That the Cabinet notes the report. 2. That the Cabinet approves forecast profiled budget, being an adverse position of £13.594m, at Month 8 (30 th November 2024) and the forecast potential adverse position by year end of £20.390m, with mitigations in place to reduce expenditure, as detailed at Annex 1 to the report. 3. That the Cabinet notes the Medium-Term Financial Plan update for the period 2025/26 to 2029/30 included within Section 7, of Annex 1 to the report. 4. That the Cabinet approves the delegation of authority to the Deputy Chief Executive for Health and Care, in conjunction with the Director of Finance, to progress the procurement of an external strategic partner to support the work around transformation across three key areas. 5. that ... view the full minutes text for item 7.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
The report provides Cabinet with an update as at 30 November 2024 (Month 8) of the Council’s 2024/25 forecast revenue budget position and an update on the Medium Term Financial position (at Annex 1) alongside the financial position of the capital programme together with the revised capital programme 2024/25 to 2028/29 (at Annex 2).
Executive summary
Revenue Position
The forecast overspend position based on the Month 8 profiled budget is £13.594m which if not addressed would result in a year-end overspend of £20.390m (£19.912m at month 6).
This financial monitoring report follows on from the position reported at month 6 is a warning of the potential year end position if no further action is taken to reduce net expenditure. The management actions already implemented for 2024/25 have been factored into the Month 8 forecasts. Work continues across the organisation to address this position and it is anticipated that by the year end, the current outturn deficit position should reduce even further.
An update on the Month 8 2024/25 position is detailed within Annex 1.
As part of its budget setting process, the Council annually updates its Medium Term Financial Plan. Included within Section 7 of Annex 1 is an update on this plan with an indicative budget position for the period 2025/26 to 2029/30 in advance of the Provisional Local Government Finance Settlement expected later in December. Furthermore, to help support and shape transformational activity around drivers of costs across three key areas, it is proposed that the Council seeks external support through a strategic partner to help complete a sophisticated and detailed review that will underpin the comprehensive work needed to support sustainable service reductions and better outcomes over the medium to long term. It is proposed that Delegated Authority is granted to the Deputy Chief Executive for Health and Care, in conjunction with the Director of Finance to progress the procurement to support this work.
Capital Position
The report outlines the most up to date capital spending position for 2024/25 to 2028/29 for approved schemes. The revised capital programme budget for 2024/25 is £99.553m at the close of month 8 (£99.505m at month 6), a net increase of £0.047m. Actual expenditure to 30 November 2024 was £46.557m (46.77% of the forecast outturn).
Recommendations That Cabinet:
1. Notes the contents of the report. 2. Approves forecast profiled budget, being an adverse position of £13.594m at Month 8 and the forecast potential adverse position by year end of £20.390m, with mitigations in place to reduce expenditure as detailed at Annex 1. 3. Notes the Medium Term Financial Plan update for the period 2025/26 to 2029/30 included within Section 7 of Annex 1. 4. Approves the delegation of authority to the Deputy Chief Executive for Health and Care in conjunction with the Director of Finance to progress the procurement of a external strategic partner to support the work around transformation across three key areas. 5. Approves the revised capital programme for 2024/25 including the proposed virements and the forecast for the financial years to 2028/29 as at Month 8 as outlined in Annex 2.
2 Cabinet 16 December 2024
Revenue Monitor and Capital Investment Programme 2024/25 Month 8 – November 2024
Background
1.1The Authority’s 2024/25 revenue budget was approved by Council on 28 February 2024 at a sum of £299.818m to be met by government grants, Council Tax, Business Rates, and the use of General Earmarked Reserves. This report sets out the updated revenue financial position at Month 8.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.