Capital Outturn 2020/21 and Capital Programme Update 2021/22

Approved Committee 1 paper

Health and Housing approved this item on Thursday 10 June 2021. Below is the council's own wording, with the papers it was decided on.

Item58

Resolved

RESOLVED THAT COMMITTEE: Approved the slippage of the following budgets into the 2021/22 capital programme: • Disabled Facilities Grants, £567,500. • Landlord/Tenant Grants, £15,900. • Clitheroe Affordable Housing Scheme, £11,770.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Health and Housing

DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO HEALTH AND HOUSING COMMITTEE

meeting date: 10 JUNE 2021 title: CAPITAL OUTTURN 2020/21 AND CAPITAL PROGRAMME 2021/22 UPDATE submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK

1 PURPOSE

1.1To report the 2020/21 capital programme outturn for this Committee and to seek member approval for the slippage of some capital scheme budgets from the 2020/21 financial year to the 2021/22 financial year.

1.2Relevance to the Council’s ambitions and priorities:  Community Objectives – none identified.  Corporate Priorities - to continue to be a well-managed council providing efficient services based on identified customer need.  Other Considerations – none identified.

2 2020/21 CAPITAL PROGRAMME BACKGROUND

2.1Three capital schemes for this Committee’s original estimate budget, totalling £513,940, were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2020 and March 2020 respectively. This included new annual budgets for two on-going grants schemes and also budget for two 2019/20 schemes that had been moved from the 2019/20 capital programme to the 2020/21 capital programme.

2.2In addition to the original estimate budget above, the following budget changes were made:

 Five capital schemes were not completed by 31 March 2020 and had unspent budget available at that date. The total unspent budget of £658,890 on those schemes, known as slippage, was moved into the 2020/21 capital programme budget, after slippage requests from the budget holders were agreed by the Director of Resources.

 Following approval of the original estimate budget for this Committee, the Disabled Facilities Grants (DFGs) funding for 2020/21 from Central Government was confirmed as £346,368. The DFGs scheme budget was initially set at £347,000 on the basis that this would be changed to reflect the confirmed DFGs funding that was received. Therefore, the DFGs 2020/21 budget was decreased by £630 to £346,370.

 In June 2020, Onward Homes confirmed that they would contribute £90,655 towards the cost of disabled adaptations carried out in 2019/20 and 2020/21 on their properties under the DFGs regime. This funding is ring-fenced for disabled adaptations so the DFGs budget was increased by £90,650.

8-21hh 1 of 8  In August 2020, the Emergency Committee approved an increase of £42,530 to the Chipping Community Housing Grant scheme budget from £115,000 to £157,530.

 In November 2020, Policy and Finance Committee approved a budget of £140,840 for the new Clitheroe Affordable Housing Scheme.

2.3As a result of the above, the total approved budget for this Committee’s capital programme of six schemes was £1,446,220. This is shown at Annex 1.

2.4The revised capital programme budget of £1,277,520 for six schemes was then approved by the Special Policy and Finance Committee in February 2021, following a review of progress on all schemes in the capital programme. This included moving £215,340 of budget on two schemes into the 2021/22 financial year. The revised estimate budget is shown at Annex 1. 2.5 During the financial year this Committee has received reports monitoring the progress of schemes within the capital programme.

3 CAPITAL OUTTURN 2020/21

3.1Annex 1 shows this Committee’s capital programme outturn position by scheme, including budget approvals, actual expenditure in-year and requested slippage into 2021/22. The table below summarises the final outturn position.

Budget Total Requested Original Moved Slippage Additional Approved Revised Budget Actual Slippage Estimate from from Approvals Budget Estimate Moved to Expenditure into 2020/21 2019/20 2019/20 2020/21 2020/21 2020/21 2021/22 2020/21 2021/22 £ £ £ £ £ £ £ £ £ 397,000 116,940 658,890 273,390 1,446,220 1,277,520 215,340 679,007 595,170

3.2Actual expenditure on the capital programme was £679,007, which is 53.2% of the revised estimate budget.

3.3Three of the six capital programme schemes were completed in-year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn 2020/21 and Capital Programme Update 2021/22Report 113 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 24 attended
MH
Councillor Mark HindleChair, present
JA
Councillor Jan Alcock JPCommittee Member, present
SA
Councillor Stephen AtkinsonCommittee Member, present
IB
Councillor Ian BrownCommittee Member, present
R(
Councillor Rosemary (Rosie) ElmsCommittee Member, present
SF
Councillor Steve FarmerCommittee Member, present
JH
Councillor Jonathan HillCommittee Member, present
BH
Councillor Brian HoldenVice-Chair, present
AK
Councillor Allan KnoxCommittee Member, expected
GM
Councillor Ged MirfinCommittee Member, present
RN
Councillor Richard NewmarkCommittee Member, present
DO
Councillor Donna O'RourkeCommittee Member, present

All 24 on the meeting page

On this subject at Ribble Valley

Search all
  1. Capital Outturn 2020/21 and Capital Programme Update 2021/22This decision
  2. Capital Outturn 2025/26Approved
  3. Capital Outturn 2025/26Approved
  4. Capital Outturn 2025/26Approved
  5. Capital Outturn 2024/25Approved
  6. Capital Outturn 2024/25Approved

More from Ribble Valley Health and Housing

All decisions
MeetingDecisionOutcome
3 Sep 2026 Dog Control Public Spaces Protection Order 2026RESOLVED THAT COMMITTEE: 1. Having regard to the provisions of Section 60 of the Anti-Social Behaviour, Crime and Pol... Approved Open
3 Sep 2026 Public Health Act Funerals PolicyRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Public Health Act Funerals Policy/Procedure. 2. Permit the H... Approved Open
3 Sep 2026 Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 2 of Part 1 of Schedule 12A of t... Decided Open
4 Jun 2026 Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approve the slippage of £815,630 as set out at paragraph 3.6 of the report. Approved Open
4 Jun 2026 Civil Penalties Under the Renters' Rights Act 2025 and Other Housing LegislationRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Civil Penalties Under the Renters Rights Act 2025 and Other ... Approved Open