Resolved
RESOLVED THAT COMMITTEE: Approve the slippage of £755,668 as set out at paragraph 3.6 of the report.
Health and Housing approved this item on Thursday 5 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT COMMITTEE: Approve the slippage of £755,668 as set out at paragraph 3.6 of the report.
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO HEALTH AND HOUSING COMMITTEE
meeting date: 5 JUNE 2025 title: CAPITAL OUTTURN 2024/25 submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: JEAN WADDINGTON
1 PURPOSE
1.1The purpose of this report is to review the final outturn of the 2024/25 capital programme for this Committee and to seek member approval for the slippage of some capital scheme budgets from the 2024/25 financial year to the 2025/26 financial year.
1.2Relevance to the Council’s ambitions and priorities: • Community Objectives – none identified. • Corporate Priorities - to continue to be a well-managed council providing efficient services based on identified customer need. • Other Considerations – none identified.
2 2024/25 CAPITAL PROGRAMME BACKGROUND
2.1There were 6 capital schemes for this Committee’s original estimate budget, totalling £3,166,080. These were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2024 and March 2024 respectively. This included budget for 3 new/rolling schemes for 2024/25 plus budget for 5 schemes that had been moved from the 2023/24 capital programme.
2.2In addition, at the end of the 2023/24 financial year a total budget of £438,160 covering 6 schemes was unspent and was moved into the 2024/25 capital programme budget, after approval by this Committee in June 2024. This unspent budget that was moved is known as slippage.
2.3Additional budget of £85,930 was approved for the Disabled Facilities Grants Scheme. This was funded by grant monies and therefore had no impact on the Council’s resources.
2.4As a result of the above elements, the total approved budget for this Committee’s 2024/25 capital programme of 8 schemes was £3,690,170.
2.5Later in the year the 2024/25 capital programme budget was revised in respect of these 8 schemes to 7 schemes with a budget of £1,972,780 and was then approved by the Special Policy and Finance Committee in February 2025. This followed a review of progress on all schemes in the capital programme and included moving budget of £1,717,390 on 3 schemes into the 2025/26 financial year. The revised estimate budget is shown at Annex 1.
2.6During the financial year this Committee has received reports monitoring the progress of schemes within the capital programme.
7-25hh 1 of 12 3 CAPITAL OUTTURN 2024/25
3.1Annex 1 shows this Committee’s capital programme outturn position by scheme, including budget approvals, actual expenditure in-year and requested slippage into 2025/26. The table below summarises the final outturn position.
Total Requested Budget Original Slippage Additional Approved Revised Budget Actual Slippage Moved from Estimate from Approvals Budget Estimate Moved to Expenditure into 2023/24 2024/25 2023/24 2024/25 2024/25 2024/25 2025/26 2024/25 2025/26 £ £ £ £ £ £ £ £ £ 513,500 2,652,580 438,160 85,930 3,690,170 1,972,780 1,717,390 1,176,199 755,668
3.2Actual expenditure on this Committee’s capital programme was £1,176,199 which is 59.6% of the revised estimate budget. 3.3 Of the 7 schemes in the revised capital programme 1 was completed in-year. 3.4 The remaining 6 schemes were not completed in-year, resulting in requested slippage from the 2024/25 financial year into the 2025/26 financial year. 3.5 Annex 2 shows details for each scheme of: • the outcomes achieved for schemes that have been completed; and • where schemes have yet to be completed, requests for Committee approval for slippage into the 2025/26 financial year. 3.6 Shown below is a summary of the slippage requests for this Committee: Slippage Cost Scheme Requested Centre £ AHLON Affordable Housing - Longridge 82,730
CLCED Clitheroe Cemetery Drainage Scheme 49,375
DISCP Disabled Facilities Grants 73,417
EQSOS Assisted Purchase Scheme 421,969
FTBGR First Time Buyer Grants 98,177
TEMPH Temporary Housing Scheme 30,000
TOTAL 755,668
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Outturn 2024/25Report | 205 KB | DownloadRead as text |
Follow Health and Housing at Ribble Valley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Dog Control Public Spaces Protection Order 2026RESOLVED THAT COMMITTEE: 1. Having regard to the provisions of Section 60 of the Anti-Social Behaviour, Crime and Pol... | Approved | Open |
| 3 Sep 2026 | Public Health Act Funerals PolicyRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Public Health Act Funerals Policy/Procedure. 2. Permit the H... | Approved | Open |
| 3 Sep 2026 | Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 2 of Part 1 of Schedule 12A of t... | Decided | Open |
| 4 Jun 2026 | Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approve the slippage of £815,630 as set out at paragraph 3.6 of the report. | Approved | Open |
| 4 Jun 2026 | Civil Penalties Under the Renters' Rights Act 2025 and Other Housing LegislationRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Civil Penalties Under the Renters Rights Act 2025 and Other ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.