RESOLVED THAT COMMITTEE: Approve the slippage of the following budgets into the 2021/22 capital programme – · Dewhurst Road, Langho – resurfacing works - £3,850 · Redesign of Corporate website - £12,000 · Replacement PCs - £10,000 · Financial system upgrade - £8,430 Councillor S Fletcher declared an interest in the next item of business and took no part in the debate or vote.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO POLICY AND FINANCE COMMITTEE
meeting date: 22 JUNE 2021 title: CAPITAL OUTTURN 2020/21 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To report the 2020/21 capital programme outturn for this Committee and to seek member approval for the slippage of some capital scheme budgets from the 2020/21 financial year to the 2021/22 financial year.
1.2Relevance to the Council’s ambitions and priorities: Community Objectives – none identified. Corporate Priorities - to continue to be a well-managed council providing efficient services based on identified customer need. Other Considerations – none identified.
2 2020/21 CAPITAL PROGRAMME BACKGROUND
2.1Four capital schemes for this Committee’s original estimate budget, totalling £204,530, were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2020 and March 2020 respectively. This included two new schemes for 2020/21 and budget for two 2019/20 schemes that had been moved from the 2019/20 capital programme to the 2020/21 capital programme.
2.2In addition to the original estimate budget above, the following budget changes were made:
Four 2019/20 capital schemes were not completed by 31 March 2020 and had unspent budget available at that date. Unspent budget of £33,480 on those schemes, known as slippage, was moved into the 2020/21 capital programme budget, after slippage requests from the budget holders were agreed by the Director of Resources.
In August 2020, the Emergency Committee approved a new scheme budget of £25,000 for the Purchase of land behind Old Row, Barrow. This was added to this Committee’s capital programme.
2.3As a result of the above, the total approved budget for this Committee’s capital programme of eight schemes was £263,010. This is shown at Annex 1
2.4The revised capital programme budget of £158,310 for seven schemes was then approved by the Special Policy and Finance Committee in February 2021, following a review of progress on all schemes in the capital programme. This included moving £105,510 of budget on four schemes into the 2021/22 financial year. The revised estimate budget is shown at Annex 1. 2.5 During the financial year this Committee has received reports monitoring the progress of schemes within the capital programme.
33-21pf 1 of 8 3 CAPITAL OUTTURN 2020/21
3.1Annex 1 shows this Committee’s capital programme outturn position by scheme, including budget approvals, actual expenditure in-year and requested slippage into 2021/22. The table below summarises the final outturn position.
Budget Total Requested Original Moved Slippage Additional Approved Revised Budget Actual Slippage Estimate from from Approvals Budget Estimate Moved to Expenditure into 2020/21 2019/20 2019/20 2020/21 2020/21 2020/21 2021/22 2020/21 2021/22 £ £ £ £ £ £ £ £ £ 95,800 108,730 33,480 25,000 263,010 158,310 105,510 124,022 34,280
3.2Actual expenditure on this Committee’s capital programme was £124,022, which is 78.3% of the revised estimate budget.
3.3Three of the seven capital programme schemes were completed in-year.
3.4Four schemes were not completed in-year, as follows:
Dewhurst Road, Langho – Resurfacing Works (-£3,850): At revised estimate stage, this Committee approved an additional pre-tender works budget of £10,100 for this scheme in 2020/21. Initial pre-tender works were completed in-year, totalling £6,250. The second stage of pre-tender works received approval in mid- February 2021, but works by third parties needed to be completed before placing orders with specialist contractors to complete the investigation works. Slippage of £3,850 into 2021/22 is requested to cover the cost of the remaining pre-tender investigation works, now that the works by third parties have been completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.