Housing, Tuesday 24 September 2013 at 4.00pm

Marshfield House - Cladding and external repair

Approved Committee 2 papers

Housing approved this item on Tuesday 24 September 2013. Below is the council's own wording, with the papers it was decided on.

Item27

Resolved

(1) That approval be given to tender the works based on a budget estimate of £340,000 including a £25,000 allowance for contingencies/unforeseen works. (2) That following a full tender evaluation authority to enter into contract with the preferred bidder is delegated to the Head of Housing and Property Services.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Housing

Purpose of report

1.1To seek permission to go out to tender and appoint a contractor to undertake planned maintenance works to 1-24 Marshfield House.

1.2The works are required to ensure the integrity of the building and reduce the on- going maintenance required.

1.3If approved, it is anticipated that the works could commence by March 2014.

Recommendations

i That approval be given to tender the works based on a budget estimate of £340,000 including a £25,000 allowance for contingencies / unforeseen works.

ii That following a full tender evaluation authority to enter into contract with the preferred bidder is delegated to the Head of Housing and Property Services.

Background

3.1The block 1-24 Marshfield House is located in the Drayton & Farlington Ward and is of crosswall construction, built in 1965. Within the boundary of the site are 2No garage blocks that are included within the scheme.

3.2There is 24No properties contained in the block with 8No of these being leasehold properties.

1 www.portsmouth.gov.uk 3.3 A number of elements of the building fabric have either reached the end of their serviceable life and now require replacement in addition to other elements that now require routine remedial work.

3.4The main areas of work will include insulated cladding to replace the existing tile hanging, external and communal decoration, installation of emergency lighting, replacement fencing, new windows to the communal stairwells, structural repairs, re-roofing of garage blocks and other associated repairs.

3.5It is anticipated that the contract will commence by March 2014 with a contract period of 16 weeks.

Reasons for recommendations

4.1The works will ensure the integrity of the building fabric to the block and help protect against future deterioration, thus maintaining a lettable asset for PCC.

4.2The project will improve the visual appearance of the block, helping to improve the external environment for both residents of the block and neighbouring properties.

4.3It is considered that once the proposed works are undertaken the blocks will continue to provide a good living environment for the residents.

5. Options considered and rejected

5.1An option considered and rejected was to repair the areas of defective tile hanging rather than replacing them with insulated cladding. This option was rejected as surveys indicated that the battens that hold the tile hanging have rotted in many places meaning complete replacement would be required

5.2Repairing the tile hung areas would be cheaper in the short term however there would be an on-going demand for repairs to these areas that when combined with the high cost of scaffold access in the long term would offset the initial saving.

5.3Standard products are being used for general repair works to maintain the block and therefore it is not considered that there are alternative options for these items.

6. Duty to involve

6.1A planning application has been submitted and approved during which all residents and leaseholders were notified.

6.2Face to face consultation has taken place with all leaseholders of the block with a Notice of Intent being issued to them in April 2013. The feedback from leaseholders is that they are generally satisfied with the repayment options available to them and the proposed work.

2 www.portsmouth.gov.uk 6.3 When tenders are returned section 20 notices will be sent to all leaseholders outlining their required contributions when the work is completed. The earliest that any leaseholder is likely to receive a bill for the completed work is September 2015.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Marshfield House: Cladding and external repairReport 171 KB DownloadRead as text
PDF
hous20130924r5appAReport 89 KB Download

At this meeting

Whole meeting
25Kings Road Area Fire DoorsApproved 26St James' Road ImprovementsApproved
27Marshfield House - Cladding and external repairThis decision

Who was there

3 of 3 attended
DS
Councillor Darren SandersChair, present
DH
Councillor David HorneOpposition spokesperson, present
LS
Councillor Luke StubbsOpposition spokesperson, present

More from Portsmouth Housing

All decisions
MeetingDecisionOutcome
20 Jul 2020 Development of Affordable Housing - Highgrove Lodge Site(1) The Cabinet Member for Housing approved Capital Expenditure of £ 5.1m, to deliver 6 new properties housing 24 adu... Approved Open
9 Mar 2020 Resources for Rough Sleepers in Portsmouth (information report)The contents of the information report were noted. (This is not subject to call-in provisions.) Noted Open
9 Mar 2020 Development of Affordable Homes - Huntsman Close, Havant(1) the Cabinet Member for Housing approved Capital Expenditure of £1.9m, to deliver 10 new affordable housing proper... Approved Open
9 Mar 2020 Council Housing Maintenance and Improvements and Housing IT Business Software 2020/21The Cabinet Member for Housing agreed: (1) That the area programmes and allocation of finance for the funding of the ... Agreed Open
27 Jan 2020 Temporary Accommodation Placement PolicyThe Cabinet Member for Housing (1) recognises the important role that temporary accommodation has in supporting peopl... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies