Fernwood Academy Special Educational Needs and Disabilities (SEND) Unit

Approved Executive 3 papers

AI summaryNottingham City Council Executive Board approved £830,000 extra funding for a SEND unit at Fernwood Academy, bringing total project cost to £3,980,000 for 24 pupils.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegated authority to spend £830,000 and award construction contract
Money£830,000 extra, total £3,980,000From carried forward High Needs Capital Grant
What happens nextNot stated
Who it affects24 Key Stage 3 and 4 pupils with SENDIncluding 20 new local authority commissioned places

What was decided

The Board authorised the allocation and spend of £830,000 of carried forward High Needs Provisions Capital Allowance Grant for additional design and construction costs of the SEND unit at Fernwood Academy Wollaton, bringing the total project cost to £3,980,000.

Authority was delegated to the Corporate Director for Children's and Education Services to procure and award the construction contract up to £3,214,500 using the SCAPE Regional Construction Framework, in consultation with the Executive Member for Employment, Education and Skills.

Authority was also delegated to modify the contract with Perfect Circle JV Ltd for professional fees using the SCAPE National Consultancy Framework, and to enter any necessary licence agreements with Fernwood Academy.

Why

The proposal will expand specialist SEND provision at The Fernwood School for 24 Key Stage 3 and 4 pupils with Moderate Learning Difficulties and some with Autistic Spectrum Disorder, including 20 new places commissioned by the local authority.

An additional £830,000 is required for design improvements including relocating the sensory garden, adding life-skills kitchens, and reconfiguring parking to support safe access and staff recruitment.

The updated design introduces calm spaces, improved circulation and drop-off arrangements, and expanded parking, aimed at reducing reliance on costly external placements and supporting inclusive provision within the community, in line with the Council's SEND Sufficiency Strategy.

What happens next

The Corporate Director for Children's and Education Services will spend the additional funding to address increased costs from change in scope, extended programme, additional professional fees, and inflation.

The Corporate Director will procure and award the construction contract up to £3,214,500, using the SCAPE Regional Construction Framework.

The Corporate Director will modify the Perfect Circle JV Ltd contract value for professional fees and enter any necessary licence agreements with Fernwood Academy to access the site and carry out works.

The money

  • £830,000 Additional funding from carried forward High Needs Provisions Capital Allowance Grant for design and construction
  • £3,980,000 Total project cost after additional funding
  • £3,214,500 Maximum value of construction contract to be awarded via SCAPE Regional Construction Framework
  • £372,226 Budget cost for proposed new car parking areas (additional scope requested) Report P2
  • £125,000 Increased cost due to inflation and programme delay from original cost submission Report P2
  • £70,000 Additional prelims for works to be done in summer, extending programme duration Report P2
  • £61,774 Client contingency Report P2
  • £55,000 Cost for designing new parking areas Report P2
  • £26,000 Fee for service agreement (SCAPE fees) Report P2
  • £24,000 Life skills kitchen ground floor (school request) Report P2
  • £24,000 Additional sensory garden equipment (school request) Report P2
  • £20,000 Major Projects internal fees Report P2
  • £20,000 Perfect Circle Quantity Surveyor and Contract Administration Report P2
  • £19,000 Life skills kitchen first floor (school request) Report P2
  • £10,000 Pre-construction charge (SCAPE fees) Report P2
  • £3,000 Addition for removing existing sensory garden offsite (school request) Report P2

Options considered

  • Rejected: Continue with the previous plans within the already approved funding. Would provide a sub-optimal educational offer for children with SEND who the provision is designed to support
  • Rejected: Halt the project and charge all current expenditure to revenue. Would create a significant revenue pressure and would not address the priority needs identified in Phase 1 of the SEND Capital Strategy 2023-28 or in the updated Strategy approved by Executive Board on 24 February 2026

Implications

  • Financial: Additional £830,000 spend required, bringing total project cost to £3,980,000, funded from carried forward High Needs Provisions Capital Allowance Grant.
  • Financial: Construction contract to be awarded up to £3,214,500 via SCAPE Regional Construction Framework.
  • Equalities: Provision will support 24 Key Stage 3 and 4 pupils with Moderate Learning Difficulties and some with Autistic Spectrum Disorder, including 20 new local authority commissioned places.
  • Other: Design includes calm spaces, improved circulation and drop-off, and expanded parking to create a safe, accessible and low-stress environment.
  • Other: Enhanced provision intended to reduce reliance on costly external placements.

Who and where

  • 24 Key Stage 3 and 4 pupils with Moderate Learning Difficulties and some with Autistic Spectrum Disorder
  • 20 new local authority commissioned SEND places
  • Fernwood Academy Wollaton

Timeline

  • 24 February 2026: Updated SEND Capital Strategy approved by Executive Board
  • Phase 1 of the SEND Capital Strategy 2023-28: Priority needs identified that this project addresses

Plain English for the jargon

  • SEND: Special Educational Needs and Disabilities
  • MLD: Moderate Learning Difficulties
  • ASD: Autistic Spectrum Disorder
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Resolved to: (1) authorise the allocation and spend of carried forward High Needs Provisions Capital Allowance Grant funding or £830,000 from the 2024-2025 Grant Determination for capital expenditure purposes, for the additional design and construction costs of the Special Educational Needs and Disabilities (SEND) Unit at Fernwood Academy Wollaton, bringing the total cost of the project to £3,980,000; (2) delegate authority to the Corporate Director for Children’s and Education Services to spend the additional funding to address increased costs due to change in scope, extended programme, additional professional fees, and inflation; (3) delegate authority to the Corporate Director for Children’s and Education Services to procure and award the construction contract up to the value of £3,214,500, utilising the SCAPE Regional Construction Framework, in consultation with the Executive Member for Employment, Education and Skills; (4) delegate authority to the Corporate Director for Children’s and Education Services to modify the value of the contract with Perfect Circle JV Ltd using the SCAPE National Consultancy Framework (Lot 1: Built Environment Consultancy) to address professional fees, that form part of the original approval granted within the original Option G contract; (5) delegate authority to the Corporate Director for Children’s and Education Services to enter into any necessary licence agreements with Fernwood Academy to enter the site and carry out works. Reason for decisions: the proposal will expand specialist SEND provision at The Fernwood School by creating facilities for 24 Key Stage 3 and 4 pupils with Moderate Learning Difficulties and some with Autistic Spectrum Disorder (ASD), including 20 new places commissioned by the local authority. The enhancements are designed to better meet pupils’ needs and support inclusive provision within the community, in line with the Council’s SEND Sufficiency Strategy; an additional £830,000 is required to fund design improvements, including relocating the sensory garden, adding life-skills kitchens, and reconfiguring parking to support safe access and staff recruitment. The updated design introduces calm spaces, improved circulation and drop-off arrangements, and expanded parking, ensuring a safe, accessible and low-stress environment while reducing reliance on costly external placements. Other options considered: continue with the previous plans within the already approved funding. This option was rejected as this would provide a sub-optimal educational offer for children with SEND who the provision is designed to support; halt the project and charge all current expenditure to revenue. This option was rejected as it would create a significant revenue pressure and would not address the priority needs identified in Phase 1 of the SEND Capital Strategy 2023-28 or in the updated Strategy approved by Executive Board on 24 February 2026.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Appendix one – breakdown of additional costs

Additional Items Reason Cost Life skills kitchen GF School request £24,000 Life Skills kitchen FF School request £19,000 Addition for removing existing sensory School request £3,000 garden offsite Additional sensory garden equipment School request £24,000 Increased cost due to inflation Programme delay from original cost £125,000 submission therefore package costs outdated Cost for designing new parking areas Additional Scope requested £55,000 Budget cost for proposed new car Additional scope requested £372,226 parking areas Additional Prelims Works to be done in summer £70,000 so additional prelims and programme duration. Work previously not in scope Fee for service Agreement Scape Fees £26,000 Pre-construction charge Scape Fees £10,000 Internal Fees Major Projects Fees £20,000 Professional Services Fee Perfect Circle – Quantity Surveyor £20,000 and Contract Administration Client Contingency Contingency 61,774 £830,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Fernwood Academy Special Educational Needs and Disabilities (SEND) UnitReport 79 KB DownloadRead as text
PDF
Fernwood Academy Special Educational Needs and Disabilities (SEND) UnitReport 188 KB Download
PDF
Fernwood EIA FINAL 29.4.26Report 257 KB Download

At this meeting

Whole meeting

Who was there

9 of 21 attended
BB
Beth BrownOfficer, expected
MC
Michael CareyClerk, expected
SF
Stuart FairOfficer, expected
JH
Councillor Jay HayesCommittee Member, present
PU
Councillor Patience Uloma IfedioraCommittee Member, present
NJ
Nicki JenkinsOfficer, expected
HK
Councillor Helen KalsiCommittee Member, present
NK
Councillor Neghat KhanChair, present
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, present
SM
Councillor Sulcan MahmoodCommittee Member, present
NM
Neil McArthurOfficer, expected

All 21 on the meeting page

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies