Resolved
RESOLVED to note the contents of the report.
Nottingham Fire and Rescue Authority - Finance and Resources noted this item on Friday 31 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the contents of the report.
To update Members on the Newark fire station project and the appointment of a works contractor.
CONTACT OFFICER
John Buckley Name : Chief Fire Officer Tel : (0115) 967 0880
Email : [email protected]
Media Enquiries Therese Easom Contact : (0115) 967 0880 [email protected] 1. BACKGROUND
1.1Newark fire station and the site is wholly owned by Nottinghamshire Fire and Rescue Service (NFRS). The main station building is of CLASP construction and was built in 1963. The remainder of the site comprises largely of storage and garaging, this is of traditional construction dating back to circa 1915. This part of the site was previously owned by what is now the Ministry of Defence (MoD).
1.2The main station building itself is over 50 years old and is now beyond its original life expectancy and planned for replacement in the Property Strategy.
1.3The station is currently a two pump station, one pump on the wholetime duty system (WDS) and the second pump on the retained duty system (RDS). The RDS also provide a national resilience support along with crewing from other NFRS stations for the high volume pump capability; these vehicles are currently garaged at Newark in the old MoD buildings.
1.4From April 2016 the station also took on the role of the technical rescue station as part of the reorganisation a Specialist Rescue Team (SRT). This function is carried out by the WDS staff.
1.5The new station will have three appliance bays, similar to that of Retford fire station, and will have a smaller building footprint of circa 685 square metres compared with the existing floor area of 1,382 square metres.
1.6The authority to proceed with the replacement Newark Fire Station was confirmed by Members in January 2017.
2. REPORT
2.1This report is to update Members on the progress of the Newark fire station project and the results from the competitive tendering process and appointment of a building contractor.
2.2The high volume pump (HVP) vehicles and associated equipment, formally accommodated in the old MoD buildings, have now been relocated to Tuxford fire station. This now fully utilises the accommodation at Tuxford and also provided greater resilience for the national role utilising the RDS staff at the station.
2.3Planning permission has been granted by the Local Authority for the project with a number of conditions. Many of the conditions are standard planning requirements none of which are currently cause for concern.
2.4The pre-qualification and tendering process for the main contract works (the building contract) was carried out between November 2016 and March 2017. 2.5 In November 2016 an expression of interest was published nationally in the form of a pre-qualification questionnaire (PQQ). This was carried out using NFRS’s electronic tendering portal, In-Tend.
2.6Initially twenty contractors expressed an interest in the project and were sent the PQQ providing the information on the project and a set of questions to allow a pre-qualification process to by run. Out of the twenty, nine contractors completed and submitted the on-line PQQ.
2.7From these nine contractors the top five highest scoring contractors were invited to submit a tender for the works. The invitation to tender (ITT) was sent out in December 2016. The contractors shortlisted were:
J Tomlinson GF Tomlinson RG Carter Gelder Group Wildgoose Construction
2.8Shortly after the ITT was issued to the five contractors GF Tomlinson withdrew from the process. As this occurred early in the ITT process the next highest scoring contractor, Extraspace Solutions, were offered and subsequently accepted the invitation to submit a tender for the project.
2.9The tender scoring was based on 70% for the tendered price with the remaining 30% for the quality and technical element of the tender submission.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Newark Fire Station ProjectReport | 195 KB | DownloadRead as text |
Follow Nottingham Fire and Rescue Authority - Finance and Resources at Nottingham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Jun 2026 | 2025/26 Revenue and Capital OutturnResolved to 1. Scrutinise and gain assurance on the contents of this report. 2. Approve the use of underspend as set ... | Approved | Open |
| 19 Jun 2026 | Revenue and Capital Monitoring Report to 30 April 2026Resolved to (1) Scrutinise the financial outturn forecasts as at April 2026 as detailed in the report. (2) Approve th... | Approved | Open |
| 19 Jun 2026 | External Audit Plan 2025/26Resolved to scrutinise the contents of the External Audit Plan and Strategy and gain assurance on the approach being ... | Decided | Open |
| 19 Jun 2026 | Internal Audit Annual Report 2025/26Resolved to (1) Note the new Global Internal Audit Standards (GIAS) and associated CIPFA Application Note which now d... | Noted | Open |
| 27 Mar 2026 | Revenue, Capital and Prudential Code Monitoring Report to 31 January 2026Resolved (1) to approve the slippage, acceleration and underspend in the capital programme into / from 2025/26 as det... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.