RESOLVED THAT COMMITTEE: 1. Approve the 2021/22 revised estimate of £50,000 for this committee’s capital programme as set out, and 2. Approve the transfer of £51,750 of the Economic Development Initiatives capital budget from 2021/22 to 2022/23.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
RIBBLE VALLEY BOROUGH COUNCIL DECISION REPORT TO ECONOMIC DEVELOPMENT COMMITTEE
meeting date: 20 JANUARY 2022 title: REVISED CAPITAL PROGRAMME 2021/22 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To approve the 2021/22 revised estimate for this Committee’s capital programme.
1.2Relevance to the Council’s ambitions and priorities:
• Community Objectives – none identified.
• Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs.
• Other Considerations – none identified.
2 2021/22 CAPITAL PROGRAMME BACKGROUND
2.1One capital scheme for this Committee’s original estimate budget, totalling £66,750, was approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2021 and March 2021 respectively. The scheme budget had been moved from the 2020/21 capital programme to the 2021/22 capital programme.
2.2In addition to the original estimate budget, two 2020/21 capital schemes were not completed by 31 March 2021 and had unspent budget available at that date. The total unspent budget of £35,000 on those schemes, known as slippage, was moved into the 2021/22 capital programme budget, after approval by this Committee in June 2021.
2.3As a result of the above, the total approved budget for this Committee’s capital programme of two schemes was £101,750. This is shown at Annex 1.
3 REVISING THE 2021/22 CAPITAL PROGRAMME
3.1We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect their progress and estimated full year expenditure. Following this review, the proposed revised estimate is £50,000 for two schemes, a reduction of £51,750 from the total approved budget.
3.2The reduction relates to the Economic Development Initiatives scheme, which had a previously approved budget of £81,750. £30,000 of this budget has previously been set aside for land appraisal work on a piece of land along the A59. At this stage, there are no other development opportunities being considered that are likely to lead to further spend on this capital budget in 2021/22. Given this, it is proposed that the 2021/22 revised estimate for this scheme is reduced to £30,000 and that £51,750 of the scheme budget is moved to 2022/23.
03-22ed 1 of 4 3.3 Annex 1 shows the full capital programme by scheme, including the budget and expenditure to date. The summary position is shown below.
Actual Expenditure Total including Original Budget Slippage Approved Revised Budget commitments Estimate Moved from from Budget Estimate Moved to as at end of 2021/22 2020/21 2020/21 2021/22 2021/22 2022/23 December 2021 £ £ £ £ £ £ £ 0 66,750 35,000 101,750 50,000 51,750 7,950
3.4At the end of December 2021 £7,950 had been spent or committed. This is 15.9% of the revised capital programme budget for this Committee.
3.5Progress on the two schemes in this Committee’s capital programme is as follows:
• Economic Development Initiatives (£30,000 budget remaining): Consultants have now been engaged to undertake the land appraisal work on the piece of land along the A59 and it is expected that their work will be reported to officers by the last week of March 2022.
• Gateway Signs for Whalley, Longridge and Clitheroe (£12,050 budget remaining): The supply and installation of the two new welcome signs is being undertaken by Lancashire County Council. The work was ordered and an initial payment was made in Autumn 2021. It is currently expected that the work will be completed before financial year-end, but we are currently waiting for LCC to confirm the actual installation dates.
4 RISK ASSESSMENT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/2027 Climate Change Action PlanRESOLVED THAT COMMITTEE: Approve the 2026/27 Climate Change Action Plan at Appendix 1 of the report for formal adoption.
2025/2026 Climate Change Annual ReportRESOLVED THAT COMMITTEE: Note the content of the 2025/2026 Annual Climate Change Report that includes an update on th...
Tourism Budget and Service ChangesRESOLVED THAT COMMITTEE: 1. Approve the proposed virement to create a temporary staffing budget. 2. Confirm acceptanc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.