RESOLVED THAT: 1. The estimated General Fund and HRA capital outturn for 2019/20 and planned financing be noted at appendices A and B 2. The draft Capital Programmes in 2020/21 be approved for consultation detailed in: · Appendix A – General Fund Capitals Schemes · Appendix B – HRA Capital Schemes And in 2021/22, these schemes only: · £755,000 for the vehicle replacements as detailed in Paragraphs 3.8 3. The proposed procurement routes in respect of vehicles, equipment and plant be noted and authority to award these contracts and any associated agreements furtherance of the project be delegated to the Strategic Director of Place in consultation with the portfolio holder, subject to final approval of the Capital programmes in February 2020. Reason for decision: To enable projects to be included in the Programmes for consultation.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Title of Report 2020/21 - 2024/25 DRAFT CAPITAL PROGRAMMES
Presented by Councillor Nicholas Rushton Corporate Portfolio Holder
Background Papers Corporate Scrutiny Public Report: Yes Committee Draft Minutes – 7 November 2019 Key Decision: Yes
Financial Implications The Draft General Fund Capital Programme for 2020/21 is £12.7m. The majority of the new investment is the redevelopment of Appleby Magna Caravan Park and the bridge works for the new Coalville Leisure Centre.
The Draft Housing Revenue Account Capital Programme for 2020/21 is £12.7m. The two main schemes are the Home Improvement Programme and the New Supply programme.
Signed off by the Section 151 Officer: Yes
Legal Implications None
Signed off by the Monitoring Officer: Yes
Staffing and Corporate None Implications Signed off by the Head of Paid Service: Yes
Purpose of Report To advise Members of the likely Capital Outturn and the relevant financing for 2019/20 for the General Fund and the Housing Revenue Account.
To seek approval to the Draft General Fund and HRA Capital Programmes for 2020/21 and to note indications for future years and associated funding for consultation.
Reason for Decision To enable projects to be included in the Programmes for consultation.
Recommendations 1) THAT THE ESTIMATED GENERAL FUND AND HRA CAPITAL OUTTURN FOR 2019/20 AND PLANNED FINANCING BE NOTED AT APPENDICES A AND B
2) THAT CABINET APPROVES FOR CONSULTATION THE DRAFT CAPITAL PROGRAMMES IN 2020/21 DETAILED IN: APPENDIX A – GENERAL FUND CAPITALS SCHEMES APPENDIX B – HRA CAPITAL SCHEMES AND IN 2021/22, THESE SCHEMES ONLY: £755,000 FOR THE VEHICLE REPLACEMENTS AS DETAILED IN PARAGRAPHS 3.8
3) THAT CABINET NOTES THE PROPOSED PROCUREMENT ROUTES IN RESPECT OF VEHICLES, EQUIPMENT AND PLANT AND DELEGATES THE AUTHORITY TO AWARD THESE CONTRACTS AND ANY ASSOCIATED AGREEMENTS FURTHERANCE OF THE PROJECT TO THE STRATEGIC DIRECTOR OF PLACE IN CONSULTATION WITH THE PORTFOLIO HOLDER, SUBJECT TO FINAL APPROVAL OF THE CAPITAL PROGRAMMES IN FEBRUARY 2020.
1.0INTRODUCTION
1.1By Regulation, all local authorities are required to have regard to the Prudential Code when setting their Capital Programmes. The core objectives of the Code are to ensure that Capital schemes are ‘Affordable, Prudent and Sustainable’. This is reviewed in conjunction with both the Capital Strategy and the Treasury Management Strategy Statement (TMSS) which contains indicators that evidence compliance with the Code. These strategies will be presented to members with the budget in February 2020.
1.2As part of the process of effectively assessing property items for inclusion in the capital programme, the Council has collated a Planned Preventative Maintenance (PPM) Schedule that prioritises works based on a matrix scoring system. Items of a capital nature that are essential have been included in the capital programme in 2020/21.
1.3Appendix A shows the General Fund estimated outturn for 2019/20 and the proposed Capital Programme for 2020/21 to 2024/25.
1.4There are no Special Expenses estimated for 2020/21.
1.5Appendix B shows the H.R.A. estimated outturn for 2020/21 and the proposed Capital Programme for 2021/22 to 2024/25.
2.0GENERAL FUND - ESTIMATED OUTTURN 2019/20
2.1The projected outturn for 2019/20 on General Fund schemes total £5.4m. This is a decrease in the year of £7.3m, against the original budget of £12.7m.
2.2This managed decrease is caused by the following:
£ £
Original Budget 2019/20 12,708,590
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.