage of the Coalville Project.
1.4This report sets out progress since the last report including governance arrangements, stakeholder engagement and financial arrangements.
2.0PROJECT GOVERNANCE
2.1Recognising the importance and high profile nature of the Coalville Project specific internal governance arrangements have been established.
2.2A Programme Board comprising a senior responsible officer (SRO – Chief Executive), programme assurance (Head of Legal and Support Services), financial governance (Section 151 officer, Head of Finance, until appointment of an Interim Director of Resources) and a director (Director of Housing) reviews progress on the entire project monthly, reporting to Cabinet on a quarterly basis. This is the first of such reports.
2.3The Project Team meets weekly and includes the programme manager (Interim Head of Economic Development), and officers responsible for delivery of supporting workstreams.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.