Resolved
RESOLVED to note the report and give authority to proceed with the project to build a new fire station on the existing site at Boundary Road.
Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 20 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the report and give authority to proceed with the project to build a new fire station on the existing site at Boundary Road.
To update Members on the Newark Fire Station Project and to seek authority to proceed with the construction of the new fire station.
CONTACT OFFICER John Buckley Name : Chief Fire Officer Tel : (0115) 967 0880
Email : [email protected] Media Enquiries Therese Easom Contact : (0115) 967 0880 [email protected] 1. BACKGROUND
1.1Members of the Committee will be aware that the replacement or refurbishment of Newark fire station is a key aim of the current Property Strategy and that financial support for the project has been factored into the current and anticipated capital programme.
1.2Newark fire station and the site is wholly owned by Nottinghamshire Fire and Rescue Service (NFRS). The main station building is of CLASP construction and was built in 1963. The remainder of the site comprises largely of storage and garaging, this is of traditional construction dating back to circa 1915. This part of the site was previously owned by what is now the Ministry of Defence (MoD).
1.3The total existing building floor area is in the region of 1,382 square metres including garaging and storage. This is considerably larger than other stations carrying out a comparable role.
1.4The main station building itself is over fifty years old and is now beyond its original life expectancy and planned for replacement in the Property Strategy.
1.5The station is currently a two pump station, one pump on the whole-time duty system and the second pump on the retained duty system (RDS). The RDS is one of a number of sections who also provide national resilience support for the high volume pump (HVP) capability; these vehicles are currently garaged at Newark in the old MoD buildings.
1.6From April this year the station also took on the role of the technical rescue station as part of the reorganisation of the Specialist Rescue Team.
1.7The new station will have three appliance bays, similar to that of Retford fire station, and will have a smaller building footprint of circa 685 square metres.
1.8The Newark fire station project has now developed and progressed to the stage where the estimated cost can be assessed prior to the return of tenders from the bidding contractors, and therefore enable Members to make a final decision on the proposed project.
2. REPORT
2.1This report is to provide a full update to Members on the progress of the proposed project for a new Newark fire station to be constructed on the existing site at Boundary Road, and to seek authority to proceed with the project.
2.2An option appraisal and feasibility study was carried out identifying the choices available for the replacement of the station; this was based on whole life cost in order to determine the best value option. These are shown in the table below. Option Description Estimated Estimated Whole Life Capital Cost Cost (incl 5% contingency allowance Option 1 Do nothing, the status quo £4.21M N/A
Option 2 Full refurbishment of the £4.22M N/A existing buildings
Option 3 Part demolition and part £4.00M N/A refurbishment of the existing buildings
Option 4 Demolish and rebuild on the £4.83M £3.57M same site
Option 5 Build a new station £4.64M £3.37M alternative site and dispose of the current site (disposal of existing site)
Option 6 Demolish and rebuild on £4.47M £3.19M one part of the same site (disposal of any residual land)
2.3Options 1, 2 and 3 would require the lifespan of the existing CLASP structure to be extended well beyond its original design life. Extending the life of the building to over ninety years was considered an unacceptably high risk. None of these options are considered feasible.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NEWARK FIRE STATION PROJECTReport | 170 KB | DownloadRead as text |
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Jun 2026 | 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... | Approved | Open |
| 19 Jun 2026 | Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... | Approved | Open |
| 19 Jun 2026 | External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... | Decided | Open |
| 19 Jun 2026 | Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... | Noted | Open |
| 27 Mar 2026 | Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.