PROGRESS REPORT ON THE PROPOSED NEW STATION 18

Noted Finance 1 paper

Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 11 July 2014. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

RESOLVED (1) to note the report; (2) to approve the latest cost estimate of £4.95 million notwithstanding that this will be offset by £2.5 million of capital receipts and any subsequent rental agreement with the City Council
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Finance and Resources

Purpose of report

To update Members on the progress, costs and programme of the new Station 18 project.

CONTACT OFFICER Neil Timms Name : Strategic Director of Finance & Resources

Tel : (0115) 967 0880

Email : [email protected]

Media Enquiries Bridget Aherne Contact : (0115) 967 0880 [email protected] 1. BACKGROUND

1.1The authorisation to proceed with the sale of the existing Central Fire Station site, the relocation and building of a new Station 18 was covered in the original Fire Cover Review (FCR) presented and agreed by the Fire Authority (the sale and relocation of Central element) in February 2011.

1.2Once the sale and relocation of Central Fire Station was agreed a site search and feasibly study was carried out and a short list of suitable sites were identified; the preferred location being a former petrol filling station located on London Road.

1.3Between early 2012 to late 2012 negotiations with the vendor of the preferred site were conducted; however these were eventually abandoned as it became clear that the likelihood of completing the sale was becoming remote.

1.4From late 2012 discussions with the owner (Nottingham City Council) of the second favoured site at the former Gresham Works site, London Road began with an early agreement that the site would be sold to NFRS.

1.5The site was occupied by a number of City Council tenants all of whom were offered the opportunity to relocate to other Council properties or provided with assistance to move elsewhere. This process has taken some time with considerable effort on the part of the City Council where all but one of the tenants has now moved off the site.

1.6As part of the new station development the City Councils Emergency Planning Team (EPT) will relocate from Central Fire Station to the new station with NFRS; this will be under a long term lease arrangement.

1.7Site surveys and site investigations have been on-going from early this year and the project design teams have been working on the scheme since the beginning of 2013. The design is now agreed and has been submitted for planning approval with the City Council.

2. REPORT

THE CURRENT SITUATION

2.1Final Heads of Terms for the sale of the site and the subsequent lease agreement for the accommodation for the Emergency Planning Team are now with the City Council awaiting their agreement. Once these documents have been agreed the formal contracts can be drafted by the relevant legal representatives.

2.2At the time of writing the Council were still working through the legal proceedings with the last remaining tenant at the former Gresham Works site; once this process is complete the site should be available as vacant possession.

2.3As part of the due diligence being carried out for the purchase of the site a full intrusive site investigation (SI) was carried out week commencing 9 June 2014. Access to the site to carry out this SI had been delayed thus far due to the sitting tenant.

2.4The purchase of the site by NFRS is conditional on (amongst other things) the site being taken on vacant possession, the granting of planning permission and that the site is clear of contamination.

THE PROGRAMME

2.5The outline project programme is as follows:

2.5.1 Site investigation – w/c 9 June 2014

2.5.2 Site investigation laboratory test results – by mid-August 2014

2.5.3 Competitive tender the project works – September to mid-October 2014

2.5.4 Tender assessment period – mid-October to mid-November 2014

2.5.5 Appointment of the works contractor – mid to late November 2014

2.5.6 Contractor mobilisation period – December 2014 through to January 2015

2.5.7 Site purchase and completion of land sale – by December 2014

2.5.8 Contractor start on site – January 2015

2.5.9 Completion of a new fire station – March 2016

2.5.10 Decant from existing Central Station to new fire station – March / April 2016

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PROGRESS REPORT ON THE PROPOSED NEW STATION 18Report 425 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
MW
Councillor Malcolm WoodChair, present
JA
Councillor John AllinCommittee Member, present
CB
Councillor Chris BarnfatherCommittee Member, present
JC
Councillor John ClarkeCommittee Member, present
GW
Councillor Gordon WheelerCommittee Member, present
CM
Carol M JacksonConstitutional Services, present

On this subject at Nottingham

Search all
  1. PROGRESS REPORT ON THE PROPOSED NEW STATION 18This decision
  2. Internal audit progress report q3 2018/19 and proposed internal audit plan 2019-20Noted

More from Nottingham Nottingham Fire and Rescue Authority - Finance and Resources

All decisions
MeetingDecisionOutcome
19 Jun 2026 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... Approved Open
19 Jun 2026 Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... Approved Open
19 Jun 2026 External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... Decided Open
19 Jun 2026 Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... Noted Open
27 Mar 2026 Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies