Nottingham City Council
Executive Board, Tuesday 12 May 2026 at 2.00pm

Procurement of replacement core infrastructure servers

Approved Executive 1 paper

AI summaryExecutive Board approves up to £1,500,000 procurement of replacement core server hardware using the CCS framework, to be purchased in 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedUp to £1.5m via CCS framework RM6098 Lot 2
MoneyUp to £1,500,000Includes £0.260m contingency, from IT Investment Fund
What happens nextMini-competition and purchase in 2026/27Procure quickly per CCS supply chain warning
Who it affectsAll wardsCouncil-wide IT services and citizens

What was decided

Approved allocation of IT Investment Fund money for replacement core server hardware to be bought in 2026/27. Report 2.3

Delegated authority to the Chief Technology Officer and Head of Service (IT), with the Executive Member for Finance and Resources, to procure via CCS framework RM6098 Lot 2 up to £1,500,000 with a 5-year extended manufacturer warranty. Report 2.3, 6.3

Requested the capital budget be increased by £1.5m via a draw-down of funds. Report 5.2

Why

The core Hyper-V server estate was last replaced in January 2016 and is now significantly past its anticipated supportable service life, with hardware already 3 years beyond end of life. Report 2.1, P8

Central government requirements, such as the Public Sector Network Code of Connection, require the Council's systems to remain supportable to reduce risk to services for citizens. Report 2.2, 11.1

Using the CCS framework gives access to pre-assessed providers, helping ensure quality and security capability of bidders. Report 2.3

What happens next

Run a mini-competition through the CCS framework to secure competitive tension and best value. Report P27, 7.1

Complete the purchase at pace in Q1 of 2026 FY, as recommended by Crown Commercial Service to limit exposure to ongoing supply chain price volatility. Report P8

Seek Section 151 Officer sign-off and increase the capital budget by £1.5m via draw-down from the existing IT reserve investment fund. Report 5.2, 5.3

The money

  • £1,500,000 Estimated total value of the procurement decision Report 5.1, 2.3
  • £1.5m Capital budget increase requested via draw-down Report 5.2
  • £0.260m Contingency included within the £1.5m estimate Report 5.2
  • approximately £2m per year Annual revenue top-up to the IT reserve investment fund Report 5.2

Options considered

  • Rejected: Do nothing and continue running the current hardware. Would not fix increasing risk of failure, reduced supportability and reliability past intended lifespan Report 3.1
  • Rejected: Migrate the entire NCC IT server estate to a cloud-based service such as Microsoft Azure. Cannot be done wholesale or at pace because of legacy site-based applications that cannot be moved or would be cost-prohibitive Report 3.2

Implications

  • Risk: Continuing to run aged hardware raises risk of unplanned service interruption, cyberattack vulnerability and disproportionate demand on IT maintenance resource. Report P8
  • Financial: Spend is funded from an existing IT Investment Fund, but the Council is warned of global IT equipment price volatility linked to AI datacentre demand, DRAM and NAND shortages, and Middle East transport cost increases. Report 5.2, P8
  • Legal: Procurement must comply with the Public Contract Regulations 2015 or the Procurement Act 2023 and the Council's Contract Procedure Rules; use of the RM6098 framework is assessed as a legally compliant route. Report 6.2, 6.3, 6.7
  • Other: No Data Protection Impact Assessment, Equality Impact Assessment, Climate Impact Assessment, Crime and Disorder, or NHS Constitution implications are required. Report 8.1, P31, P33, P34

Who and where

  • All wards across Nottingham Report P43
  • Council IT Services and wider council staff relying on core systems Report P8, 2.1
  • Citizens receiving council services supported by the core server estate Report 2.2

Timeline

  • January 2016: Current core Hyper-V server hardware was last replaced Report 2.1
  • 10 October 2023: CCS framework RM6098 commenced under the Public Contract Regulations 2015 Report 6.3
  • 2026/27: Financial year in which the replacement hardware is to be purchased Report 2.3
  • Q1 of 2026 FY: Period recommended by Crown Commercial Service for procurement to limit exposure to supply chain volatility Report P8
  • 9 October 2027: End date of the RM6098 framework after optional extensions are used Report 6.3

Plain English for the jargon

  • Hyper-V: Microsoft's server virtualisation technology used to run the Council's core infrastructure.
  • CCS: Crown Commercial Service, a UK public sector procurement body.
  • RM6098 (TePAS 2): CCS framework for Technology Products and Associated Services, Lot 2 covers hardware.
  • PSN: Public Services Network, a UK government network with a Code of Connection that requires supportable systems.
  • DPIA / EIA / CIA: Data Protection, Equality and Climate Impact Assessments, all assessed as not required for this renewal.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Resolved to: (1) approve allocation of funding from the IT Investment Fund for the purchase of replacement core server hardware to be made in the 2026/27 financial year; (2) delegate authority to the Chief Technology Officer and Head of Service (IT), in consultation with the Executive Member for Finance and Resources, to enter into the procurement of replacement server hardware up to the value of £1,500,000 using established and approved CCS framework procurement processes, RM6098 Technology Products & Associated Services, Lot 2, for replacement core server hardware with a 5-year extended manufacturer warranty; (3) request the capital budget is increased by £1.5m accordingly via a draw-down of funds. Reason for decisions: the server hardware comprising the core Hyper-V estate infrastructure was last replaced in January 2016 and is now significantly past its anticipated supportable service life; requirements placed on the Council by central government require the organisation’s systems remain supportable to minimise risk to the services provided to citizens; use of the CCS framework allows the Council to access pre-assessed providers of products and services which helps ensure the quality, including security capability, of bidders. Other options considered: do nothing. This option was rejected as it would not correct the risk of running hardware past the end of its intended lifespan as well as the reduced supportability and reliability of that hardware; migrate the entire NCC IT server estate to a cloud-based infrastructure service. This option was rejected as it cannot be embraced wholesale or at pace.
Word for word from the decision Nottingham published for this meeting. Source: committee.nottinghamcity.gov.uk

Follow this further

Built from Nottingham's papers

What the report saysPro

Report to Executive Board

Reasons for recommendations

2.1The server hardware comprising the core Hyper-V estate infrastructure was last replaced in January 2016 and is now significantly past its anticipated supportable service life.

2.2Requirements placed on The Council by Central Government – for example, via the Public Sector Network (PSN) Code of Connection (see 11.1) – require the organisation’s systems to remain supportable in order to minimise risk to the services provided to citizens.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of replacement core infrastructure serversDecisions 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
BB
Beth BrownOfficer, expected
MC
Michael CareyClerk, expected
SF
Stuart FairOfficer, expected
JH
Councillor Jay HayesCommittee Member, present
PU
Councillor Patience Uloma IfedioraCommittee Member, present
NJ
Nicki JenkinsOfficer, expected
HK
Councillor Helen KalsiCommittee Member, present
NK
Councillor Neghat KhanChair, present
LL
Lucy LeeOfficer, expected
SL
Councillor Sam LuxCommittee Member, present
SM
Councillor Sulcan MahmoodCommittee Member, present
NM
Neil McArthurOfficer, expected

All 21 on the meeting page

On this subject at Nottingham

Search all
  1. Procurement of replacement core infrastructure serversThis decision
  2. Procurement of replacement Backup and Disaster Recovery infrastructureApproved

More from Nottingham Executive Board

All decisions
MeetingDecisionOutcome
22 Sep 2026 Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t... Approved Open
22 Sep 2026 Quarter 1 (Q1) Delivery Plan Performance ReportResolved to: (1) note the Q1 Delivery Plan Performance Update presented at Appendix A; (2) receive future updates of ... Noted Open
22 Sep 2026 Adult Social Care Strategy - Enabling Gloriously Ordinary LivesResolved to: (1) endorse, approve and adopt the Adult Social Care Strategy – Enabling Gloriously Ordinary lives 2026-... Approved Open
22 Sep 2026 HRA funded capital adaptations - Stairlifts, Step lifts, through-floor lifts and hoistsResolved to: (1) approve the request to procure and award a framework for HRA Specialist Equipment – mechanical; stai... Approved Open
22 Sep 2026 Recommissioning of Changing Futures Services in Nottingham - Key DecisionResolved to: (1) note that the Director of Public Health will vary the contract for the Changing Futures Main Deliver... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies