NEWARK FIRE STATION PROJECT

Noted Finance 1 paper

Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 20 January 2017. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

RESOLVED to note the report and give authority to proceed with the project to build a new fire station on the existing site at Boundary Road.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Nottingham Fire and Rescue Authority - Finance and Resources

Purpose of report

To update Members on the Newark Fire Station Project and to seek authority to proceed with the construction of the new fire station.

CONTACT OFFICER John Buckley Name : Chief Fire Officer Tel : (0115) 967 0880

Email : [email protected] Media Enquiries Therese Easom Contact : (0115) 967 0880 [email protected] 1. BACKGROUND

1.1Members of the Committee will be aware that the replacement or refurbishment of Newark fire station is a key aim of the current Property Strategy and that financial support for the project has been factored into the current and anticipated capital programme.

1.2Newark fire station and the site is wholly owned by Nottinghamshire Fire and Rescue Service (NFRS). The main station building is of CLASP construction and was built in 1963. The remainder of the site comprises largely of storage and garaging, this is of traditional construction dating back to circa 1915. This part of the site was previously owned by what is now the Ministry of Defence (MoD).

1.3The total existing building floor area is in the region of 1,382 square metres including garaging and storage. This is considerably larger than other stations carrying out a comparable role.

1.4The main station building itself is over fifty years old and is now beyond its original life expectancy and planned for replacement in the Property Strategy.

1.5The station is currently a two pump station, one pump on the whole-time duty system and the second pump on the retained duty system (RDS). The RDS is one of a number of sections who also provide national resilience support for the high volume pump (HVP) capability; these vehicles are currently garaged at Newark in the old MoD buildings.

1.6From April this year the station also took on the role of the technical rescue station as part of the reorganisation of the Specialist Rescue Team.

1.7The new station will have three appliance bays, similar to that of Retford fire station, and will have a smaller building footprint of circa 685 square metres.

1.8The Newark fire station project has now developed and progressed to the stage where the estimated cost can be assessed prior to the return of tenders from the bidding contractors, and therefore enable Members to make a final decision on the proposed project.

2. REPORT

2.1This report is to provide a full update to Members on the progress of the proposed project for a new Newark fire station to be constructed on the existing site at Boundary Road, and to seek authority to proceed with the project.

2.2An option appraisal and feasibility study was carried out identifying the choices available for the replacement of the station; this was based on whole life cost in order to determine the best value option. These are shown in the table below. Option Description Estimated Estimated Whole Life Capital Cost Cost (incl 5% contingency allowance Option 1 Do nothing, the status quo £4.21M N/A

Option 2 Full refurbishment of the £4.22M N/A existing buildings

Option 3 Part demolition and part £4.00M N/A refurbishment of the existing buildings

Option 4 Demolish and rebuild on the £4.83M £3.57M same site

Option 5 Build a new station £4.64M £3.37M alternative site and dispose of the current site (disposal of existing site)

Option 6 Demolish and rebuild on £4.47M £3.19M one part of the same site (disposal of any residual land)

2.3Options 1, 2 and 3 would require the lifespan of the existing CLASP structure to be extended well beyond its original design life. Extending the life of the building to over ninety years was considered an unacceptably high risk. None of these options are considered feasible.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
NEWARK FIRE STATION PROJECTReport 170 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
MW
Councillor Malcolm WoodChair, present
JA
Councillor John AllinCommittee Member, present
CB
Councillor Chris BarnfatherCommittee Member, present
JC
Councillor John ClarkeCommittee Member, apologies, sent representative
DL
Councillor Dave LiversidgeCommittee Member, present
GW
Councillor Gordon WheelerCommittee Member, apologies, sent representative
JB
John BuckleyPublic, in attendance
TE
Therese EasomPublic, in attendance
SM
Sue MaycockOfficer, in attendance
IP
Ian PritchardPublic, in attendance
NT
Neil TimmsOfficer, in attendance
JW
James WelbournClerk, in attendance

All 14 on the meeting page

On this subject at Nottingham

Search all
  1. NEWARK FIRE STATION PROJECTThis decision
  2. Newark Fire Station ProjectNoted

More from Nottingham Nottingham Fire and Rescue Authority - Finance and Resources

All decisions
MeetingDecisionOutcome
19 Jun 2026 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... Approved Open
19 Jun 2026 Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... Approved Open
19 Jun 2026 External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... Decided Open
19 Jun 2026 Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... Noted Open
27 Mar 2026 Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies