Treasury Management Mid-Year Review for April – September 2025

Noted Executive 3 papers

AI summaryCabinet noted Oxford City Council's Treasury Management performance for the six months to 30 September 2025. Investments of £66.182 million earned a forecast £4.924 million in net interest, £2.679 million above target.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted Treasury Management performance for April to September 2025
Money£2.679 million favourable varianceNet interest of £4.924 million against a £2.245 million target
What happens nextContinue within strategyStrategy fully adhered to so far, no changes planned
Who it affectsCouncil finances and servicesExternal debt of £288.526 million relates wholly to Housing

What was decided

Cabinet noted the performance of the Treasury Management function for the six months to 30 September 2025. Report P3

The Council recorded a favourable forecast variance of £2.679 million in net interest against the £2.245 million target. Report P9

All Treasury Management activity has been operated within the parameters set by the Treasury and Prudential indicators in the 2025/26 Strategy. Report P20

Why

The Council is required by regulations under the Local Government Act 2003 and by the CIPFA Code of Practice on Treasury Management to produce and consider this monitoring report. Report P24

Favourable factors included lower General Fund borrowing costs, an HRA borrowing cost transfer, lower minimum revenue provision, extra interest from companies, and higher investment interest as rates stayed higher for longer. Report P9

What happens next

The beneficial impact of treasury operations will be incorporated into the regular monitoring reports to Cabinet. Report P9

The £10 million National Homelessness Property Fund investment will be rolled into a follow-on fund to maintain service benefits and housing nomination rights, following a prior Cabinet decision. Report P19

The Council will continue to manage risk through counterparty lists, credit ratings and ongoing review of investment vehicles, with no significant changes to investment approach at this time. Report P21, P25

The money

  • £66.182 million Investments held at 30 September 2025 Report P9, P17
  • £4.924 million Net forecast interest for the year Report P9
  • £2.245 million Target interest for the year Report P9
  • £2.679 million Favourable forecast variance Report P9
  • £13.547 million Invested in 4 pooled investment funds Report P11
  • £3.546 million Held in property funds Report P17
  • £10 million Held in multi asset funds Report P17
  • £52.635 million Held in instant access cash facilities Report P17

Implications

  • Financial: Forecast capital loss of circa £0.850 million on the Lothbury fund, which is being wound up; £5.666 million of capital has already been returned. Report P14
  • Financial: The statutory override for pooled fund gains and losses runs until 31 March 2029 for relevant investments made before 1 April 2024, after which surpluses and deficits will hit the revenue position. Report P12
  • Risk: Uncertainty around future Bank of England interest rate movements and economic conditions creates risk for both investment returns and borrowing costs. Report P25
  • Equalities: The ethical investment policy and interest income supporting council services have a beneficial equalities impact. Report P26
  • Other: ESG criteria are used as an overlay, with security, liquidity and yield prioritised under the Treasury Management Code. Report P10

Who and where

  • Council tenants and the Housing Revenue Account, which bears all external debt interest Report P20
  • Oxford residents who receive council services funded in part by investment returns Report P26
  • Rough sleepers and people at risk of homelessness, served by the National Homelessness Property Funds Report P19
  • Treasury counterparties and the Council's investment providers Report P10, P22

Timeline

  • May 2025: Bank of England lowered interest rates from 4.5% to 4.25% Report P6
  • April to June 2025: Gross Domestic Product rose 0.3% before flatlining Report P6
  • August 2025: Bank of England lowered interest rates to 4% and held them there Report P6
  • 11 August 2025: Latest interest rate forecast issued, used without update Report P8
  • 30 September 2025: Investments valued at £66.182 million and portfolio composition recorded Report P9, P17
  • 21 January 2026: Cabinet meeting at which the mid year review was noted Report P2
  • 31 March 2029: Statutory override for pooled fund gains and losses ends for pre April 2024 investments Report P12

Plain English for the jargon

  • CIPFA: Chartered Institute of Public Finance and Accountancy, which sets the Treasury Management Code and Prudential Code
  • PWLB: Public Works Loan Board, a UK government lending facility for local authorities operated by the Debt Management Office
  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spend
  • MRP: Minimum Revenue Provision, the amount set aside each year to repay debt
  • Specified and non specified investments: Specified investments are sterling, short term, with eligible counterparties; non specified investments include property funds and those over 364 days
  • ESG: Environmental, Social and Governance criteria considered when choosing investment providers
  • Section 151 Officer: The council's statutory chief finance officer, who authorises the counterparty list
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item134

Resolved

Cabinet resolved to: Note the performance of the Treasury Management function for the six months to 30 th September 2025.
Word for word from the decision Oxford published for this meeting. Source: mycouncil.oxford.gov.uk

Follow this further

Built from Oxford's papers

What the report saysPro

Report to Cabinet

Agenda Item 15

To: Cabinet Date: 21st January 2025 Report of: Group Finance Director Title of Report: Treasury Management Mid-Year Review for April – September 2025

Summary and recommendations Purpose of report: To report on the performance of the Treasury Management function for the 6 months to 30 September 2025 Key decision: No Executive Board Councillor Ed Turner, (Deputy Leader) Finance and Member: Corporate Assets Corporate Priority: A well-run Council Policy Framework: Treasury Management Strategy Recommendation(s): That the Cabinet resolves to: 1. Note the performance of the Treasury Management function for the six months to 30th September 2025

Appendices Appendix 1 List of investments as 30th September 2025 Appendix 2 Risk Register

Introduction and Background 1. This report has been written in accordance with the requirements of the Chartered Institute of Public Finance and Accountancy’s (CIPFA) Code of Practice on Treasury and has been prepared in compliance with CIPFA’s Code of Practice on Treasury Management, covering the following: • An economic overview for the first part of the 2025/26 financial year • A review of the Council’s investment portfolio for 2025/26 • A review of the Council’s borrowing for 2025/26

. 1237 • A statement of compliance with Treasury and Prudential Limits for 2025/26 2. The Council operates a balanced budget, which broadly means cash raised during the year will meet its cash expenditure from a revenue perspective. Greater or lesser demand for cash generally is driven from capital activities. Part of the treasury management operations ensure this cash flow is adequately planned, with surplus monies being invested in suitable counterparties, providing adequate liquidity and security initially before considering optimising investment return. 3. The second main function of the treasury management service is the funding of the Council’s capital plans. These capital plans provide a guide to the borrowing need of the Council, essentially the longer term cash flow planning to ensure the Council can meet its capital spending operations. This management of longer term cash may involve arranging long or short term loans, or using longer term cash flow surpluses, and on occasion any debt previously drawn may be restructured to meet Council risk or cost objectives. 4. The Council held investments of £66.182 million (based on the investment value) as at 30th September 2025. Net forecast total interest to be earned during the year, including from loans to companies, and less minimum revenue provision and external borrowing, is £4.924 million against a target of £2.245 million, a favourable annual forecast variance of £2.679 million. Economic Overview 5. In the wider economy, the following factors formed the background to the overall economic position: • Gross Domestic Product picked up 0.3% in the period April to June 2025 but more recently flatlined with higher taxes for business restraining growth.; • CPI inflation finished September 2025 at 3.8%, Core inflation eased to 3.6% • The Bank of England lowered interest rates from 4.5% to 4.25% in May then to 4% in August and then maintained them at that level; • 10 year gilt yields fluctuated between 4.4% and 4.8% and ended September at 4.7%

Interest and Interest Rate Forecasts 6. The Council employs MUFG (formerly Link Group) as its treasury advisors and part of their service is to assist the Council to formulate a view on interest rates. Part of this advice includes a forecast of the Public Works Loan Board (PWLB) rates. The PWLB is a lending facility operated by the UK Debt Management Office (DMO) on behalf of HM Treasury and provides loans to local authorities. The PWLB rate forecasts below are based on the Certainty Rate (the standard rate minus 20 bps) which has been accessible to most authorities since 1st November 2012.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
List of InvestmentsAppendix 1 111 KB Download
PDF
Risk Register TM Mid Year 202526Appendix 2 104 KB Download
PDF
Treasury Management Mid-Year Review for April: September 2025Report 560 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Oxford

Search all
  1. Treasury Management Mid-Year Review for April – September 2025This decision
  2. Treasury Management StrategyApproved
  3. Treasury Management Strategy 2026/27Approved
  4. Treasury Management Strategy - 2010/11 OutturnNoted
  5. Treasury Management Strategy - Half Year ReviewNoted
  6. Treasury Management - 2011/12 Strategy Update and 2012/13 StrategyApproved

More from Oxford Cabinet

All decisions
MeetingDecisionOutcome
19 Aug 2026 Procurement of a GO strategic partnerCabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design a... Noted Open
19 Aug 2026 Controlled Parking Zones (CPZ) Review of existing zones and CIL spendCabinet resolved to: Approve the request to add the West Oxford Controlled Parking Zone (CPZ) to the approved list of... Approved Open
19 Aug 2026 Oxfordshire Infrastructure Strategy (OxIS)Cabinet resolved to: Endorse the Oxfordshire Infrastructure Strategy (OxIS) which has already been endorsed by the Ox... Decided Open
19 Aug 2026 Use of CIL funding to support infrastructure and public realm related to the Cowley Branch LineCabinet resolved to: Ringfence 30% of future CIL income arising from development within 1.5 km of either of the two C... Agreed Open
8 Jul 2026 Thames Valley Strategic Authority Proposal: Update and Implications for Oxford CityCabinet resolved to: 1. Note Oxfordshire County Council’s decision to veto the Thames Valley Foundation Strategic Aut... Agreed Open