BUDGET PROPOSALS FOR 2014/2015 TO 2016/2017 AND OPTIONS FOR COUNCIL TAX
DecidedFinance1 paper
Nottingham Fire and Rescue Authority - Finance and Resources decided this item on Friday 17 January 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED (1) to recommend to the Fire Authority at its meeting on 28 February 2014; (a) the Capital and Revenue Budgets for 2014/2015 set out in the report; (b) the outline Capital and Revenue Budgets for 2015/2016 and 2016/2017 set out in the report; (c) not to accept the Council Tax freeze grant being offered for 2014/2015; (d) to increase Council Tax for 2014/2015 by 1.9% on the proviso that the referendum limit remains at 2%; (2) to request the Chief Fire Officer to prepare a range of options which can be consulted upon to bring budgets into balance for 2015/2016 and 2016/2017 and to include these options within the budget report to full Fire Authority on 28 February 2014. Councillors Wheeler and Roberts asked that their vote against resolutions (1) (c) and (1) (d) above be recorded in the minutes.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Report to Nottingham Fire and Rescue Authority - Finance and Resources
Purpose of report
To allow Members to consider the options for the recommendation of a balanced revenue budget over the next three years to the Fire Authority for acceptance. Implications for Council Tax are also considered.
CONTACT OFFICER Neil Timms Name : Assistant Chief Officer, Finance & Resources Tel : (0115) 967 0880
1.1The Finance and Resources Committee is charged with considering the financial position of the Authority and proposing revenue and capital budgets to the Fire Authority for approval. The Fire Authority will also decide upon levels of Council Tax for the coming year and will consider the recommendations of the Finance and Resources Committee in doing so.
1.2In late December, the government announced the provisional grant settlement for 2014/2015 and for 2015/2016 which gives some certainty to budget planning those years. It is difficult to plan with any precision for later years. However, estimates have been made given the best information that is available at present.
2. REPORT
Capital Budget proposals 2014/2015 to 2016/2017
2.1The Authority maintains a sustainable Capital Programme that has been planned out over an extended period. This programme seeks to replace appliances and vehicles when they are approaching the end of their useful life, maintains a rolling programme of ICT replacements and a property programme that will both ensure that property remains fit for purpose, is appropriately located and can be contained within the internal capacity of the organisation to complete.
The proposed Capital Programme for 2014/2015 to 2016/17 is as follows:
2014/2015 2015/2016 2016/2017 £000’s £000’s £000’s Transport Rescue Pump 910,020 619,970 1,265,500 Replacement Vehicles Equipment 36,405 24,270 48,540 Light Vehicles 137,500 289,885 436,448 Total Transport 1,083,925 934,125 1,750,488
Information Technology Business Continuity and 30,000 30,000 30,000 Disaster Recovery Mobile Computing 0 0 0 Business Expansion 25,000 25,000 25,000 Replacement Equipment 85,000 85,000 85,000 Business Process 0 0 0 Automation Microsoft Software 200,000 0 0 Licences Telephone System PABX 250,000 0 0 Replacement Storage Area Network 100,000 0 0 and Back up solution Replacement Total Information 690,000 140,000 140,000 Technology
Finance Agresso Upgrade 0 70,000 0 New Payroll System 30,000 40,000 0 Total Finance 30,000 110,000
Total Programme 4,363,925 4,299,625 4,505,988
2.2Rescue pump renewals follow the usual practice of replacing four pumping appliances each year on a rolling basis to ensure that no appliance older than 12 years is in the fleet. The usual requirement would be for this budget to be over £1m in each year however the reduction in pumping appliances which has taken place over the past year or so is beginning to reflect in the replacement programme. The equipment budget reflects the equipment carried almost as part of the vehicle such as ladders, hose reels and pumps.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ...
Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.