Revenue Monitor and Capital Investment Programme 2025/26 - Month 10
ApprovedExecutive1 paper
AI summaryCabinet notes a £4.946m forecast revenue overspend for 2025/26 and approves a revised £70.818m capital programme. A one-off £10.056m capitalisation of interest on assets under construction has cut the variance from £15.199m.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedForecast adverse revenue position of £4.946m noted
Money£4.946m adverse revenue varianceDown from £15.199m after £10.056m capitalisation benefit
What happens nextContinue mitigations to year endFinal outturn to be reported separately
Who it affectsAdult Social Care, Children's Services, PlaceThree directorates with significant pressures
What was decided
Cabinet noted the forecast revenue adverse position of £4.946m at the end of Month 10 and the general revenue usable reserves position for 2025/26. Report P9, P3
Cabinet approved the revised 2025/26 Capital Programme of £70.818m, including the proposed virements, and noted the forecast through to 2029/30. Report P9, P7, 2.5
Why
Work with external treasury advisors concluded that capitalising interest costs for assets under construction would generate a £10.056m one-off benefit to the General Fund Balance, reducing the adverse variance from £15.199m to £4.946m. Report P4, 2.1, 2.3, 2.37
Three directorates continue to report significant pressures: Adult Social Care £8.928m, Children's Services £5.476m, and Place £4.576m. Report 2.3, 2.8, P68
Of the £26.584m approved budget savings, 80% are delivered or on track, 4% are off track but achievable, and 16% are at high risk of not being achieved. Report 3.2, P138, 6.2
What happens next
The Executive Team will continue enhanced spending controls and management actions to reduce the adverse variance by the financial year end, with the final position reported in the outturn report. Report 2.4, 4.1, 4.2, 5.6, 6.6
Capital receipts are to be kept under review through the monthly Capital Receipts meeting, with the 2025/26 financing requirement dependent on one large disposal expected by year end. Report 3.11, 3.13
The Council will pursue mitigations across directorates including placement reviews, recruitment controls, and property disposals to protect financial resilience. Report 2.17, 2.23, 2.31, 2.34
£4.576m Place directorate adverse variance Report 2.3, 2.8, P68
£26.584m Total approved 2025/26 budget reduction target Report 3.2, P138
£21.233m Savings delivered or on track (80%) Report 3.2, P138
£4.257m Savings at high risk of non-delivery (16%) Report 3.2, P138
£33.774m General reserves on 1 April 2025 Report 5.1
£18.865m General Fund Balance on 1 April 2025 Report 5.1
Options considered
Chosen: Agree the recommendations (consider forecasts and changes in the report). Preferred option as it notes the updated forecasts and approves the revised capital programme Report P23, 3.1, P24, 4.1
Rejected: Do not agree the recommendations and propose alternative forecasts Report P23, 3.1
Implications
Financial: Adverse revenue variance reduced from £15.199m to £4.946m through a one-off £10.056m capitalisation of interest on assets under construction. Report P4, 2.1, 2.3
Financial: The £15.002m variance is to be financed by £4.946m from general revenue usable reserves and £10.056m from the General Fund Balance. Report 5.5, P165
Financial: General revenue usable reserves are forecast to increase by 32% over the medium term under the approved MTFS strategy. Report 5.4
Financial: The capital programme assumes £4.714m of capital receipts in 2025/26, of which £1.366m has been received and a further £4.873m has been identified. Report 3.9, 3.10
Risk: 16% of approved budget savings are at high risk of non-delivery, with the Children's Investment Plan accounting for £2.202m of the £4.257m red-rated savings. Report 3.2, 3.5, P139
Risk: The 2025/26 capital receipts position depends on one large disposal still expected by year end; delay would require increased prudential borrowing or a reduced capital programme. Report 3.11, 3.13
Legal: No legal issues identified at this time. Report 7.1
Equalities: No equality, community cohesion or crime implications identified in the screening assessment. Report 9.1, P222, P228
Who and where
Adult Social Care service users and providers, with pressures in Community Health and Social Care, Learning Disability, and Mental Health services Report 2.11, 2.12, 2.13, 2.14, 2.15
Children in care and looked-after children, with £7.574m pressure on external placements above budget provision Report 2.21, 2.22
Place directorate services including waste, environment, property, parking, and town centre operations Report 2.26, 2.27, 2.28, 2.30
Residents and businesses accessing council housing, leisure, and regulatory services Report 2.30, P101
Council taxpayers and recipients of Government grants funding the £322.928m revenue budget Report 1.1
Council staff subject to recruitment controls and reduced agency spend Report 2.4, 2.34
Timeline
17 February 2025: Capital strategy approved at Cabinet Report 1.1
6 March 2025: Council approves 2025/26 revenue budget of £322.928m Report 1.1
1 April 2025: Opening general reserves of £33.774m and General Fund Balance of £18.865m Report 5.1
30 January 2026: Month 10 revenue position of £4.946m adverse variance reported Report P1, P3
31 January 2026: Capital expenditure of £43.927m recorded (62.03% of forecast outturn) Report P7, 2.5, P191
4 March 2026: Budget Council approves 2026/27 revenue budget including further growth for Adult Social Care and Children's Services Report 2.10
23 March 2026: Cabinet notes Month 10 report and approves revised Capital Programme Report P9
End of 2025/26: Financial year end with outturn to be reported separately; final position of £10.056m capitalisation benefit to be confirmed Report 2.4, 4.2
Plain English for the jargon
MTFS: Medium Term Financial Strategy, the council's multi-year budget planning document
HRA: Housing Revenue Account, the ringfenced account for council housing
Virement: Reallocation of budget between service areas within the same year
Capitalisation of interest: Treating borrowing interest costs as a capital cost on assets under construction rather than a revenue cost
EFS: Exceptional Financial Support, temporary government assistance for councils facing severe financial difficulties
SEND: Special Educational Needs and Disabilities
Earmarked reserves: Reserves set aside for specific identified purposes rather than general use
Section 114 notice: A formal declaration by a council's chief finance officer that expenditure is likely to exceed available resources
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item29
Resolved
That the Cabinet notes the contents of the report. Notes the forecast revenue position at the end of Month 10 at £4.946m as detailed at Annex 1, of the submitted report. 2. That the Cabinet notes the general revenue usable reserves position for 2025/26. 3. That the Cabinet approves the revised Capital Programme for 2025/26 including the proposed virements and notes the forecast for the financial years to 2029/30 as at the end of Month 10 as outlined in ... view the full minutes text for item 29.
Word for word from the decision Oldham published for this meeting.Source: committees.oldham.gov.uk
The report provides Cabinet with an update as of 30 January 2026 (Month 10) of the Council’s 2025/26 forecast revenue budget position alongside the financial position of the capital programme together with the revised capital programme 2025/26 to 2029/30 (at Annex 2).
Executive summary
Revenue Position
The forecast adverse position for 2025/26 at the end of Month 10 is estimated to be £4.946m (£15.199m at the end of Quarter 3).
The details within this revenue monitoring report for Month 10 follows on from the Quarter 3 report previously presented. A forecast adverse position based on the Month 10 revenue controllable budget is £4.946m which is a favourable movement of £10.253m from the position previously reported. As highlighted within the Quarter 3 report, the Council has explored opportunities in conjunction with its external treasury advisors to look at our current policy on capitalising interest costs for assets under construction. The outcome of this work has resulted in a forecast one-off benefit to the Council’s General Fund Balance of £10.056m for 2025/26.
Given, the in-year financial position of the Council, the level of reserves available, the approved budget reductions for 2026/27 and the budgetary gaps reported within the Council’s Medium Term Financial Strategy (MTFS), work continues across the organisation to reduce this forecast adverse variance by the financial year end. The recent publication of the Local Government Finance Settlement has provided some additional support to the Council as a result of the Fair Funding Review and the continuation of the Recovery Grant for another 3 years. Whilst this funding is welcomed, the Council must deliver within the financial resources allocated for 2026/27 onwards. The Council’s strategy to transfer much needed resources to reserves to increase the reserve position is a positive movement in ensuring the organisations financial resilience over the medium term. Further details of the current estimated position is included at Annex 1.
Capital Position
The report outlines the most up to date capital spending position for 2025/26 to 2029/30 for approved schemes. The revised Capital Programme budget for 2025/26 is £70.818m at the close of month 10 which incorporates the changes made from the annual review of the programme. Actual expenditure to 31 January 2026 was £43.927m (62.03% of the forecast outturn).
Recommendations That Cabinet:
1. Notes the contents of the report. 2. Notes the forecast revenue position at the end of Month 10 at £4.946m as detailed at Annex 1. 3. Notes the general revenue usable reserves position for 2025/26. 4. Approves the revised Capital Programme for 2025/26 including the proposed virements and notes the forecast for the financial years to 2029/30 as at the end of Month 10 as outlined in Annex 2.
2 Cabinet 23 March 2026
Revenue Monitor and Capital Investment Programme 2025/26 Month 10 – January 2026
Background
1.1The Authority’s 2025/26 revenue budget was approved by Council on 6 March 2025 at a sum of £322.928m to be met by Government grants, Council Tax and Business Rates. This report sets out the updated revenue financial position at the end of Month 10.
1.2As the year progresses the monthly and outturn projections will reflect the evolving position of the impact of management actions put in place to mitigate in-year pressures, new developments and changes in the profile of planned expenditure and any additional grants that are announced from the Government.
2 Current Position
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe...
Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.