RESOLVED – That authority be delegated to the Director of Economy, in consultation with the Cabinet Member for Economy and Enterprise, the Cabinet Member for Finance, the Director of Legal Services and the Director of Finance to procure, negotiate, re-negotiate award and execute a main contractor for the works.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
Update Cabinet on the development of the project to date To approve progress of Royton Town Hall and Library into the next phase of contractor procurement
Executive summary
Cabinet have previously approved £2.9m of funding to deliver the refurbishment of Royton Town Hall and Library. Planning permission was granted in April 2019, a cost plan has been produced and the opportunity to tender for the works has been published.
Recommendations
Cabinet is recommended to:
1. Delegate authority to the Cabinet Member for Economy and Enterprise in consultation with the Director of Economy, the Director of Legal Services, the Director of Finance (or their nominees) and the Cabinet Member for Finance to procure, negotiate, re-negotiate award and execute a main contractor for the works. Cabinet September 2019
Royton Town Hall and Library Update
Background
1.1Purpose built for the local board in 1880, Royton Town Hall is a municipal building constructed in a free style of architecture and includes a domed roof and clock tower topped by a copper cupola. The building has had accommodation added to the original building footprint over the years with extensions to the rear, which has materials and scale not sensitive to the original design.
1.2Royton library was built shortly after and is located adjacent to the Town Hall building, meaning the 2 buildings are ‘semi-detached’ in appearance. Together the buildings house;
• Library facilities • Office space for the District Team • Desk space for GMP / PCSO’s • A meeting room used by Councilors and Community groups
1.3The buildings are in a dilapidated state of internal finish and are only partially occupied. A feasibility exercise was carried out that sought to identify alternative uses that were commercially viable and brought the buildings back to full use.
1.4Relocating the library from next door, making better use of the “main” town hall building and using the area vacated by the library for commercial use appears to be the most logical opportunity for the future of the building. The commercial rental income from the vacated library would then offset some of the revenue / running costs of the refurbished Town Hall, housing the new library.
1.5This would best involve demolishing the later rear extension and redressing the rear elevation as well as remodeling / reconfiguring the external area immediately behind.
1.6In September 2018 Cabinet approved spend of £2.9 m and resolved to progress a scheme to remodel and refurbish Royton Town Hall and Library.
2 Current Position
2.1Following extensive consultation with the building users, the Elected Members, Royton Historical Society and other stakeholders a design solution was reached that best reflected the heritage value of the building. A planning application was submitted and in April 2019, Planning Committee granted Planning Permission for the scheme.
2.2Over the past 6 months more detailed design have been drawn up and a cost plan finalised meaning the Council will shortly be able to tender the works.
2.3As the cost of the works is over the threshold for Delegated Decisions the appointment of the contractor would normally be a Cabinet Decision, however,
2 given the timescales involved in obtaining Cabinet approval it would be prudent to delegate the decision to the appropriate Portfolio Holder and Officers.
3 Options/Alternatives
3.1Option 1 - Authorise Cabinet to Delegate authority to the Cabinet Member for Economy and Enterprise in consultation with the Director of Economy, the Director of Legal Services, the Director of Finance (or their nominees) and the Cabinet Member for Finance to procure, negotiate, re-negotiate award and execute a main contractor for the works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.