RESOLVED THAT CABINET 1) Notes the estimated General Fund and Housing Revenue Account (HRA) Capital Outturn for 2020/21 and planned financing in Appendices A and B 2) Approves for consultation the Draft Capital Programmes in 2021/22 detailed in: · Appendix A: General Fund Capital Schemes · Appendix B: HRA Capital Schemes and in 2022/23, these schemes only. · £526,000 for the Vehicle replacements as detailed in Paragraph 5.10 3) Notes the proposed procurement routes in respect of vehicles, equipment and plant and delegates the authority to award these contracts and any associated agreements furtherance of the project to the relevant Strategic Director, in consultation with the relevant portfolio Holders, subject to the final approval of the Capital Programmes in May 2021 Reason for decision : To enable projects to be included in the programmes for consultation.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
Title of Report 2021/22 - 2025/26 DRAFT CAPITAL PROGRAMMES
Presented by Councillor Nicholas Rushton Corporate Portfolio Holder Background Papers Corporate Scrutiny Draft Public Report: Yes Minutes – 11 November 2020 Key Decision: Yes
Financial Implications As contained in the report.
Signed off by the Section 151 Officer: Yes
Legal Implications None
Signed off by the Monitoring Officer: Yes
Staffing and Corporate None Implications Signed off by the Head of Paid Service: Yes
Purpose of Report To advise Members of the forecast Capital Outturn and the relevant financing for 2020/21 for the General Fund and the Housing Revenue Account.
To seek approval of the Draft General Fund, and HRA Capital Programmes for 2021/22 and to note indications for future years and associated funding for consultation. Reason for Decision To enable projects to be included in the Programmes for consultation.
Recommendations THAT CABINET:
1) NOTE THE ESTIMATED GENERAL FUND AND HOUSING REVENUE ACCOUNT (HRA) CAPITAL OUTTURN FOR 2020/21 AND PLANNED FINANCING IN APPENDICES A AND B.
2) APPROVES FOR CONSULTATION THE DRAFT CAPITAL PROGRAMMES IN 2021/22 DETAILED IN: APPENDIX A: GENERAL FUND CAPITAL SCHEMES APPENDIX B: HRA CAPITAL SCHEMES AND IN 2022/23, THESE SCHEMES ONLY: £526,000 FOR THE VEHICLE REPLACEMENTS AS DETAILED IN PARAGRAPHS 5.10. 3) NOTES THE PROPOSED PROCUREMENT ROUTES IN RESPECT OF VEHICLES, EQUIPMENT AND PLANT AND DELEGATES THE AUTHORITY TO AWARD THESE CONTRACTS AND ANY ASSOCIATED AGREEMENTS FURTHERANCE OF THE PROJECT TO THE RELEVANT STRATEGIC DIRECTOR, IN CONSULTATION WITH THE RELEVANT PORTFOLIO HOLDER, SUBJECT TO FINAL APPROVAL OF THE CAPITAL PROGRAMMES IN FEBRUARY 2021.
1.0INTRODUCTION
1.1By Regulation, all local authorities are required to have regard to the Prudential Code when setting their Capital Programmes. The core objectives of the Code are to ensure that Capital schemes are ‘Affordable, Prudent and Sustainable’. This is reviewed in conjunction with both the Capital Strategy and the Treasury Management Strategy Statement (TMSS) which contains indicators that evidence compliance with the Code. These strategies will be presented to members with the budget in February 2021.
1.2As part of the process of effectively assessing property items for inclusion in the capital programme, the Council has collated a Planned Preventative Maintenance (PPM) Schedule that prioritises works based on a matrix scoring system. Items of a capital nature that are essential have been included in the capital programme in 2021/22.
1.3Appendix “A” shows the General Fund estimated outturn for 2020/21 and the proposed Capital Programme for 2021/22 to 2025/26.
1.4There are no Special Expenses estimated for 2020/21
1.5Appendix “B” shows the Housing Revenue Account (HRA) estimated outturn for 2020/21 and the proposed Capital Programme for 2021/22 to 2025/26.
2.0CONSULTATION WITH CORPORATE SCRUTINY
2.1As introduced last year as part of the 2020/21 budget setting process, a report was taken to the Corporate Scrutiny on the 11 November 2020 to seek feedback on early budget proposals. This was designed to enhance member scrutiny of the proposed budget changes for the forthcoming year, and also provide members with an opportunity to feed suggestions into the process.
2.2A link to the draft minutes is provided in the background papers on page one of the report. Members have made comments in relation to the Breedon Gate, Marlborough Square and Memorial Square proposals. None of the schemes have changed as a result of the comments made.
3.0GENERAL FUND CAPITAL PROGRAMME– ESTIMATED OUTTURN 2020/21
3.1The projected outturn for 2020/21 on General Fund schemes total £11.96 million. This is a decrease in the year of £963k against the original budget of £12.92 million.
3.2This managed decrease is caused by the following: £ £
Original Budget 2020/21 12,920,310
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.