Nottingham City Council
Executive Board, Tuesday 12 May 2026 at 2.00pm

Increase in Traffic Signals Maintenance Contract Value

Approved Executive 1 paper

AI summaryNottingham City Council Executive Board raised the Traffic Signals Maintenance Contract spend ceiling from £5m to £9.5m to cover grant-funded modernisation work already delivered.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedIncrease of £4.5m on the existing Traffic Signals Infrastructure Contract
Money£4.5 million increaseFunded by external grants, no council borrowing required
What happens nextSpend to continue through March 2027Lead contractor varying contract term to allow more time
Who it affectsAll wards across the cityTraffic signals infrastructure maintenance and modernisation

What was decided

The Executive Board approved an increased spend of £4.5m, taking the council's share of the Traffic Signals Infrastructure Contract from £5m to £9.5m. Report 5.1, 5.2

The increase covers maintenance and improvement of traffic signals across the city, with the overall £30m framework across partner authorities unchanged. Report 5.2, P6

Why

The original contract allocation, set in 2019, is nearing its limit because of higher-than-expected spending driven by grant-funded programmes that were not anticipated when the contract began. Report 2.1, 2.2

These additional programmes include £3.4m from Transforming Cities, £631k from the Traffic Signals Obsolescence Grant, and £500k of Local Transport Plan funding, which have modernised infrastructure, improved resilience, and reduced energy use. Report 2.2

The existing contract has performed well, with price rises limited to CPI and capped at 5% and the contractor meeting all key performance indicators. Report 2.2

What happens next

The lead contractor is in the process of varying the contract term to extend the spending window while partner councils go through local government reorganisation. Report P20, P21

No new procurement is required: the increase stays within the original OJEU-advertised terms and does not need a contract variation. Report 6.1, 7.1

The current contract is due to end in March 2027, with partner authorities considering a further extension. Report P6, P20

The money

  • £9.5 million New total spend ceiling for Nottingham City Council within the Traffic Signals Infrastructure Contract Report 5.2
  • £4.5 million Total value of the decision, being the increase in NCC's allocated contract spend Report 5.1
  • £30 million Maximum value of the overall framework across combined authorities, unchanged Report 5.2, P6
  • £5m Previous spend ceiling for Nottingham City Council within the contract Report 5.2
  • £3.4 million Transforming Cities grant funding contributing to the contract Report 2.2
  • £631k Traffic Signals Obsolescence grant funding Report 2.2
  • £500k Local Transport Plan funding contributing to the contract Report 2.2
  • 5% Maximum annual price increase under the contract, linked to CPI Report 2.2

Options considered

  • Chosen: Increase spend within the existing Traffic Signals Infrastructure Contract. Strong value for money with CPI-linked rises capped at 5%, good contractor performance against KPIs, and continued economies of scale with partner authorities. Report 2.2
  • Rejected: Tender a new separate contract solely for Nottingham's Traffic Signals Infrastructure. Would bring inflationary price rises, add annual maintenance charges for new assets, and lose the cost benefits of the existing shared contract. Report 3.1, P3

Implications

  • Financial: Additional spend is funded predominantly by external grants with no adverse impact on the Medium Term Financial Plan and no additional borrowing required. Report 5.3
  • Legal: No contract variation or further procurement is needed because the increase is within the value originally advertised via OJEU, and legal have no procurement law concerns. Report 6.1, 7.1
  • Risk: Risk of challenge from an alternative contractor has been reviewed by Legal, Finance and Procurement colleagues and is considered mitigated. Report P6
  • Climate: A Carbon Impact Assessment was not required for this decision, though earlier grant-funded modernisation has reduced energy use and lowered the city's carbon footprint. Report 2.2, 8.1
  • Equalities: An Equality Impact Assessment is not required as the decision continues existing service provision with no addition or change to services. Report 8.1, P26
  • Other: Social value commitments for the local economy, employment and community initiatives continue as a Key Performance Indicator within the contract. Report 8.2, P29, P32

Who and where

  • All wards across Nottingham City Report P43
  • Road users and residents served by the city's traffic signals network Report 2.2
  • Partner councils sharing the Traffic Signals Infrastructure Contract framework Report P6, P20
  • The lead contractor and its workforce delivering signals maintenance and modernisation Report 2.2, P20

Timeline

  • 2019: Original Traffic Signals Infrastructure Contract estimate created Report 2.1, 2.2
  • 10/09/2019: Contract awarded by the Commissioning and Procurement Sub-Committee Report 11.1, P40
  • 13/02/2026: Finance advice provided by Susan Turner, Strategic Finance Business Partner Report P13
  • 10.03.2026: Legal advice provided by Del Sander, Solicitor Report P17
  • 2026-05-12: Executive Board decision to increase the contract spend ceiling to £9.5m
  • End of March 2027: Current contract term due to end, with a variation being explored to extend it Report P20

Plain English for the jargon

  • CPI: Consumer Price Index, the standard measure of inflation used in the contract
  • OJEU: Official Journal of the European Union, used for public procurement notices
  • MTFP: Medium Term Financial Plan, the council's multi-year budget framework
  • KPI: Key Performance Indicator, a measurable target used to judge contractor performance
  • LTP: Local Transport Plan, a government funding stream for transport projects
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

Resolved to approve an increased spend value of £9.5 million (within the Traffic Signals Infrastructure Contract) to allow continued maintenance and improvement of Traffic Signals infrastructure across Nottingham City. Reason for decisions: the Council’s original contract spend allocation is nearing its limit due to higher-than-expected expenditure, primarily driven by additional grant-funded programmes such as Transforming Cities and Traffic Signals Obsolescence. These programmes, not anticipated when the contract was set in 2019, have significantly increased investment in traffic signal infrastructure across the city; the existing contract continues to provide strong value for money, with price increases limited to CPI and capped at 5%, and with the contractor consistently meeting performance standards. The additional investment has supported large-scale modernisation, improving resilience, reducing energy use, and lowering the city’s carbon footprint. Other options considered: carry out a tender process for a new separate contract solely for Nottingham Traffic Signals Infrastructure. This option was rejected, as there would be anticipated price rises due to inflationary pressures, the addition of annual maintenance charges compared ot the existing contract, and loss of economies of scale.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Reasons for recommendations

2.1The original spend value allocated to Nottingham City Council is now nearing its limit, due to greater than anticipated expenditure (associated with increased spending via Grant Funded programmes such as Transforming Cities and the Traffic Signals Obsolescence Grant).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Increase in Traffic Signals Maintenance Contract ValueReport 111 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
BB
Beth BrownOfficer, expected
MC
Michael CareyClerk, expected
SF
Stuart FairOfficer, expected
JH
Councillor Jay HayesCommittee Member, present
PU
Councillor Patience Uloma IfedioraCommittee Member, present
NJ
Nicki JenkinsOfficer, expected
HK
Councillor Helen KalsiCommittee Member, present
NK
Councillor Neghat KhanChair, present
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, present
SM
Councillor Sulcan MahmoodCommittee Member, present
NM
Neil McArthurOfficer, expected

All 21 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open