(1) That approval be given for a budget estimate of £385,000 including a £37,000 allowance for contingencies/unforeseen works. (2) That following a full tender evaluation authority to enter into contract with the preferred bidder is delegated to the Head of Housing and Property Services.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To seek permission to go out to tender and appoint a contractor to undertake planned maintenance works to 29-51 St James's Road and 53-75 St James Road.
1.2The works are required to ensure the integrity of the buildings and reduce the on-going maintenance.
1.3If approved, it is anticipated that the works could commence by January 2014.
Recommendations
i That approval be given for a budget estimate of £385,000 including a £37,000 allowance for contingencies / unforeseen works.
ii That following a full tender evaluation authority to enter into contract with the preferred bidder is delegated to the Head of Housing and Property Services.
Background
3.1The blocks 29-51 St James's Road and 53-75 St James Road are located within the St. Thomas Ward. Both blocks were built in 1966 using concrete ring beam construction method.
3.2The blocks 29-51 St James's Road and 53-75 St James's Road contains 2No three bedroom flats, 4No two bedroom flats and 18No three bedroom maisonettes.
1 www.portsmouth.gov.uk 3.3 There are 3No Leaseholders within 29-51 St James's Road and 1No Leaseholder within 53-75 St James Road.
3.4The key demand from both blocks is the poor decorative condition of the metal stairwell screens that are also indicating corrosion as well as contributing to issues with the communal flooring that becomes hazardous when wet due to the semi-open design. In addition the blocks require redecoration and spalling areas of concrete on the ring beams require repair.
3.5The proposed works consist of complete replacement of the stairwell screens in order to fully enclose the communal stairwell, undertaking concrete repairs and other associated structural works across the blocks, fire safety upgrades, external and communal decoration and other associated repairs.
3.6A Fire Risk Assessment undertaken to these blocks has highlighted planned fire upgrade works that will be incorporated into the scheme including installing FD30s rated fire doors to all property entrance doors and emergency lighting.
3.7It is anticipated that the contract will commence during January 2014 with a contract period of 14 weeks.
Reasons for recommendations
4.1The works will ensure the structural integrity of the blocks and help protect it against future deterioration, thus maintaining a letable asset for PCC.
4.2The project will improve the visual appearance of the blocks, helping to improve the external environment for both residents and neighbouring properties.
4.3The works will improve the safety of the block by reducing the likelihood of a resident slipping or falling and thus minimising the potential for a claim to be made against PCC.
4.4It is considered that once the proposed works are undertaken the blocks will continue to provide a good living environment for the residents.
4.5The scheme will maintain the security of the internal communal areas.
5. Options considered and rejected
5.1Due to the nature of the defects present to the building there are few alternative options available. The structural works are essential to ensure to the integrity of the building and fire safety measures are necessary due as a result of a Fire Risk Assessment undertaken to comply with the Regulatory Reform (Fire Safety) Order 2005.
5.2An option considered and rejected was to remove the existing stairwell screens and not to replace them. Whilst this would be a cheaper option it was rejected as additional works would be required to protect the building structure from the
2 www.portsmouth.gov.uk weather and ensure that the floor surfaces were slip resistant when fully exposed to the elements, this would lead to increased on-going maintenance costs. The communal areas would also become unsecured which would be considered unacceptable by residents.
6. Duty to involve
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary Accommodation Placement PolicyThe Cabinet Member for Housing (1) recognises the important role that temporary accommodation has in supporting peopl...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.