Resolved
RESOLVED to approve this joint scheme and agree to the project being accelerated forward in the Capital Programme.
Nottingham Fire and Rescue Authority - Finance and Resources approved this item on Friday 11 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to approve this joint scheme and agree to the project being accelerated forward in the Capital Programme.
To inform Members of a joint capital scheme involving Eastwood Fire Station, that may require some acceleration of the Capital Programme.
CONTACT OFFICER Neil Timms Name : Strategic Director of Finance & Resources
Tel : (0115) 967 0880
Email : [email protected]
Media Enquiries Bridget Aherne Contact : (0115) 967 0880 [email protected]
1 1. BACKGROUND
1.1Members may be aware that as part of the annual settlement the Department for Communities and Local Government (DCLG) set aside £75m of funding for capital schemes for which Fire and Rescue Services were invited to bid. The criteria for bids were quite narrow and centred around the implementation of types of initiatives set out in the Sir Ken Knight report.
1.2Bids needed to be submitted by 4 June 2014 for consideration by DCLG and Nottinghamshire have submitted two bids, one for the new Central Fire Station and one in respect of a development at Eastwood.
1.3As members have already approved the Central scheme there is no requirement for further approval but the Eastwood scheme is new and therefore does require Member approval. Should Members not wish to pursue the Eastwood scheme then the bid can be withdrawn.
2. REPORT
2.1One of the bidding criteria for the government’s transitional funding capital grant is that schemes should seek out collaboration with other emergency services, especially but not exclusively the Police.
2.2Nottinghamshire Fire and Rescue Service (NFRS) owns a retained fire station in Eastwood which is a shared premises with the East Midlands Ambulance Service for which they pay an annual rental. NFRS also rent a small piece of land to the NHS for use as a car park for their adjacent health centre.
2.3Recently Nottinghamshire Police have acquired a piece of land in front of the health centre and adjacent to the fire station for their own use, and the NHS and the Police have approached NFRS to see if there is any possibility of a joint development of the whole site.
2.4The idea is to create a single “campus” style development which includes buildings for Police, Fire, EMAS and the NHS and to share common areas such as canteen facilities, reception desk, gym etc. as well as a number of community and meeting rooms.
2.5Eastwood Fire Station is not in the best state of repair however it is not envisaged that it would be scheduled for redevelopment until about 2017, however this opportunity to create a joint service hub in Eastwood seems a logical thing to do. It also fits into the criteria for attracting government grant.
2.6There are very few details available at present about this development as at present there is only an agreement in principle from all four services. Nevertheless funding is to be made available from both the Police and the
2 NHS to finance their element of this. It is envisaged that EMAS will continue to rent their portion of the building from NFRS.
2.7This project will match the bidding criteria quite closely and therefore a capital grant bid has been submitted for £1.575m for the Fire Service element of this scheme. The overall cost is just over £5m but Police and NHS have committed to fund the balance. Ordinarily a refurbishment or rebuild of Eastwood might be expected to cost approximately £1.5m so a successful bid of this nature would represent a significant saving.
2.8Further reports will be brought back to Members when the bidding process is completed and there is more detail around the specifics of the scheme.
2.9Members are therefore asked to approve this joint scheme and agree to this project being accelerated forward in the Capital Plan.
The financial implications are set out in Paragraph 2.7 above.
4. HUMAN RESOURCES AND LEARNING AND DEVELOPMENT IMPLICATIONS
There are no human resources implications arising directly from this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EASTWOOD FIRE STATIONReport | 127 KB | DownloadRead as text |
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Jun 2026 | 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... | Approved | Open |
| 19 Jun 2026 | Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... | Approved | Open |
| 19 Jun 2026 | External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... | Decided | Open |
| 19 Jun 2026 | Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... | Noted | Open |
| 27 Mar 2026 | Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.