Capital Outturn 2020/21

Approved Committee 1 paper

Economic Development approved this item on Thursday 17 June 2021. Below is the council's own wording, with the papers it was decided on.

Item82

Resolved

RESOLVED THAT COMMITTEE: Approve the slippage of the following budgets into the 2021/22 capital programme: · Economic Development Initiatives - £15,000 · Gateway Signs for Whalley, Longridge and Clitheroe - £20,000
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Economic Development

DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO ECONOMIC DEVELOPMENT COMMITTEE

meeting date: 17 JUNE 2021 title: CAPITAL OUTTURN 2020/21 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK

1 PURPOSE

1.1To report the 2020/21 capital programme outturn for this Committee and to seek member approval for the slippage of some capital scheme budgets from the 2020/21 financial year to the 2021/22 financial year.

1.2Relevance to the Council’s ambitions and priorities:  Community Objectives – none identified.  Corporate Priorities - to continue to be a well-managed council providing efficient services based on identified customer need.  Other Considerations – none identified.

2 2020/21 CAPITAL PROGRAMME BACKGROUND

2.1One capital scheme for this Committee’s original estimate budget, totalling £81,750, was approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2020 and March 2020 respectively. The scheme budget had been moved from the 2019/20 capital programme to the 2020/21 capital programme.

2.2In addition to the original estimate budget, there was one 2019/20 capital scheme that was not completed by 31 March 2020. The total unspent budget of £20,000 on that scheme, known as slippage, was moved into the 2020/21 capital programme budget after the slippage request from the budget holder was agreed by the Director of Resources.

2.3As a result of the above, the total approved budget for this Committee’s capital programme of two schemes was £101,750. This is shown at Annex 1.

2.4The revised capital programme budget of £35,000 for two schemes was then approved by the Special Policy and Finance Committee in February 2021, following a review of progress on all schemes in the capital programme. This included moving £66,750 of budget on one scheme into the 2021/22 financial year. The revised estimate budget is shown at Annex 1. 2.5 During the financial year this Committee has received reports monitoring the progress of schemes within the capital programme.

3 CAPITAL OUTTURN 2020/21

3.1Annex 1 shows this Committee’s capital programme outturn position by scheme, including budget approvals, actual expenditure in-year and requested slippage into 2021/22. The table overleaf summarises the final outturn position.

7-21ed 1 of 6 Budget Total Original Moved Slippage Approved Revised Budget Actual Requested Estimate from from Budget Estimate Moved to Expenditure Slippage 2020/21 2019/20 2019/20 2020/21 2020/21 2021/22 2020/21 into 2021/22 £ £ £ £ £ £ £ £ 0 81,750 20,000 101,750 35,000 66,750 0 35,000

3.2There was no expenditure on this Committee’s capital programme in 2020/21 and both schemes in the capital programme were not complete at year-end, as follows:

 Economic Development Initiatives (-£15,000): One appropriate scheme for funding from this capital budget, re improving employment land site access at Salthill, was identified as possibly taking place in early 2021. However, the scheme did not take place in 2020/21 because there was no further progress by the landowner before year-end. Slippage of £15,000 into 2021/22 is requested to add to the £66,750 budget already moved to 2021/22 to fund any economic development schemes that would be appropriate to fund from this capital budget in 2021/22.

 Gateway Signs for Whalley, Longridge and Clitheroe (-£20,000): There was no spend in 2020/21 on this scheme because officers are still to obtain permissions from Lancashire County Council to allow installation of the signs. Slippage of £20,000 into 2021/22 is requested to fund the planned installation of the two new welcome signs and replacement of a damaged sign at Simonstone.

4 SLIPPAGE 4.1 Where capital schemes are not complete at year-end and budget is requested to be moved into the next financial year, this is known as slippage. For this Committee slippage of £35,000 is requested into 2021/22 for two schemes:  Economic Development Initiatives, £15,000.  Gateway Signs for Whalley, Longridge and Clitheroe, £20,000.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn 2020/21Report 102 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 20 attended
SH
Councillor Stuart HirstChair, present
RB
Councillor Richard BennettCommittee Member, apologies
DB
Councillor David BerrymanCommittee Member, present
DB
Councillor David BirtwhistleCommittee Member, present
R(
Councillor Robert (Bob) BullerCommittee Member, present
SC
Councillor Stuart CarefootCommittee Member, present
JC
Councillor Judith ClarkCommittee Member, present
LE
Councillor Louise EdgeVice-Chair, present
R(
Councillor Rosemary (Rosie) ElmsCommittee Member, present
SF
Councillor Steve FarmerCommittee Member, present
SF
Councillor Stewart FletcherCommittee Member, present
MF
Councillor Mark FrenchCommittee Member, present

All 20 on the meeting page

On this subject at Ribble Valley

Search all
  1. Capital Outturn 2020/21This decision
  2. Capital Outturn 2025/26Approved
  3. Capital Outturn 2025/26Approved
  4. Capital Outturn 2025/26Approved
  5. Capital Outturn 2024/25Approved
  6. Capital Outturn 2024/25Approved

More from Ribble Valley Economic Development

All decisions
MeetingDecisionOutcome
11 Jun 2026 2026/2027 Climate Change Action PlanRESOLVED THAT COMMITTEE: Approve the 2026/27 Climate Change Action Plan at Appendix 1 of the report for formal adoption. Approved Open
11 Jun 2026 2025/2026 Climate Change Annual ReportRESOLVED THAT COMMITTEE: Note the content of the 2025/2026 Annual Climate Change Report that includes an update on th... Noted Open
11 Jun 2026 Lobbying letter to Government re. Fuel Duty and VATRESOLVED THAT COMMITTEE: Approve the letter at Appendix 1 of the report to use the Council's influence to lobby Gover... Approved Open
11 Jun 2026 Tourism Budget and Service ChangesRESOLVED THAT COMMITTEE: 1. Approve the proposed virement to create a temporary staffing budget. 2. Confirm acceptanc... Approved Open
11 Jun 2026 Appointment to Working GroupsRESOLVED THAT COMMITTEE: Approve the continuation of the Climate Emergency Working Group for 2026/27 municipal year w... Approved Open