Oracle Managed Service Provider Contract – permission to issue tender
ApprovedExecutive1 paper
AI summaryNottingham City Council's Executive Board approved issuing a tender for an Oracle managed service contract worth up to £3.8m over six years, shared with Leicestershire County Council, to run from February 2027 to January 2033.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedOracle managed service contract, Feb 2027 to Jan 2033
MoneyUp to £3.8mOver 6 years, shared with Leicestershire
What happens nextTender to be issuedNew contract starts February 2027
Who it affectsFinance, payroll and HR systemAll wards across both councils
What was decided
Approved issuing of a tender for the Oracle managed service provider contract, up to £3.8m combined for Nottingham City Council and Leicestershire County Council, covering February 2027 to January 2033. Report 5.2
Delegated authority to the Corporate Director of Finance and Resources (Section 151 Officer), in consultation with the Leader and the Strategic Director of Legal and Governance, to enter into contracts and sign the contract.
Why
To ensure support for the core finance, payroll and HR system provides the best outcomes in terms of quality and value for money. Report 2.1
The current provider's performance has been inconsistent and the market has developed significantly since 2022, with new providers and services available. Report 3.1
The contract is complex and a longer-term arrangement until 2033 was an important consideration; only one framework provided for that length and no main suppliers were registered with it. Report 3.2
What happens next
An open tender process will be run in line with the Procurement Act 2023, to give the greatest market reach and align with the Oracle Fusion System (Softcat) contract. Report 7.2, 7.3
A contract clause will be included to reflect any LGR decisions, allowing the contract to be ended earlier than six years with no financial consequence. Report 5.7
Any additional services outside the current approved budget would need further approval and identification of additional funding before being agreed. Report 5.6
The money
£3.8m Maximum combined value of the tender over 6 years (NCC and Leicestershire) Report 5.1, 5.3
£2.1m Annual support contract total over 6 years at £0.350m per annum, funded equally by both partners Report P13
£1.7m Additional change request services total over 6 years at £0.283m per annum, determined by each partner Report P13
£0.633m Approximate annual cost over the 6 year term Report 5.3
£0.432m Total annual budget split across partners (£0.350m support and £0.082m change requests) Report 5.5
Options considered
Rejected: Not testing the market and extending the current contract. Market has developed significantly since 2022 and current provider's performance has been inconsistent Report 3.1
Rejected: Use of a procurement framework as an efficient route to market. Complex contract needing a longer-term arrangement to 2033; only one framework provided that length and no main suppliers were registered with it Report 3.2
Implications
Legal: Open tender must comply with the Procurement Act 2023 and the Council's best value duty; client department must consult Data Protection, HR, IT, Finance, Procurement and Legal. Report 6.2, 6.3, 6.4
Financial: Additional services outside the current approved budget would require further approval and identification of additional funding, to avoid budget pressure. Report 5.6
Risk: A detailed handover plan will be developed to manage transition between suppliers, and the new contract allows termination at any time with notice. Report P6
Equalities: A Data Protection Impact Assessment (DPIA) has been completed. Report 8.1
Other: A contract clause will reflect potential Local Government Reorganisation (LGR) decisions, allowing early termination without financial consequence. Report 5.7
Who and where
Nottingham City Council and Leicestershire County Council as joint partners sharing the Oracle system Report 5.2, 6.1
Finance, payroll and HR departments supported by the shared Oracle platform Report 2.1, 6.1
East Midlands Shared Services (EMSS), which manages the shared system Report 6.1, 7.2
All wards of Nottingham City Council Report P49
Timeline
18/06/2026: HR advice provided by HR MI and Systems Manager Report P37
24/06/2026: Finance advice provided by Strategic Director of Finance Strategy Report P19
24/06/2026: Procurement and IT advice provided Report P33
February 2027: New Oracle managed service contract starts Report 5.2
January 2033: New Oracle managed service contract ends Report 5.2
Plain English for the jargon
EMSS: East Midlands Shared Services, which manages the shared Oracle Cloud finance, payroll and HR system for the partner councils.
DPIA: Data Protection Impact Assessment, completed for this procurement.
MSP: Managed Service Provider, the external supplier supporting the Oracle system.
NCC and LCC: Nottingham City Council and Leicestershire County Council, the two partner authorities.
LGR: Referred to in the report in the context of potential Local Government Reorganisation decisions, but not defined in the papers supplied.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item49
Resolved
Resolved to: (1) approve the issuing of the tender for the Oracle managed service provider contract for up to £3.8m (combined for Nottingham City Council and Leicestershire County Council) from February 2027 to January 2033; (2) delegate authority to the Corporate Director of Finance and Resources (Section 151 Officer) in consultation with the Leader of the Council and the Strategic Director of Legal and Governance (Monitoring Officer) to enter into the contracts relating to the procurement activity outlined in Recommendation 1, and to sign and enter into the contract. Reason for decisions: to ensure that the support for the core finance, payroll, and HR system provides the best outcomes in terms of quality and value for money. Other options considered: not testing the market and extending the current contract. This option was rejected as the market has developed significantly since 2022, with new providers and services available. In addition, the current provider’s performance has been inconsistent so it would be remiss not to ensure that the councils are receiving the best services available, delivering value for money; use of a framework as an efficient method of investigating the market. This option was rejected as this is a complex contract and being able to offer a longer-term arrangement until 2033 was an important consideration. Only one framework provided for this length on engagement and none of the main suppliers were registered with it. This procurement route was unlikely to result in the quality outcomes required.
Word for word from the decision Nottingham published for this meeting.Source: committee.nottinghamcity.gov.uk
Subject: Oracle Managed Service Provider Contract – permission to issue tender
Executive Member(s): Councillor Ethan Radford, Executive Member for Finance and Resources Corporate Stuart Fair, Corporate Director of Finance and Resources (Section Director(s)/Director(s): 151 Officer) Summary of issues: To seek Executive Board approval to issue a tender for the contract for Oracle support on behalf of the East Midlands Shared Services Partnership (EMSS) for a 6 year period from February 2027 to January 2033.
The existing contract reaches the end of its current term in February 2027 and the EMSS Sponsors wish to test the market in terms of quality and value for money in procuring a new contract for Oracle support.
Recommendation(s): 1 To approve the issuing of the tender for the Oracle managed service provider contract for up to £3.8m (combined for Nottingham City Council and Leicestershire County Council) from February 2027 to January 2033.
2 To delegate authority to the Corporate Director of Finance and Resources (Section 151 Officer) in consultation with the Leader of the Council and the Strategic Director of Legal and Governance and Monitoring Officer to enter into the contracts relating to the procurement activity outlined in Recommendation 1, to sign and enter into the contract.
Relevant Council Plan Core Mission: 1. 2. 3. 1. A Renewed Council 2. Delivering for local 3. Leading Nottingham people forward • Fostering governance • Empowering safe • Revitalising the transparency and communities economy innovation • Providing safe, • Celebrating cultural • Financial stewardship affordable housing heritage • Adopting a ‘One • Healthy and safe • Improving Council’ approach residents infrastructure and • Enhancing education connectivity and skills • Championing sustainability If a Key Decision, state the reason: (a) Expenditure Income Savings of £750,000 or more taking account of the overall impact of the decision (b) Significant impact on communities living or working in two or more wards in the City Does this report contain any information that is exempt from publication? No 1. Background
1.1Nottingham City Council and Leicestershire County Council share an Oracle Cloud finance, payroll and HR system. The support for this system is provided by an external company. This contract began in 2023 with an initial contract term of three years. The contract provides support for issues and standard changes as well as additional services including new projects and developments for example implementing new modules or significant changes. The contract is managed by EMSS.
1.2This is a key contract ensuring the continued stability of the Council’s finance, payroll and HR system and ensuring the platform is available and working as expected.
1.3The partners had planned to re-tender this contract in 2025 but unfortunately neither partner had sufficient resource available to support this work. The current contract was extended in February 2026 for a period of up to two years. This renegotiation included a reduction of costs of £0.03m and improved contract terms.
1.4However the performance of the current provider has been inconsistent and partners are keen to investigate this market as it has grown since the last tender in 2022.
1.5As Nottingham City Council is the host authority for EMSS they hold all contracts on behalf of the partnership and provide Procurement support. Both partners have been working together to update the specification, invitation to tender and other tender documents including the contract.
1.6It is proposed to match the term of this contract with that for the Oracle system to bring them into line with each other. This would give a final end date of 31 January 2033.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Delivery – Tranche 3Resolved to: (1) approve the proposals included within the paper; (2) delegate authority to the Section 151 Officer t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.