Portsmouth City Council
Housing, Tuesday 24 September 2013 at 4.00pm

Kings Road Area Fire Doors

Approved Committee 2 papers

Housing approved this item on Tuesday 24 September 2013. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

(1) That approval be given to tender the works based on a budget estimate of £575,000 including a £60,000 allowance for contingencies / unforeseen works. (2) That following a full tender evaluation authority to enter into contract with the preferred bidder is delegated to the Head of Housing and Property Services. (3) That officers undertake further one-to-one discussions with the leaseholder residents regarding the financial implications of the scheme, giving regard to the best repayment options for them, and that the Cabinet Member for Housing is regularly updated on the progress of this consultation.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Housing

Purpose of report

1.1To seek permission to go out to tender and appoint a contractor to undertake installation of composite fire doors to 41No blocks of flats in the Kings Road area.

1.2The works are required to comply with the Regulatory Reform (Fire Safety Order) 2005 and to ensure the integrity of the buildings and reduce their on- going maintenance.

1.3If approved, it is anticipated that the works could commence by April 2014.

Recommendations

i That approval be given to tender the works based on a budget estimate of £575,000 including a £60,000 allowance for contingencies / unforeseen works.

ii That following a full tender evaluation authority to enter into contract with the preferred bidder is delegated to the Head of Housing and Property Services.

Background

3.1The blocks are all located in the St Thomas Ward of Portsmouth and are of traditional construction, built between 1952 and 1960.

3.2The 41No blocks contain 322No properties of which 213No are leaseholders.

1 www.portsmouth.gov.uk 3.3 Each block is served by a single staircase that the property entrance door opens directly onto. There is also resident storage sheds located in the stairwell that open directly into the stairwell.

3.4After undertaking of Fire Risk Assessments to these blocks it has been identified that all property entrance doors, shed doors and electrical cupboard doors that open directly into the stairwell need to be replaced with FD30s rated fire doors.

3.5Installing FD30s rated fire doors will maintain a fire break between the communal stairwell means of escape route and individual properties helping to reduce spread of fire and assist the PCC stay-put policy in the event of a fire breaking out.

3.6The type of door proposed is a composite fire door, this type of door should reduce future maintenance as they do not require cyclical decoration, offer better thermal performance and will be more secure than traditional timber doors.

3.7It is anticipated that the contract to install fire doors will commence during April 2014 with a contract period of 16 weeks. Once the fire doors have been installed, a contract for external decorations and associated repairs will commence by September 2014 to all the blocks and it is anticipated that this work will be completed by March 2015.

Reasons for recommendations

4.1The works are requirement of the Regulatory Reform (Fire Safety) Order 2005 following the undertaking of a Fire Risk Assessment. The Hampshire Fire & Rescue Service, who is the enforcing authority, have reviewed the Fire Risk Assessments undertaken and concluded that they are a comprehensive assessment of the risks and planned actions.

4.2The works will ensure the safety of residents and in the event of a fire contain it by preventing fire spread which will reduce the potential harm to residents and any potential damage to the building structure.

4.3The installation of the composite doors will assist the longer term maintenance of the blocks with reduced life cycle costs.

4.4The doors will afford residents improved security to their flats.

5. Options considered and rejected

5.1Due to the nature of the works there are few alternative options available. The fire safety measures are necessary as a result of a fire risk assessment under the Regulatory Reform (Fire Safety) Order 2005.

5.2An option considered and rejected was to upgrade the existing timber doors to make them FD30s. This was rejected as the original doors are of a style that is

2 www.portsmouth.gov.uk not capable of being upgraded. This has been validated independently by Fire Door Services, who are a specialist external consultant and a member of the Fire Protection Association, who undertook a door survey of the existing doors.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Kings Road Area Fire DoorsReport 179 KB DownloadRead as text
PDF
hous20130924r3appAReport 89 KB Download

At this meeting

Whole meeting

Who was there

3 of 3 attended
DS
Councillor Darren SandersChair, present
DH
Councillor David HorneOpposition spokesperson, present
LS
Councillor Luke StubbsOpposition spokesperson, present

On this subject at Portsmouth

Search all
  1. Kings Road Area Fire DoorsThis decision
  2. 19/00615/FUL - 46-50 Kingston Road and 2A New Road, Portsmouth, PO2 7RBAgreed
  3. A2047 Corridor Junction Treatments - Raised Tables (Fratton Road, Kingston Road and London Road)Approved
  4. 16/00086/LBC - Former Kingston Prison Milton Road Portsmouth PO3 6AS - Demolition of listed engineering/workshop building, part demolition and conversion of listed prison buildings (with associated internal and external alterations) to provDecided

More from Portsmouth Housing

All decisions
MeetingDecisionOutcome
20 Jul 2020 Development of Affordable Housing - Highgrove Lodge Site(1) The Cabinet Member for Housing approved Capital Expenditure of £ 5.1m, to deliver 6 new properties housing 24 adu... Approved Open
9 Mar 2020 Resources for Rough Sleepers in Portsmouth (information report)The contents of the information report were noted. (This is not subject to call-in provisions.) Noted Open
9 Mar 2020 Development of Affordable Homes - Huntsman Close, Havant(1) the Cabinet Member for Housing approved Capital Expenditure of £1.9m, to deliver 10 new affordable housing proper... Approved Open
9 Mar 2020 Council Housing Maintenance and Improvements and Housing IT Business Software 2020/21The Cabinet Member for Housing agreed: (1) That the area programmes and allocation of finance for the funding of the ... Agreed Open
27 Jan 2020 Temporary Accommodation Placement PolicyThe Cabinet Member for Housing (1) recognises the important role that temporary accommodation has in supporting peopl... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies