Resolved
RESOLVED (1) to note and endorse the Strategic Risk Register; (2) to note and endorse the Corporate Risk Register; (3) to note the most significant risks facing the Authority.
Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 17 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (1) to note and endorse the Strategic Risk Register; (2) to note and endorse the Corporate Risk Register; (3) to note the most significant risks facing the Authority.
To present Members with updated Strategic and Corporate Risk Registers and associated commentary.
CONTACT OFFICER
Neil Timms Name : Assistant Chief Officer, Finance & Resources Tel : 0115 967 0880
Email : [email protected]
Media Enquiries Bridget Aherne Contact : (0115) 967 0880 [email protected] 1. BACKGROUND
1.1Members of the Finance and Resources Committee requested at the 12 July 2013 meeting that they receive a report twice a year that provides evidence of the Authority’s risk management activity, including up-to-date versions of the Strategic and Corporate Risk Registers and a list of the top ten corporate risks.
1.2Members also agreed at the 12 July 2013 committee to receive risk management training, and this has been arranged to commence at the rising of the meeting at which this paper is to be considered.
1.3The reporting of risk management activity to Members via the Finance and Resources Committee forms part of the Authority’s planned and systemic approach to the management of risk. The purpose of this is both to aid strategic decision making and provide assurance.
2. REPORT
2.1The Strategic Risk Register, which is used to ensure that the Authority has the flexibility to respond to factors that may affect long-term strategic vision or aims, has been updated and debated by Corporate Management Board (CMB). The Strategic Risk Register is attached at Appendix A.
2.2The amendments to the strategic risk register, together with the rationale for the changes are:
• the impacts from EU: admittance of new Member States – the potential financial impact of this is now considered to be a low risk and has been removed from the Strategic Risk Register (low levels of risk do not warrant management attention and are unlikely to influence strategic direction);
• Human Resources – this risk was quite specific and operational in its nature, rather than giving rise to an impact on strategic direction or objective-setting. It is already covered in the Corporate Risk Register and it is therefore not included in the Strategic Risk Register;
• the wider public sector – this describes the counterparty risk that public bodies with which the Authority may be engaged in partnership working become unable to fulfil their partnership obligations, thus threatening service delivery. This risk also provides an indication that even without a change in government policy, organisations may find that they are unable to respond rapidly enough to changes in their operating environment. 2.3 The Corporate Risk Register, which identifies significant operational risks that require the attention of, or monitoring by CMB, has been updated following consultation with the risk owners; consultation with Service Managers, allowing an opportunity for significant departmental risks to be escalated; and debated at CMB.
2.4To summarise, the key changes to the Corporate Risk Register were:
• Health, Safety, Welfare and Environment – it was agreed that the procedure which provides the operational intelligence required to protect life and property, was due to be reviewed. The Corporate Services Support Department has been charged by the Corporate Management Board with reviewing this process to ensure that it is fit for purpose, and this work will be planned for next year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CORPORATE RISK MANAGEMENTReport | 163 KB | DownloadRead as text |
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Jun 2026 | 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... | Approved | Open |
| 19 Jun 2026 | Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... | Approved | Open |
| 19 Jun 2026 | External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... | Decided | Open |
| 19 Jun 2026 | Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... | Noted | Open |
| 27 Mar 2026 | Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.