AI summaryOxford City Council Cabinet approves a four-year tender framework for capital works on its 718 leasehold properties and delegates award decisions to an officer, subject to statutory leaseholder consultation.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFour-year framework for leasehold capital works
MoneyUp to £250 million HRA programmeApproved December 2024, including £177 million capital works
What happens nextTender process to beginSubject to Section 20 statutory consultation with leaseholders
Who it affects718 leasehold propertiesCouncil acts as freeholder and landlord
What was decided
Cabinet approved the start of a four-year framework tender for capital works on leasehold properties, subject to required statutory consultation. Report P5
Cabinet delegated authority to the Deputy Chief Executive for Communities and Citizens, in consultation with the Cabinet Member for Housing and Communities, to award framework places, call-off contracts, and finalise contractual arrangements. Report P5
Cabinet approved expenditure against the capital works budget under the HRA Asset Management Strategy approved in December 2024, and noted the statutory leaseholder consultations required. Report P5, P6
Why
The Council is the freeholder and landlord for 718 leasehold properties and must meet landlord obligations under the HRA Investment Programme of up to £250 million over 5 years. Report P3, P10, P15
Under Section 20 of the Landlord and Tenant Act 1985, the Council must consult leaseholders on qualifying works and long-term agreements, or it can only recover up to £250 per leaseholder for major works and £100 per year for service contracts. Report P9, P10, P17
Recovering contributions from leaseholders helps offset wider HRA costs and complies with the Council's fiduciary duty to its tenants. Report P16
What happens next
Commence the tender process for the four-year framework covering three lots: fencing and external works; external decoration and common parts; roofing, doors and window installation. Report P5, P7
Run the Section 20 Qualifying Long-Term Agreement consultation with leaseholders, followed by 30-day Notice of Intention and 30-day Notice of Estimates stages before appointing a contractor from the framework. Report P11
Award framework places, call-off contracts and finalise contractual arrangements via delegated authority, with call-offs using JCT 2024 contract options suited to each job. Report P5, P8
The money
£250 million HRA Investment Programme over 5 years approved December 2024 Report P15
£177 million HRA 5-year Capital Programme for planned works Report P15
£250 Section 20 cap per leaseholder for major works if consultation is not carried out Report P10, P17
£100 Section 20 annual cap per leaseholder for utilities or service/maintenance contracts if consultation is not carried out Report P10, P17
£750,000 Constitutional threshold above which Cabinet must authorise projects and contract awards Report P17
£9,033,368.00 Illustrative total cost of works 2026/27 to 2030/31 across leasehold blocks with Section 20 applied Report P14
£2,780,801.80 Illustrative leasehold recoverable contribution with Section 20 in place, 2026/27 to 2030/31 Report P14
£2,702,801.80 Illustrative amount written off to HRA without Section 20, 2026/27 to 2030/31 Report P14
Options considered
Chosen: Proceed with Section 20 consultation and framework tender to recover leaseholder contributions. Enables recovery of leaseholder share of capital works costs and offsets HRA spend Report P5, P14, P16
Rejected: Do not carry out Section 20 consultation before framework or works. Recovery per leaseholder would be capped at £250 for major works and £100 a year for service contracts, with the rest written off to the HRA Report P10, P14, P17
Implications
Financial: Subject to consultation succeeding, up to £2,780,801.80 could be recovered from leaseholders over 2026/27 to 2030/31; without it, £2,702,801.80 would be written off to the HRA. Report P14, P15
Legal: Procurement must comply with the Procurement Act 2023, the Procurement Regulations 2024, and the Council's Constitution; legal services are instructed to support. Report P17
Legal: Failure to follow the Service Charges (Consultation Requirements) (England) Regulations 2003 caps recoverable service charges and could expose the Council to First Tier Tribunal disputes. Report P10, P16, P17
Equalities: An Equality Impact Assessment has been carried out and has not identified any unlawfully disadvantaged groups. Report P19
Climate: Adoption is expected to contribute to good property maintenance, including insulation of properties. Report P19
Risk: Not mitigating rising HRA costs would conflict with the Corporate Plan's financial sustainability objectives. Report P18
Other: Standard Oxford City Council leases do not allow recovery of major works improvement costs except for items set out in the lease schedules, such as pre-paint joinery. Report P13
Who and where
Leaseholders in the Council's 718 leasehold properties, who will be statutorily consulted and may be recharged a share of capital works Report P10, P11
Social tenants in blocks containing leasehold flats, who share common parts where works are carried out Report P11
The Housing Revenue Account, which funds capital works and would absorb unrecovered costs if consultation is not carried out Report P14, P15
Prospective contractors, who will be able to bid for places on the framework and subsequent call-off contracts Report P5, P7
Timeline
December 2024: Earlier Cabinet approval of the HRA Investment Programme and Asset Management Strategy that funds these works Report P15
30 days (Stage 1): Section 20 Notice of Intention to carry out works to leaseholder blocks Report P11
30 days (Stage 2): Section 20 Notice of Estimates to leaseholders Report P11
2026/27 onwards: Indicative delivery of capital works and leaseholder income recovery Report P14
21 January 2026: Cabinet decision to approve tender and delegations Report P2
Plain English for the jargon
HRA: Housing Revenue Account, the ring-fenced account that funds council housing
Section 20 (S20): Consultation duty on landlords under the Landlord and Tenant Act 1985 before qualifying works or long-term agreements
QLTA: Qualifying Long-Term Agreement, a contract over 365 days that triggers Section 20 consultation
Framework: An agreement with selected contractors from which call-off contracts are awarded, usually via mini-competition
Call-off contract: A contract awarded under a framework for a specific piece of work
JCT 2024: Standard building contract forms published by the Joint Contracts Tribunal
EqIA: Equality Impact Assessment under the Equality Act 2010
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item132
Resolved
Cabinet resolved to: 1. Approve the commencement of a tender process for a four-year framework for capital works on leasehold properties, subject to the required statutory consultation with leaseholders as detailed in this report 2. Delegate authority to the Deputy Chief Executive for Communities and Citizens, in consultation with the Cabinet Member for Housing and Communities, to: a. award the placement of contractors on the framework and enter into the framework agreement with the successful contractors; and b. award call-off contracts procured from the framework to deliver capital works required on the leasehold properties throughout the duration of the framework c. finalise any and all contractual arrangements 3. To approve the expenditure against the budget for the capital works pursuant to the decision of the Cabinet in December 2024 in respect of the approval of the HRA Asset Management Strategy. 4. Note the statutory consultations required with leaseholders when carrying out works on leasehold properties as detailed in this report.
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
To: Cabinet Date: 21 January 2026 Report of: Director of Housing Title of Report: Leasehold: Tender process
Summary and recommendations Decision being To commence a tender process for a four year framework taken: for capital works on leasehold properties and delegate authority to award the placement of contractors on the framework and award call-off contracts to those contractors under the framework as and when works are required Key decision: Yes Cabinet Member: Councillor Linda Smith – Housing and Communities Corporate Priority: Good, affordable homes Policy Framework: HRA Asset Management Strategy 2025 – 2027
Recommendation(s): That Cabinet resolves to:
. 1. Approve the commencement of a tender process for a four year framework for capital works on leasehold properties, subject to the required statutory consultation with leaseholders as detailed in this report 2. Delegate authority to the Deputy Chief Executive for Communities and Citizens, in consultation with the Cabinet Member for Housing and Communities, to: a) award the placement of contractors on the framework and enter into the framework agreement with the successful contractors; and b) award call-off contracts procured from the framework to deliver capital works required on the leasehold properties throughout the duration of the framework c) finalise any and all contractual arrangements 3.To approve the expenditure against the budget for the capital works pursuant to the decision of the Cabinet in December 2024 in respect of the approval of the HRA Asset Management Strategy.
1173 4. Note the statutory consultations required with leaseholders when carrying out works on leasehold properties as detailed in this report.
Introduction and background: 1. This report seeks approval to commence the procurement of a framework for capital works on the Council’s housing stock, which includes leasehold properties. The Framework 2. The Council has developed a capital works programme to maintain the entire housing stock. It is proposed that the Council would procure a four-year framework for capital works on leasehold properties and call-off the required works via a mini-competition, as and when works are required subject to the statutory consultation with leaseholders. 3. The works shall be split into three lots: • Lot 1: Fencing, railings, gates, walls, car ports • Lot 2: External decoration, gutters, downpipes, fascias, soffits, bargeboards, balustrades/handrails, external steps, hardstanding, timber decking, external stores, garages, outbuildings, service cupboards, internal communal doors, rotary drying facilities, communal flooring, internal decorations, bin stores and external lighting • Lot 3: Roofing, doors and window installation
4. The call-off contracts include a number of different JCT 2024 contract options to provide flexibility depending on the works required, for example, Minor Works Building Contract (with or without design) for simple routine decoration and maintenance, or small basic construction, that are for one-off pieces of work, where the work does not require phasing or specialist trades, Intermediate Building Contract (with or without design) for use in bigger construction projects, involving all the recognised trades and skills of the industry, but without complex building service installations or other specialist work and where a collateral warranty is required, Measured Term Contract for ongoing periodic / regular decoration / repairs and cyclical maintenance, and Design and Build Contract for larger more complex projects where the contractor is designing the full works and carrying out the construction.
5. The Council will ensure robust contract management for the delivery of the works to the leasehold properties via a number of performance and operational meetings. Statutory Consultations 6. By law, landlords must consult leaseholders before carrying out qualifying work or entering into a long-term agreement for providing works or services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement of a GO strategic partnerCabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.