Admiral Blocks Refurbishment

Approved Committee 1 paper

Housing approved this item on Tuesday 14 July 2015. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

(1) Approval was given to tender the works based on a budget estimate of £1.65 million, inclusive of fees. (2) That following a full tender evaluation authority to enter into contract with the preferred bidder be delegated to the Director of Property and Housing.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Housing

Purpose of report

1.1To seek permission to go out to tender and appoint a contractor to undertake planned maintenance works to 7no blocks of flats in the Portsea area of Portsmouth.

1.2The works are required to ensure the integrity of the buildings, reduce their on- going maintenance and improve the living environment for residents.

1.3If approved, it is anticipated that the works could commence by January 2016.

Recommendations

i That approval be given to tender the works based on a budget estimate of £1.65 Million, inclusive of fees.

ii That following a full tender evaluation authority to enter into contract with the preferred bidder is delegated to the Director of Property and Housing.

Background

3.1All the properties are located within the Charles Dickens Ward and were built between 1955 and 1958.

3.2The site contains a total of 108 properties within seven blocks of flats which are a mixture of one, two and three bed flats and maisonettes.

3.3There are nine leaseholders that are located within four of the seven blocks of flats. The remaining three blocks of flats are fully owned by PCC. There are 99No properties that are let to PCC residents. 1 www.portsmouth.gov.uk 3.4 All of the blocks have been evaluated, a full building survey has been undertaken, defects identified and relevant proposals put forward to address the defects.

3.5The main area of work relates to the roof covering of the blocks. From inspection the clout nails present have corroded and there are numerous instances where tiles have slipped and require repair. The consequence is that regular roofing repairs are required to all the blocks, particularly during the winter months; it is therefore proposed to replace the existing roof covering.

3.6In conjunction with the roof covering being replaced the opportunity is being taken to install Photo Voltaic (PV) panels to the roofs.

3.7A Fire Risk Assessment has been undertaken to all blocks and a number of recommended planned actions have been made.

It is proposed to install LED emergency lighting to the common parts of all blocks along escape route and install new composite fire doors where necessary to relevant properties at some of the blocks.

3.8In addition to the above general repairs to the external and communal areas will be undertaken along with decorations to these areas as identified from the survey.

Reasons for recommendations

4.1The works will ensure the integrity of the building fabric, help protect against future deterioration and reduce current levels of repair expenditure.

4.2In particular the replacement of the roof covering will eliminate the on-going costly repairs for this type of work as well as to remove the potential risk of damage to the resident's properties or safety risk from falling tiles.

4.3The installation of Photo Voltaic (PV) panels will provide an income stream to the Housing Revenue Account (HRA) that is particularly cost effective as it will be undertaken in conjunction with the roof replacement whilst the scaffold access to the roof is already available. The payback period for the investment of undertaking the PV installation will be less than 4 years.

4.4The project will upgrade the aesthetic visual appearance of the blocks and together with the increased lighting levels in the stairwells will improve the communal environment.

4.5The scheme will provide a better living environment for residents and maintain good quality accommodation for families in the city.

2 www.portsmouth.gov.uk 5. Options considered and rejected

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Admiral Blocks RefurbishmentReport 163 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 4 attended
SW
Councillor Steve WemyssCabinet Member, present
SP
Councillor Stuart PotterOpposition spokesperson, present
YC
Councillor Yahiya ChowdhuryOpposition spokesperson, present
MW
Councillor Matthew WinningtonOpposition spokesperson, present

More from Portsmouth Housing

All decisions
MeetingDecisionOutcome
20 Jul 2020 Development of Affordable Housing - Highgrove Lodge Site(1) The Cabinet Member for Housing approved Capital Expenditure of £ 5.1m, to deliver 6 new properties housing 24 adu... Approved Open
9 Mar 2020 Resources for Rough Sleepers in Portsmouth (information report)The contents of the information report were noted. (This is not subject to call-in provisions.) Noted Open
9 Mar 2020 Development of Affordable Homes - Huntsman Close, Havant(1) the Cabinet Member for Housing approved Capital Expenditure of £1.9m, to deliver 10 new affordable housing proper... Approved Open
9 Mar 2020 Council Housing Maintenance and Improvements and Housing IT Business Software 2020/21The Cabinet Member for Housing agreed: (1) That the area programmes and allocation of finance for the funding of the ... Agreed Open
27 Jan 2020 Temporary Accommodation Placement PolicyThe Cabinet Member for Housing (1) recognises the important role that temporary accommodation has in supporting peopl... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies