Resolved
RESOLVED – That the Cabinet would consider the commercially sensitive information contained at Item 18 of the agenda before making a decision .
Cabinet decided this item on Monday 27 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Cabinet would consider the commercially sensitive information contained at Item 18 of the agenda before making a decision .
To update Cabinet on the preferred option for implementing improvements to the heating system at the Blessed John Henry Newman College.
It is recommended that the contents of the report are noted only, with a further report setting out the full implications to be discussed under Part B of the meeting and the preferred option agreed.
1.1On 15 December 2010 a contract was agreed between Oldham Council and Oldham BSF Limited (PFI Contractor) to construct Blessed John Henry Newman College. Oldham BSF Limited (then owned by Balfour Beattie) completed construction in September 2012. In 2016 Balfour Beattie sold its majority shareholding in Oldham BSF Limited to an investment fund within the Amber Infrastructure Group. Since the school opened in 2012, the day to day operational management of the school has been undertaken by Engie Limited (the Facilities Management subcontractor). 1.2 Following practical completion of the School in 2012, several building defects became apparent including:
Issues with the heating system, Roof leaks in the atrium area, Inability to control temperatures in certain rooms due to a variety of factors.
1.3Heating System
1.3.1 Between 2015-2017, works have taken place to improve the heating system.
1.3.2 In late-2017, Oldham BSF Limited committed to undertake and finance remedial works to improve the heating system across the School.
1.3.3 In April 2019 the Council was informed that Oldham BSF Limited was no longer prepared to finance the works until the outcome of an adjudication with its subcontractors was known. The adjudication process is intended to establish liability for the rectification works. At this time, the adjudicator’s decision has been repeatedly delayed from summer 2019 to January 2020.
1.4School’s Position
1.4.1 The Head and Governors are extremely frustrated at the longevity of the problems and the inability of various parties to remedy. These matters have impacted on the smooth operation and educational provision of students in their care
1.5Deductions
1.5.1 The remedy of failing to rectify building defects and other performance shortfalls is by way of deducting monies from the monthly Unitary Charge that the Council pays to the Contractor. To date, the Council has levied deductions in respect of the building issues and other service performance shortfalls.
2 Current Position
2.1The Council has commissioned an external contractor to carry out a full investigation to assist with implementing improvements to the heating system.
2.3In December 2019 the Council set out its required expectations and actions of the PFI Contractor from January 2020.
2.4The Council can confirm works have been carried out over the Christmas period. It is recognised this is a short-term solution and the longer-term solution required is detailed in the Part B report.
3 Options/Alternatives
3.1There are a number of options available to the Council and these can be summarised as follows;
2 Option 1 - Continue to monitor the contract and levy deductions where applicable. Option 2 - The Council prepares for implementing improvements to the heating system using its own subcontractor; Option 3 - Issue a formal warning notice to the Contractor with a view to ultimately terminating the contract.
4 Preferred Option
4.1Option 2 is the preferred option.
5.1Members of the PFI board including Cabinet Member for Finance and Corporate Services, Chair (Deputy Chief Executive), Headteacher and school governors have been consulted.
6.1These are detailed in the report due to be considered under Part B of the meeting
7 Legal Services Comments
7.1These are detailed in the report due to be considered under Part B of the meeting.
8 Co-operative Agenda
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PFI: Blessed John Henry Newman College Heating ImprovementsReport | 175 KB | DownloadRead as text |
Follow Cabinet at Oldham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2026 | MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. | Approved | Open |
| 23 Mar 2026 | Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... | Noted | Open |
| 23 Mar 2026 | Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... | Approved | Open |
| 23 Mar 2026 | Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... | Decided | Open |
| 23 Mar 2026 | Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.