RESOLVED THAT COMMITTEE 1. Approve the 2020/21 revised estimate of £61,870 for this committee’s capital programme as set out in Annex 1 of the report, and 2. Approve the move of £26,420 capital budget from 2020/21 to 2021/22 for the Introduction of Planning Portal Link to the Planning Application System and Planning System Update scheme.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO PLANNING AND DEVELOPMENT COMMITTEE
meeting date: 7 JANUARY 2021 title: REVISED CAPITAL PROGRAMME 2020/21 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To approve the 2020/21 revised estimate for this Committee’s capital programme.
1.2Relevance to the Council’s ambitions and priorities:
Community Objectives – none identified.
Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs.
Other Considerations – none identified.
2 2020/21 CAPITAL PROGRAMME BACKGROUND
2.1Two capital schemes for this Committee’s 2020/21 original estimate budget, totalling £40,920, were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2020 and March 2020 respectively. The two schemes approved were 2019/20 schemes that had been moved from the 2019/20 capital programme to the 2020/21 capital programme.
2.2In addition to the original estimate budget above, one 2019/20 capital scheme was not completed by 31 March 2020 and had unspent budget available at that date. The total unspent budget of £48,680 on this scheme, known as slippage, was moved into the 2020/21 capital programme budget, after a slippage request from the budget holder was agreed by the Director of Resources. Formal approval for this slippage request is now being sought from members as the request is incorporated into the proposed revised estimate capital programme that members are being asked to approve in this report.
2.3As a result of the above, the total approved budget for this Committee’s capital programme of three schemes was £89,600. This is shown at Annex 1.
3 REVISING THE 2020/21 CAPITAL PROGRAMME
3.1We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect their progress and estimated full year expenditure. Following this review, the revised estimate for two schemes is set at £61,870, a reduction of £27,730 from the total approved budget. The reasons for this are:
Introduction of Planning Portal Link to the Planning Application System and Planning System Update (-£26,420): The planning portal link has been installed and configured previously. The planning system update element of the scheme was previously put on-hold awaiting the outcome of the planned wider process review in the Planning section. That planned wider process review has not taken place yet because of Covid-19 issues since Spring 2020. It is hoped that the wider process review can commence in 2021, Covid-19 permitting. Given this, the planning system update element of this scheme will not be undertaken in 2020/21.
$qe2qu0do It is recommended that the 2020/21 revised estimate for the scheme is reduced to nil and the £26,420 scheme budget is moved to the 2021/22 financial year.
Replacement of Plotter/Copier in the Planning Section (-£1,310): The scheme is now complete, as the plotter/copier has been delivered and paid for. The final cost was £13,190, which is £1,310 lower than the original estimate for the scheme.
3.2Annex 1 shows the full capital programme by scheme, including the budget and expenditure to date. The summary position is shown below.
Actual Expenditure including Total commitments Original Budget Slippage Approved Revised Budget as at end of Estimate Moved from from Budget Estimate Moved to November 2020/21 2019/20 2019/20 2020/21 2020/21 2021/22 2020 £ £ £ £ £ £ £ 0 40,920 48,680 89,600 61,870 26,420 61,862
3.3At the end of November 2020 both of the schemes in the revised capital programme for this Committee had been completed within the revised estimate budget set.
4 RISK ASSESSMENT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.