REVENUE AND CAPITAL MONITORING REPORT TO NOVEMBER 2016

Noted Finance 1 paper

Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 20 January 2017. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

RESOLVED to: (1) note the contents of the report; (2) approve the capital variation of £190,000 in respect of the Breathing Apparatus project, as expenditure in advance of the main project to be carried out in 2017/18.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Finance and Resources

Purpose of report

To report to Members on the financial performance of the Service in the year 2016/17 to the end of November 2016. This report focuses on those key areas where outturn variances are likely to occur.

CONTACT OFFICER

Sue Maycock Name : Head of Finance

Tel : 0115 967 0880

Email : [email protected]

Media Enquiries Therese Easom Contact : (0115) 967 0880 [email protected] 1. BACKGROUND

1.1Budget monitoring is a key aspect of financial management for the Fire and Rescue Authority. Regular reporting of spending against both the revenue and capital budgets is a check that spending is within available resources and, if necessary, allows for financial resources to be re- assigned to meet changing priorities.

1.2For this report, those key areas with a higher risk of significant variance are reported on. An assessment of this risk has been made in the light of the size of the budgets selected and / or previous experience of variances, as well as the emergence of actual variances.

1.3In this financial year, the overall revenue budget is at its lowest level since 2007/08 and it is vital that an overview of the budgetary position during the year is maintained so that appropriate action can be taken in respect of significant variances and the budget is managed as a whole.

2 REPORT

REVENUE BUDGET

2.1Headlines: When the 2016/17 revenue budget of £41.295m was approved by the Fire Authority in February 2016 it was on the basis that a £98k deficit in the budget would be supported by a transfer from general reserves, resulting in a net revenue budget of £41.197m. This was in line with the Medium Term Financial Strategy which sets out as a principle that financial planning will take account of the possible use of reserves to minimise the effect of reductions in funding as a means of transition. However, at this stage in the year there is a forecasted underspend of £353k so the transfer from general reserves is unlikely to be necessary.

2.2The forecasted underspend of £353k is largely due to four significant variances:

2.2.1 A forecasted underspend of £276k relating to interest charges

2.2.2 A significant variance has arisen due to the number of wholetime employees falling faster than expected, meaning that staffing levels have already decreased to 474.6 FTE against the new approved establishment of 476. This, together with further retirements forecasted before the end of the financial year, means that the wholetime pay budget (excluding overtime) is no longer expected to significantly overspend. The creation of a £350k earmarked reserve, which Members approved to support the wholetime pay budget during this period of transition, is therefore unlikely to be required. This has resulted in a forecasted underspend of £350k against the contribution to earmarked reserves budget

2.2.3 Pre-planned and operational wholetime overtime is expected to overspend by £309k by the end of the year 2.2.4 The Authority has also received a £387k revenue grant from the Home Office due to its role as lead authority on the Emergency Services Mobile Communications Project. £207k of this grant has been redistributed to the other four fire and rescue services in the East Midlands region, and the remaining balance will be transferred to earmarked reserves.

2.2.5 These key variances are explained further in the report below. The Revenue Monitoring position is shown in summary at Appendix A.

2.3Wholetime Pay: the variance to date is a £175k overspend, and this budget is expected to be overspent by £257k by the end of the financial year. This is due to four main reasons:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
REVENUE AND CAPITAL MONITORING REPORT TO NOVEMBER 2016Report 382 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
MW
Councillor Malcolm WoodChair, present
JA
Councillor John AllinCommittee Member, present
CB
Councillor Chris BarnfatherCommittee Member, present
JC
Councillor John ClarkeCommittee Member, apologies, sent representative
DL
Councillor Dave LiversidgeCommittee Member, present
GW
Councillor Gordon WheelerCommittee Member, apologies, sent representative
JB
John BuckleyPublic, in attendance
TE
Therese EasomPublic, in attendance
SM
Sue MaycockOfficer, in attendance
IP
Ian PritchardPublic, in attendance
NT
Neil TimmsOfficer, in attendance
JW
James WelbournClerk, in attendance

All 14 on the meeting page

On this subject at Nottingham

Search all
  1. REVENUE AND CAPITAL MONITORING REPORT TO NOVEMBER 2016This decision
  2. 2025/26 Revenue and Capital OutturnApproved
  3. Revenue and Capital Monitoring Report to 30 April 2026Approved
  4. Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Approved
  5. Revenue, Capital and Prudential Code Monitoring Report to 30 November 2025Noted
  6. 2024/25 Revenue and Capital OutturnNoted

More from Nottingham Nottingham Fire and Rescue Authority - Finance and Resources

All decisions
MeetingDecisionOutcome
19 Jun 2026 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... Approved Open
19 Jun 2026 Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... Approved Open
19 Jun 2026 External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... Decided Open
19 Jun 2026 Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... Noted Open
27 Mar 2026 Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies