Resolved
RESOLVED THAT COMMITTEE: Approve the revenue Proposed Original Estimate for 2026/27 and to submit this to the Special Policy and Finance Committee.
AI summaryRibble Valley's Community Services Committee approved a revised 2025/26 capital programme of £1,830,610, a £7,183,580 reduction, moving £7,177,340 of budget on nine schemes to 2026/27.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED THAT COMMITTEE: Approve the revenue Proposed Original Estimate for 2026/27 and to submit this to the Special Policy and Finance Committee.
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO COMMUNITY SERVICES COMMITTEE
meeting date: 6 JANUARY 2026 title: REVISED CAPITAL PROGRAMME 2025/26 submitted by: DIRECTOR OF RESOURCES principal author: JEAN WADDINGTON
1 PURPOSE 1.1 To approve the 2025/26 revised estimate for this Committee’s capital programme. 1.2 Relevance to the Council’s ambitions and priorities: • Community Objectives – none identified. • Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs. • Other Considerations – none identified. 2 CAPITAL PROGRAMME 2025/26 BACKGROUND 2.1 There were 15 capital schemes that were originally approved for this committee totalling £8,666,880 (including budget and schemes moved from 2024/25). These were approved by the Policy and Finance Committee and Full Council at their meetings in February 2025 and March 2025 respectively. 2.2 At the 2024/25 year-end, it was identified that there were 9 schemes that had not been completed. The balance of budget for these schemes was £245,470 and the transfer of this budget to the 2025/26 financial year is known as slippage. There had also been early expenditure incurred on 2 schemes from the 2025/26 capital programme of £7,570 and these costs were carried forward as ‘negative’ slippage. Total slippage of £237,900 was approved by this committee at the meeting held on 27 May 2025. 2.3 During 2025/26 additional approvals of £109,410 on 1 existing and 2 new schemes were confirmed by this Committee at their meetings in September and November 2025. 2.4 As a result of the above, the total approved budget for this Committee’s capital programme of 23 schemes is £9,014,190. This is provided in detail at Annex 1. 3 REVISING THE 2025/26 CAPITAL PROGRAMME 3.1 We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect progress on the schemes and estimated full year expenditure. Following this review, the proposed revised 2025/26 capital programme for this committee is £1,830,610 for 20 schemes. 3.2 The reduction of £7,183,580 in the revised capital programme can be accounted for as follows:
Element £
Current Total Approved Budget 9,014,190
Less Budget Moved to 2026/27 -7,177,340
Adjustments Needed Due to Scheme Savings/Changes/Increased Costs -6,240
Resulting Proposed Revised Estimate 1,830,610
Page 1 of 8 3.3 Detailed below is a summary of the position on the schemes that are recommended for moving to the 2026/27 financial year.
Budget Being Latest Position Resulting in Transfer of Moved to Scheme Scheme to 2026/27 2026/27 £
The contract for this scheme is in place and work CASKP: Castle will commence in 2025/26. Due to the length of Keep Lime the project and the dependence on fine weather 399,140 Repointing Works for the work, the scheme is not expected to and Repairs complete until 2026/27. Budget has been moved forward to accommodate these circumstances.
The full programme of works planned for 2025/26 CPCRF: Car Parks is unlikely to be completed by the end of the Resurfacing Rolling financial year and therefore an amount of budget 50,000 Programme will be moved to 2026/27 to allow works to completed then.
This scheme is intrinsically linked to the Council’s FGEPP: Fence and plans to work with the Football Federation to Gates Around install 3G pitches at three new locations, and is 53,770 Edisford Playing therefore on-hold until this scheme is finalised. A Pitches separate report will be presented at this meeting on the Football Pitches.
A large part of this weather dependent work was FPDRN: Drainage of completed in 2025/26. The remainder of the Council Owned 11,550 budget is being carried forward for use in Football Pitches Spring/Summer 2026/27.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revised Capital Programme 2025/26Report | 215 KB | DownloadRead as text |
Follow Community Services at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Aug 2026 | Ribblesdale PoolIt was agreed that the solar panel element should be removed from the current contract and considered separately. Thi... | Agreed | Open |
| 25 Aug 2026 | Clitheroe WellsRESOLVED THAT COMMITTEE: Authorise to the Director of Community Services to continue to take the required steps towar... | Decided | Open |
| 25 Aug 2026 | Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co... | Approved | Open |
| 25 Aug 2026 | Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 3 of Part 1 of Schedule 12A of t... | Decided | Open |
| 26 May 2026 | Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approved the slippage of £1,000,940 as set out at paragraph 3.6 of the report. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.