What was decided
The Executive Board approved the 2026/27 Transport Programme allocations set out in tables 1 to 2 of Appendix A, including a £4.5m Wigman Road corridor, £6m Access for All and £3m Mobility Hubs packages, and accepted £500,000 of match funding from the Walk Wheel and Cycle Trust. Report P8, P9, P11, 2.4
The Board approved the start of procurement activity for the programme and delegated authority to the Director of Planning and Transport, with the Corporate Director of Growth and City Development, to appoint suppliers and contractors following the procurement.
The Board delegated authority to those same officers to accept the grant funding from EMCCA and enter the grant conditions, in line with EMCCA assurance processes and in consultation with the Monitoring Officer and Section 151 Officer.
Why
The funding comes from the Government's Transport for City Regions fund, awarded to EMCCA in the 2025 Spending Review, and aims to drive growth through investment in integrated transport networks. Report 1.1, 2.1
The schemes support the Council Plan commitment to expand Nottingham's cycle networks, improve pedestrian routes, boost connectivity and increase shared transport, and align with the emerging Mayor's Transport Plan. Report 2.1
Schemes scored highly in EMCCA's Multi-Criteria Assessment Framework and were approved by the EMCCA Board on 8 June 2026. Report 1.3, 3.2
What happens next
Schemes will be taken through EMCCA's assurance process, with detailed proposals developed in consultation with the Executive Member and ward councillors before implementation. Report 1.4
Procurement will be carried out using in-house delivery, call-offs from council frameworks and approved external frameworks, in line with Contract Procedure Rules and the Procurement Act 2023. Report 7.1, 7.2, 7.3, 7.4
Revenue funding of £2.292m will be used for feasibility and development of future schemes, including Maid Marian Way, Broad Marsh, Nottingham Station Gateway and the final section of the Wigman Road cycleway, plus continuation of the active travel behaviour change programme. Report 2.10, 5.5
The money
- £13.5m Capital funding, total value of the decision Report 5.1
- £2.292m Revenue funding, total value of the decision Report 5.1, 5.5
- £4.5m Wigman Road active travel corridor and linked highway improvements (£1m in 2026/27 and £3.5m in 2027/28) Report P8
- £6m Access for All pedestrian improvements (£1.5m in 2026/27 and 2027/28 and £3m in 2028/29) Report P9
- £3m Mobility Hubs (£1m a year in 2026/27, 2027/28 and 2028/29) Report P11
- £0.5m Match funding from the Walk Wheel and Cycle Trust for Wigman Road Report 2.4
- £0.292m Revenue from EMCCA for active travel behaviour change programme in 2026/27 Report 2.10, 5.5
- £1m Revenue funding for feasibility and development work in 2027/28 and again in 2028/29 Report 2.9, 5.5
Options considered
- Rejected: Refuse the grant funding. Would prevent delivery of the additional transport improvements, could affect future bids to the TCR programme, would lose the Wigman Road scheme and the £0.5m Walk Wheel and Cycle Trust match funding, and could harm the Council's reputation as a national leader in local transport delivery. Report 3.1, 3.3
- Rejected: Vary the programme. Schemes were developed with EMCCA, scored highly in its Multi-Criteria Assessment Framework and were approved by the EMCCA Board in June; varying it could jeopardise delivery and breach funding terms and conditions. Report 3.2
Implications
- Financial: The budget was not included in the 2026/27 MTFP because funding had not been approved at that time; the budget will be created and added to new project codes across the planned spend profile. Report 5.4
- Financial: There are no expected revenue implications or match funding requirements, so the works will not create cost pressures for the Council, and future maintenance liabilities will be managed through consultation with the Neighbourhood Operations team. Report 5.3, P19
- Legal: The Corporate Procurement Team has advised on compliant procurement routes; Legal Services supports the preferred routes subject to continued engagement with the Procurement Team and compliance with the Procurement Act 2023. Report 6.1, 7.2
- Risk: Key risks include insufficient funding, future maintenance liabilities, lack of scheme support, and lack of internal delivery resource; mitigations include phased delivery, contingencies, consultation, and aligning programme timescales with resource availability. Report P18, P20
- Equalities: No new Equality Impact Assessment was undertaken because all schemes are covered by the assessment done for the initial April Executive Board funding tranche. Report 8.1
- Climate: No new Carbon Impact Assessment was undertaken because the assessment for the transport programme was done for the initial April Executive Board funding tranche. Report 8.2
- Other: The programme is expected to improve accessibility and community health through safer crossings, footpaths, cycle lanes and public transport routes, and to support physical regeneration, with a material difference in reductions in crime and disorder. Report 8.5, 8.6
Who and where
- All wards across the city Report P59
- Cyclists using National Cycle Network Route 6, including the new segregated route on Wigman Road to Harvey Hadden Sports Complex Report 2.3
- Pedestrians, including users of improved crossings near Oakfield school and along Access for All corridors Report 2.3, P9
- Users of shared transport and micromobility services, including e-bike and e-scooter hire at the new Mobility Hubs Report 2.7, P11
- Job seekers and workplaces supported by the active travel behaviour change programme delivered with the Walk Wheel and Cycle Trust and British Cycling Report 2.10
- Visitors to the Bennerley Viaduct foot and cycle link between Ilkeston and Awsworth Report 2.4
Timeline
- 9 March (year not specified, refers to EMCCA Board): EMCCA Board approved short-term priority investment themes, including £16.601m capital and £1m revenue to the City Council for 2026/27 Report 1.2
- 21 April (refers to Executive Board): Executive Board approved the 2026/27 transport programme
- 2 April 2026: EMCCA Transport and Digital Connectivity Committee considered the next tranche of scheme proposals Report 1.3, 11.1
- 8 June 2026: EMCCA Board approved the next tranche of scheme proposals Report 1.3, 11.3
- 2026/27: Wigman Road corridor receives £1m of its £4.5m allocation Report P8
- 2026/27 and 2027/28: Access for All receives £1.5m in each year Report P9
- 2028/29: Access for All receives £3m and Mobility Hubs receives its final £1m Report P9, P11
- 21 July 2026: Executive Board decision approving the additional funding and procurement
Plain English for the jargon
- EMCCA: East Midlands Combined County Authority, the body awarding the funding
- TCR: Transport for City Regions, the Government fund providing the money
- CRSTS: City Region Sustainable Transport Settlements, the former name of the programme now combined into TCR
- NCN 6: National Cycle Network Route 6, running along Beechdale Road, Hollington Road and Wigman Road
- Mobility Hub: A location bringing together different modes of shared and sustainable transport, typically near bus or tram stops
- FTZ: Future Transport Zone, the previous programme that introduced the first six mobility hubs in Nottingham
- TCF: Transforming Cities Fund, the earlier programme that delivered the Beechdale Road and Hollington Road segregated cycle corridor
- ATE: Active Travel England, government body whose funding for behaviour change has been subsumed into EMCCA's allocation